November 9, 2021
Electrical Narrative
E1.1 – EMT or MC cable assumed in concealed locations. If not accurate please verify.
Response: EMT called out on drawing.
E1.2 – Photometric Plan added to set
E3.1 – Available Fault Current calculations.
Response: Fault current calcs added to one-line diagram.
E6.1 – All wiring must meet 2017 NEC standards.
Response: Note added to specifications.
Plumbing Narrative
P1.0 – WH-2 added to electric water heater schedule.
Structural Narrative
S0.1 – Minimum Frost Depth Ground Surface to Bottom of Footing 36"
Response: See Foundations General Note B.3 on S0.1 for required footing frost depth.
S1.1 – Stamp needs to be from an Idaho licensed Engineer.
Response: Drawings updated with required seal.
S1.1 – 36 " frost depth for footing depth.
Response: See Foundations General Note B.3 on S0.1 for required footing frost depth.
Owner Requested Change REV 2:
S1.1 – Updated Structural Foundations from CMU to Concrete
S1.2 – Updated Structural Sections showing Concrete in lieu of CMU stem walls
Plumbing – Hand Sink model changed to T2703