HomeMy WebLinkAboutReconnect7thSouthStreet-6Emergency Reconnection of
7th South St. in Rexburg!
(also known as 1000 South in the county)
The only east and west route that goes all the way through Rexburg.
09/19/2023 jws
The Challenge
of
Rexburg’s Growth
The city long
expected growth
to be on the east
side of town,
toward Sugar City.
The Challenge
of
Rexburg’s Growth
So, they started
planning for
more traffic on
the east side.
The Challenge
of
Rexburg’s Growth
The plan was called
the
“East Parkway
Corridor.”
The Challenge
of
Rexburg’s Growth
But the corridor
went right through
the Crest Haven
residential
neighborhood.
The Challenge
of
Rexburg’s Growth
The “Crest Haven
Neighborhood”
objected!
The Challenge
of
Rexburg’s Growth
Never-the-less, the
city focused on
engineering and
grant funding for
that project.
City Transportation Plan
City Transportation Plan
$2,350,000
$2,500,000
$6,000,000
The Challenge
of
Rexburg’s Growth
But city
growth went west,
not east.
The Challenge
of
Rexburg’s Growth
While the city
focused on getting
an access route to
the
“East Corridor”...
The Challenge
of
Rexburg’s Growth
12th West
Corridor …they ignored
blocked access
routes to the
“West Corridor.”
US Highway 20
blocks
access routes
into growth areas
along the 12th West
Corridor!
12th West
Corridor
The Challenge
of
Rexburg’s Growth
12th West
Area of most concern
12th West
The Burma Road
12th West
1000 South Street 7th South Street
Summerfield Planned
Community Under Construction
The Burma Road
Looking West
New Burton Elementary School
Looking East
Looking West
down 7th South
12th West
1000 South Street 7th South Street
To the Temple:
2 Miles
3 Miles
4 miles
BUT !
Looking East
Temple
US Highway 20
US 20 construction cut 7th South Street, blocking east/west traffic.
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
Blockage denies city traffic an alternate route into and out of the growth area.
Rapid residential growth on the
west side of Rexburg requires
more traffic options.
(e.g. Summerfield development)
Summerfield Planned Community
is under relentless construction!
(Dark gray lots are yet empty)
Home construction on the west side of Rexburg
The sound of hammers and nail guns constantly ring through our neighborhood.
Rexburg Idaho Married Student 4th Stake (11 Wards meet in this large building)
454 S 12th W, Rexburg
Plus, there are major
public facilities now on
the west side of Rexburg
Rexburg Idaho West Stake Center (3 Wards)
210 S 12th W, Rexburg
New Burton Elementary School
Madison Senior High
School Campus
Stadium
Field House
Performing Arts Center
Madison Senior High
School Campus
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
For all that traffic growth, there are only two ways across the freeway
Solution to this urgent problem?
Build a simple
overpass on US 20
so 7th South can
be reconnected.
No on/off ramps needed!
No on/off ramps!
Taking US 20 traffic over 7th South protects its design for tall loads.
Protects streets and driveways that open onto 7th South Street.
1000 South Street 7th South Street
Benefit: A needed alternate route for east/west traffic in Rexburg
1000 South Street 7th South Street
Benefit: Reduced traffic on the 12th West Corridor
1000 South Street 7th South Street
12th West
University Boulevard
Benefit: Reduced traffic on Main Street and University Boulevard
Main Street
1000 South Street 7th South Street
Benefit: A direct connection to the future East Parkway Corridor
1000 South Street 7th South Street
Benefit: Reduced conflict with the Crest Haven Neighborhood
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
BUT what if those freeway interchanges were blocked or closed?
Remember the coming
“Diverging Diamond”
Interchange Construction?
Closed!
(Main Street)
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
First close University Boulevard, sending all traffic to Main Street.
Closed!(Main Street)
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
…then close Main Street, sending all traffic, plus Hwy 33 traffic to University Boulevard
Hwy 33
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
BUT putting that whole volume of traffic through a single route
across the freeway is dangerous!
Hwy 33
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
…and what happens if that single route gets blocked someway?
(For example, a serious accident caused by confusion over how to navigate the new diverging diamond interchange.)
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
Then we are stranded with no access to the east side!
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
A “safety valve” is needed to prevent a possible disaster!
1000 South Street 7th South Street
12th West
Main Street
University Boulevard
7th South should be reconnected BEFORE construction of the “Diverging Diamond” Interchanges!
Reconnecting 7th South Street
Now becomes
an emergency
for the safety of people stranded
on the west side of the freeway!
It would be worth another year’s delay of the
diverging diamond interchanges to get the
safety valve of a reconnected 7th South Street
and prevent a possible traffic disaster.
Where can we find the will and the
emergency funding to reconnect
7th South Street in a year?
“The [East Parkway] project [is] at least a decade out and would
only begin when population and traffic demands dictated it.”
Transportation Plan Budget
for East Parkway Corridor
Postponed
East Parkway
Corridor
$10,850,000 +
August 16, 2023:
The Idaho Transportation Department
announced an unrestricted, no-match-
required, $2 million grant opportunity to
help Rexburg solve its traffic problems.
$2,000,000 Grant just received:
Get started now by reallocating money in the existing budget to
Reconnect 7th South Street:
IDOT Unrestricted Grant $ 2,000,000
Postponed East Parkway Corridor budget $10,850,000
TOTAL $12,850,000
Then get other funding such as:
“Potential funding sources include grants, donations, general fund,
impact fees and revenue allocation funds.”
Federal Grants: “Reconnecting Communities and Neighborhoods Grant Program”
https://www.transportation.gov/grants/rcnprogram
“Reconnecting communities by removing, retrofitting, or mitigating highways or other transportation facilities
that create barriers to community connectivity, including to mobility, access, or economic development.”
“Potential funding sources include grants, donations, general fund, impact
fees and revenue allocation funds.”
Federal Grants: “Reconnecting Communities and Neighborhoods Grant Program”
https://www.transportation.gov/grants/rcnprogram
“Reconnecting communities by removing, retrofitting, or mitigating highways or other transportation facilities
that create barriers to community connectivity, including to mobility, access, or economic development.”
State Grants: (ITD assess available funds to handle emergency construction)
“Potential funding sources include grants, donations, general fund, impact
fees and revenue allocation funds.”
Federal Grants: “Reconnecting Communities and Neighborhoods Grant Program”
https://www.transportation.gov/grants/rcnprogram
“Reconnecting communities by removing, retrofitting, or mitigating highways or other transportation facilities
that create barriers to community connectivity, including to mobility, access, or economic development.”
State Grants: (IDT assess available funds to handle emergency construction)
City General Funds:
City Impact Fees:
City Revenue Allocation Funds:
The University Boulevard-South 12th West Urban Renewal District
Reconnect 7th
South Project East Parkway
Corridor Project
Both projects are in the same Rexburg Urban Renewal District,
(The University Boulevard-South 12th West District)
No on/off ramps!
We need to find the will and the emergency funding to avoid a disaster !
No on/off ramps!
Reconnect 7th South BEFORE Building the Converging Diamond Interchanges!
END