July 11, 2023
Proposed plan for temporary power at Teton River Lofts:
With permission from Rocky Mountain Power we are hoping to find a temporary option to get power to
(2) 24-plex buildings. The meter packs have been installed but we are waiting on the main breaker
disconnects to energize each building. The disconnects have been on order for well over a year and have
now been pushed to October.
We are proposing that we use, temporarily, a Square D fused disconnect (Square D H367NR) in junction
with the Square D meter packs already installed. We have gone through the process by which we will
marry the two with our local inspector, Brett Stoddard, as well as the project engineer. Both of whom
agree that this disconnect will suffice as a temporary solution.
Once the original disconnects are delivered, we will work with Byron to coordinate outages to swap out
the fused disconnects with the breaker disconnects and with Alex to get them re-inspected. As long as
the new shipping date holds true, we will have everything set right by the end of October.
Thank you for your consideration,
Nephi’s Electric, LLC
Approved by:
Todd Payne, Electrical Engineer
Brett Stoddard, City of Rexburg Electrical Inspector