HomeMy WebLinkAboutIDT Exit 322 Required Excavation for Fiber Facilities Relocation November 171 of 3
IDT Exit 322 Required Excavation for Fiber Facilities Relocation November 17, 2023 Revision
1) Plow ~580 ft at 36” depth to existing Hand
Hole (HH) West of On Ramp
a. Place (1) 1.25” and (1) 7 Way Ducts
2) Bore (B) (2) 15 ft each canal crossings at 3’
below canal bottom, ~7’ below grade.
1) Set (1) 36”x36”x 36”HH at Lat: 43.804382° Long: -111.816657°
2) Remove Existing HH at Lat: 43.804391° Long: -111.816105°
1) Set (1) 36”x36”x 36” HH at Lat: 43.804317° Long: -
111.811825° over existing fiber.
2) Bore to existing Hand Hole (HH) East of Off Ramp.
a. Place (1) 1.25” and (1) 7 Way Ducts
1) Bore under culvert from existing HH to existing HH.
2) Place (2) 1.25” and (1) 7 Way Ducts
3) Place Existing SSC 144 fiber into Rexburg HH
Dig existing SSC 144 fiber into existing
RXBG HH (2) locations. Leave 50’ tails.
2 of 3
Abandoned Rexburg Fiber Map
Abandon ~750 ft of 1.25” Duct and 7 Way Duct.
Abandon `~1800 ft of 432 count fiber.
Abandoned Duct is in Red.
Abandoned fiber from arrow to arrow.
3 of 3
Abandoned Silver Star Fiber Map
Abandon ~1015 ft of 1.25” duct and 144 count fiber.
Abandoned Duct/Fiber is in Red.
Abandon HH at intersection of Off Ramp and University Blvd