HomeMy WebLinkAboutSOIL DENSITY TEST 4 - 23-00332 - Madison Jr High - AdditionFile Name:
23252D08102023JPC
PRIVILEGED AND CONFIDENTIAL: This document and the information contained herein are confidential and protected from disclosure. This message and its
content is intended only for the use of the addressee(s) and may contain sensitive, confidential information. If you are not the intended recipient, you are hereby
notified that the use, dissemination, or copying of this information is strictly prohibited, please notify the sender immediately.
1fbaea54224c7895-1691699135287 1
4103 E. 605 N. Suite 1
Rigby ID, 83442
208.932.4428
In Place Density of Soils ASTM D2922 & D3017
Project Number:
23-252
Project Name:
Madison JR. High
Contractor:
Hill and Son
Client:
Madison School District
Date:
08/10/2023
Time Start:
02:00 PM
Instrument ID
10483
Daily Standardization:
MS:
798
DS:
1536
Current Weather Conditions:
Partly Cloudy
Ambient Temperature (°F):
80
Wind:
5-15 mph
Details
Test #:Location:Elevation: Depth:Wet:Dry:% M:Proctor #:% Proctor:Pass Fail
1 Interior footing
East addition
Bottom
of
footings
8 129.2 127.5 1.8 134.3
Material Type
Pit Run
95
2 Interior footings
East addition
Bottom
of footing
10 130.3 127.3 4.8 134.3
Material Type
Pit Run
95
3 Interior footings
East addition
Bottom
of
footings
10 130.2 127.5 2.1 134.3
Material Type
Pit Run
95
4 Interior
footings
East addition
Bottom
of
footings
10 132.1 129.8 1.8 134.3
Material Type
Pit Run
97
5 Exterior footings
East addition
Bottom
of
footings
10 130.1 127.4 2.1 134.3
Material Type
Pit Run
95
6 Exterior footings
East addition
Bottom
of
footings
10 131.9 129.4 1.9 134.3
Material Type
Pit Run
96
Observations/Remarks:
File Name:
23252D08102023JPC
PRIVILEGED AND CONFIDENTIAL: This document and the information contained herein are confidential and protected from disclosure. This message and its
content is intended only for the use of the addressee(s) and may contain sensitive, confidential information. If you are not the intended recipient, you are hereby
notified that the use, dissemination, or copying of this information is strictly prohibited, please notify the sender immediately.
1fbaea54224c7895-1691699135287 2
I arrived on site and met with Truman (Headwaters Construction) he informed me of the locations that they
needed density testing on. I standardized my gauge and began testing the interior footings and exterior footings.
Although the material was dry, due to it having been placed 3 weeks ago, passing density tests were obtained
and reported. I notified the contractor of my observations and test results prior to leaving.
Tested By:
Jacob Christensen
Signature:
Reviewed By:
E. Vail
Signature:
Date:
08/10/2023
Inspection Images: