HomeMy WebLinkAboutGENERAL SERVICE CONTRACT - 23-00093 - Liberty GMC - Electrical(ID Sep2022)
Account #:81219282
Service ID #:121873612
Monthly
GENERAL SERVICE CONTRACT
(1000 KVA OR LESS)
between
ROCKY MOUNTAIN POWER
and
LIBERTY GMC
HL
C/C: 11471
Request #: 7016583
Contract #:
This General Service Contract ("Contract"), dated February 28, 2023, is between Rocky Mountain
Power, an unincorporated division of PacifiCorp ("Company"), and Liberty GMC ("Customer"), for
electric service for Customer's commercial operation at or near 890 W Main St, Rexburg, Idaho.
Company's filed tariffs (the "Electric Service Schedules" and the "Electric Service Regulations") and
the rules of the Idaho Public Utilities Commission ("Commission"), as they may be amended from
time to time, regulate this Contract and are incorporated in this Contract. In the event of any conflict
between this Contract and the Electric Service Schedules or the Electric Service Regulations, such
schedule and rules shall control. They are available for review at Customer's request.
1. Delivery of Power. Company will provide 277/480 volt, three-phase electric service to the
Customer facilities.
2. Contract Demand. The demand in kVA that Customer requires to meet its load
requirement and Company agrees to supply and have available for delivery to Customer,
shall be 80 kVA (diversified, based on Customer's submitted load prior to the signing of this
Contract)(the "Contract Demand").
After 36 months of service the Company may reduce Contract Demand to the maximum
recorded and billed demand in the previous 36 months. The reduction in Contract Demand
shall become effective thirty (30) days after the Company provides notice.
Within fifteen (15) days of Customer's written request for capacity above the Contract
Demand, Company shall advise Customer in writing whether the additional power and
energy is currently available, or if not currently available, initiate the processes to determine
the costs to make it available.
3. Extension Costs. Company agrees to invest $8,038.56 (the "Extension Allowance") to fund
a portion of the cost of the improvements (the "Improvements") as per tariff. Customer
agrees to pay Company the estimated construction costs in excess of the Extension
Allowance ("Customer Advance"). Customer has paid for engineering, design, or other
advance payment for Company's facilities in the amount of $0.00, which amount is reflected
in the balance due in the Customer selected option below. Customer trenching, conduit,
vault and/or right-of-way ("TCVR"), when provided for Company lines and equipment, may
also be subject to refund as calculated using Company standard costs. (Customer must
initial selected option on the blank space at the beginning of the option and pay the balance
due given in that option.)
1 of 5
Refund Option. The total Customer Advance for this work is $7,910.44, the
balance due is $7,910.44, and Customer remains eligible for refunds. Company
will refund part of the Customer Advance if additional customers connect to the
Improvements within sixty (60) months of the date Company is ready to supply
service. Company will refund a proportional share of the refundable Customer
Advance allocable to the shared Improvements for four (4) additional applicants.
Company will try to inform Customer when a refund is due. However, in the event
Company is unable to locate Customer or has not identified that a refund is due
Customer is responsible for requesting a refund within twenty-four (24) months
of the additional applicant connecting to the Improvements.
Contract Administration Credit Option. Customer chooses to receive a Contract
Administration Credit of $250 and waives their right to refunds should additional
applicants connect to the Improvements. Accordingly, the balance due is
$7,660.44.
4. Contract Minimum Billing. Customer agrees to pay a contract minimum billing (the
"Contract Minimum Billing") during the first sixty (60) months beginning from the date
Company is ready to supply service. The Contract Minimum Billing shall be the greater of:
(1) the Customer's monthly bill; or, (2) $120.13 (the monthly facilities charge) plus
eighty percent (80%) of the Customer's monthly bill. Billings will be based on Rate
Schedule No. 23 and superseding schedules. Company will reduce the minimum charges
by the amount of the facilities charges associated with refunds due from additional
applicants connecting to the Improvements.
5. Effective. This Contract will expire unless Customer signs and returns an original of this
Contract along with any required payment to Company within ninety (90) days of the Contract
date shown on page 1 of this Contract.
