HomeMy WebLinkAboutPrevail PresentationPowerPoint Presentation Rexburg City Council Meeting Rexburg Municipal Fiber January 2024   City Council Approval  March 30, 2022  Constuction Start  April 4, 2022 Project Estimation  $3,165,391.28 Construction End  Nov. 23, 2023 ONE CONNECTION AT A TIME Fiber Placed- 123,140 ft Vaults Placed- 235 Solid Rock Bore 8,330 ft 31 City Facilites Connected   ONE CONNECTION AT A TIME ONE CONNECTION AT A TIME Financial Breakdown Estimated Budget $3,165,391.28 Actual Cost $3,039,850.31 Total Savings $125,540.96 ONE CONNECTION AT A TIME