HomeMy WebLinkAboutCONCRETE FIELD TEST 4 - 23-00332 - Madison Jr High - AdditionPRIVILEGED AND CONFIDENTIAL: This document and the information contained herein are confidential and protected from disclosure. This message and its
content is intended only for the use of the addressee(s) and may contain sensitive, confidential information. If you are not the intended recipient, you are hereby
notified that the use, dissemination, or copying of this information is strictly prohibited, please notify the sender immediately.
8BC0B0FC-09D1-4D5D-82A2-019A95E72502 1
4103 E 605 N Suite 1
Rigby, ID 83442
208.932.4428
File Name:
23252C08182023LS
Compressive Strength of Concrete Test Specimens
Date:
08/18/2023
Project Number:
23-252
Project Name:
Madison JR. High
Client:
Madison School District
Time on Project:
3 hours
Start Time:
09:30 AM
Contractor:
Richardson Concrete
Supplier:
Valley Ready Mix
Mix Number:
MIX96AF
Concrete Member:
Foundation Walls
Required 28 day Strength (psi):
4,500.0
Admixtures:
POLY1025, 322-N, MICROAIR
Entrained Air Spec. (%):
5.5 +- 1.0
Slump Spec. (inches):
Max 6
Results
Testing:
Set #:Cumulative
Test
Load
Amount:
Ticket
#:
Time
Tested:
Test Location:Ambient
Temp.
(°F):
Weight
of
Concrete
(lbs):
Unit
Weight
(PCF):
Concrete
Temp.
(°F):
Entrained
Air
(%):
Slump
(in):
1 9.5 2022 10:00
AM
Foundation walls on north east
corner
82 34.220 137.4 71 6.5 5 1/2
Field Technician Information
Truck:
THOR
Total Trip Mileage:
0.00
Tested By:
Leland Steiner
Signature:
Items observed are in general conformance with approved project documents and jurisdictional requirements.
PRIVILEGED AND CONFIDENTIAL: This document and the information contained herein are confidential and protected from disclosure. This message and its
content is intended only for the use of the addressee(s) and may contain sensitive, confidential information. If you are not the intended recipient, you are hereby
notified that the use, dissemination, or copying of this information is strictly prohibited, please notify the sender immediately.
8BC0B0FC-09D1-4D5D-82A2-019A95E72502 2
Items observed are NOT in general conformance with approved project documents and jurisdictional requirements.
(Explanation to be given in Observations and/or Remarks.)
Observations and/or Remarks:
I arrived on site at around 9:30am and began my inspection of the forms for the foundation walls. I then set up
my gear and prepared for concrete to arrive. Concrete arrived on time at around 10:00am. After a yard was let
off the truck, I grabbed a sample and began testing. The first field test failed so I stopped the pour, grabbed a
new airpot and tested the same sample again, in which the concrete passed in my field testing. After the field
tests were passed, the concrete pour was resumed. I then cleaned my gear and waited in case I needed to test
again.
Reviewed By:
E. Vail
Signature:
Inspection Images:
Testing:
PRIVILEGED AND CONFIDENTIAL: This document and the information contained herein are confidential and protected from disclosure. This message and its
content is intended only for the use of the addressee(s) and may contain sensitive, confidential information. If you are not the intended recipient, you are hereby
notified that the use, dissemination, or copying of this information is strictly prohibited, please notify the sender immediately.
8BC0B0FC-09D1-4D5D-82A2-019A95E72502 3
Ticket Image: