HomeMy WebLinkAbouttesting exemption_Sterling Medical DEVIATION APPROVAL
2295 N. Yellowstone Hwy. Suite #6
Idaho Falls, Idaho 83401
208.881.0081 Page 1 of 1
Specific Deviation:
Mandrel testing on internal, site specifc, Storm Water Infrastructure
Key Reasons for Approval:
1. Infrastructure in question is privately operated & maintained.
2. Several components serve as infiltration and only have a single means of access.
3. Other compents are outfitted with landscape catch basins to accommodate surface water and will not
support the mandel apparatus.
At the request of the developer, Venture Builders, Connect Engineering, serving as the “Engineer of Record”,
approves the request to forgo the mandrel testing on all internal, site-specific, privately held storm drain
infrastructure. And in doing so, Connect Engineering is released from all liability resulting from any and all
future issues or concerns as they pertain to the internal, site-specific, privately held storm drain infrastructure.
_____________________________________________
Scott Page, Venture Builders
_____________________________________________
Blake Jolley, P.E, Connect Engineering
PROJECT: Sterling Medical DATE: 6.18.24
CONTRACTOR: Venture Builders JOB NO. 23-052
DocuSign Envelope ID: 0EB77DF9-67F2-43E0-9C23-16B28CC85065