6. Contract Minimum Billing Term and Termination. This Contract becomes binding when
both Company and Customer have signed it, and will remain in effect for five (5) years
following the date when Company is ready to supply service (the "Term").
Following execution of Contract but prior to completion of installation of. Company's__
Improvements, Customer may terminate Contract by notifying Company of their intent to not
take service. If Customer is not ready to receive service from Company within one -hundred
fifty (150) days of the date Customer signs this Contract, then Company may terminate this
Contract. Upon Customer or Company termination of Contract, Customer shall pay
Company costs incurred for design, permitting, surveying, cancelation orders,
Improvements installed and other associated Contract costs. Customer's Advance, if any,
will be applied to costs incurred, and Customer will promptly pay Company any costs in
excess of the Advance upon receipt of notice. If the Advance exceeds the costs incurred,
Company will promptly refund the portion of the Advance in excess of costs incurred.
However, if Company has completed installation of Improvements and does not terminate
Contract, Customer shall be responsible for paying the Contract Minimum Billing for the full
Term irrespective of Customer taking, not taking, or terminating service.
7. Customer Obligations. Customer agrees to:
2 of 5
a) Provide legal rights-of-way to Company, at no cost to Company, using Company's
standard forms. This includes rights-of-way on Customer's property and/or third party
property and any permits, fees, etc. required to cross public lands;
b) Prepare the route to Company's specifications;
c) Install all Customer provided trench, conduit, equipment foundations, or excavations
for equipment foundations within the legal rights -of -ways;
d) Repair, or pay for the repair of, any damage to Company's facilities except damage
caused by the negligence of Company; and,
e) Comply with all of Company's tariffs, procedures, specifications and requirements.
8. Special Provisions: The customer shall provide a trench from the existing transformer to the
new transformers location at a depth of 40" and a width of 12" and a trench from the
transformer to the meter base location 30" deep and 12" wide. The customer shall install the
flat concrete pad for the transformer base that meets the power company's requirements. The
customer shall install only 4" schedule 40 electrical grade PVC conduit for both runs of conduit
and use only 36" long sweep 90° elbows. The primary run of conduit shall have fiberglass
long sweep elbows. The customer shall install a 1,000 Ib pull string through each run of
conduit and have 6' of string excess on both ends. The customer shall install a EUSERC
approved safety socket meter base with an electrical inspection and permit number. The
transformer base is required to have 6" of 3/d' minus compacted backfill under each location.
9. Underground Facilities. If service is provided by an underground line extension, Customer
will provide, or Company will provide at Customer's expense: all trenching and backfilling,
imported backfill material, conduit and duct, and furnish and install all equipment
foundations, as designed by Company. Company may abandon in place any underground
cables installed under this Contract that are no longer useful to Company.
Customer warrants that all Customer provided trench and excavations for equipment
foundations, and Customer installed conduit and equipment foundations are installed within
legal rights-of-way, and conform to the specifications in Company's Electric Service
Requirements Manual, and other specifications as otherwise provided by Company. In the
event Customer fails to comply with the foregoing, Customer shall be liable for the cost to
Company for relocating the facilities within a legal right-of-way, acquiring right-of-way for
Company facilities, repair or replacement of improperly installed conduit or foundations, and
paying costs for damages that may arise to any third party as a result of Company facilities
being located outside of a legal right-of-way. The provisions of this paragraph 9 shall survive
the termination of this Contract.
10. Design, Construction, Ownership and Operation. Company shall design, construct,
install, and operate the Improvements in accordance with Company's standards. Company
will own the Improvements, together with Company's existing electric utility facilities that
serve or will serve Customer. Construction of the Improvements shall not begin until (1) both
Company and Customer have executed (signed) this Contract, and (2) all other
requirements prior to construction have been fulfilled, such as permits, payments received,
inspection, etc. Any delays by the Customer concerning site preparation and right-of-way
acquisition or trenching, inspection, permits, etc. may correspondingly delay completion of
the Improvements.
