July 22 2002 C. Stephen Allred, Director
Roger Greaves, PE
Forsgren Associates Inc.
350 N. 2nd E.
PO. Box 549
Rexburg,ID 83440
Re: Celestial Village Phase 1 Housing Complex, Rexburg DEQ M 02-10-33
Dear Mr. Greaves
We have reviewed the plans and specifications for the proposed water, sewer and storm drain design. The project
plans and specifications appear to meet State standards and are hereby approved with the following condition:
1. A will serve letter from the City of Rexburg Will be Required.
It is also our understanding that the storm drain piping will be connected to the proposed City system
where a detention pond and a lift station will be utilized. Per our phone conversation this will be a
separate project proposed by the City.
Our approval is for the design. We will give final project approval after the systems are constructed. Deviations
from the approved design that might result in violations of Idaho Regulations must be reviewed by this office before
field installation. This office must be kept informed of the scheduling of all construction phases so that we can make
spot inspections as necessary.
This approval will expire July 22, 2003. If construction is not complete by the expiration date, plans will need to
be resubmitted for approval before further construction proceeds. Within 30 days after construction, a professional
engineer registered in the State of Idaho must provide this office with as -built plans, or a letter of certification stating
that the project was installed substantially according to the approved design.
A copy of the approved design and specifications will be kept on file at this office. Please reference DEQ No. 02-
10-33 when submitting any future correspondence related to this project. If you have any questions regarding this
letter or if we can be of further assistance, please call me at (208) 528-2650.
Sincerely,
iiillita-mTeus er PE
Water Quality Engineer
02-10-33 CELESTIAL VILLAGE PHASE 1, HOUSING COMPLEX.DOC
Cc: John Millar, City of Rexburg
Richard Horne, Rich Bly, D7HD IF
Craig Hammond, State Plumbing Inspector, PO Box 506 Ashton, ID 83420
Plan File
Read file
02-10-33 CELESTIAL VILLAGE PHASE 1, HOUSING COMPLEX.DOC