Company warrants that its work in constructing and maintaining the Improvements shall be
consistent with prudent utility practices. COMPANY DISCLAIMS ALL OTHER
3 of 5
WARRANTIES, EXPRESS OR IMPLIED, INCLUDING BUT NOT LIMITED TO THE
WARRANTY OF MERCHANTABILITY, FITNESS FOR PARTICULAR PURPOSE, AND
SIMILAR WARRANTIES. Company's liability for breach of warranty, defects in the
Improvements, or installation of the Improvements shall be limited to repair or replacement
of any non-operating or defective portion of the Improvements or Company's other electric
utility facilities. Under no circumstances shall Company be liable for other economic losses,
including but not limited to consequential damages. Company shall not be subject to any
liability or damages for inability to provide service to the extent that such failure shall be due
to causes beyond the reasonable control of Company.
No other party, including Customer, shall have the right to operate or maintain Company's
electric utility facilities or the Improvements. Customer shall not have physical access to
Company's electric utility facilities or the Improvements and shall engage in no activities on
or related to Company's electric utility facilities or the Improvements.
11, Payments. All bills shall be paid by the date specified on the bill, and late charges shall be
imposed upon any delinquent amounts. Company reserves the right to require customer
payments be sent by EDI or wire transfer. If Customer disputes any portion of Customer's
bill, Customer shall pay the total bill and shall designate the disputed portion. Company
shall decide the dispute within sixty (60) days after Customer's notice of dispute. Any refund
Company determines Customer is due shall bear interest at the rate then specified by the
Commission or, if no rate is specified, the then effective prime rate as quoted in The Wall
Street Journal.
Company may request deposits from Customer to the extent permitted under the applicable
Electric Service Regulations and the applicable Electric Service Schedule. In the event of a
default by Customer in any of its obligations, Company may exercise any or all of its rights
and remedies with respect to any such deposits.
12. Furnishing Information and Deposits. Customer represents that all information it has
furnished or shall furnish to Company in connection with this Contract shall be accurate and
complete in all material respects. Company will base its decision with respect to credit,
deposits, allowances or any other material matter on information furnished under this
section by Customer. Should such information be inaccurate or incomplete, Company shall
have the right to revoke or modify this Contract and/or its decision to reflect the
determination Company would have made had Company received accurate and complete
information. Company may request deposits, for the purpose of guaranteeing payment of
electric service bills, as permitted under the Company's Idaho Electric Service Regulation
No. 9.
13. Governing Law; Venue. All provisions of this Contract and the rights and obligations of
the parties hereto shall in all cases be governed by and construed in accordance with the
laws of the State of Idaho applicable to contracts executed in and to be wholly performed in
Idaho by persons domiciled in the State of Idaho. Each party hereto agrees that any suit,
action or proceeding in connection with this Contract may only be brought before the
Commission, the Federal courts located within the State of Idaho, or state courts of the State
of Idaho, and each party hereby consents to the exclusive jurisdiction of such forums (and
of the appellate courts therefrom) in any such suit, action or proceeding.
14. Assignment. The obligations under this Contract are obligations at all times of Customer,
and may not be assigned without Company's consent except in connection with a sale,
assignment, lease or transfer of Customer's interest in Customer's facility. Any such
4 of 5
assignment also shall be subject to (i) such successor's qualification as a customer under
Company's policies and the Electric Service Regulations, the applicable Electric Service
Schedule, and (ii) such successor being bound by this Contract and assuming the obligation
of Customer from the date of assignment, which may be evidenced by written agreement of
such successor or other means acceptable to Company. Company may condition this
assignment by the posting by the successor of a deposit as permitted under the applicable
Electric Service Regulations and the applicable Electric Service Schedule.
Company may at any time assign its rights and delegate its obligations under this Contract
to any: affiliate; successor in interest; corporation; or any other business entity in conjunction
with a merger, consolidation or other business reorganization to which Company is a party.
15. Remedies; Waiver. Either party may exercise any or all of its rights and remedies under
this Contract, the applicable. Electric Service Regulations, the applicable Electric Service
Schedule and under any applicable laws, rules and regulations. No provision of this
Contract, the Electric Service Regulations, or the applicable Electric Service Schedule shall
be deemed to have been waived unless such waiver is expressly stated in writing and signed
by the waiving party.
16. Attorneys' Fees. If any suit or action arising out of or related to this Contract is brought by
any party, the prevailing party or parties shall be entitled to recover the costs and fees
(including, without limitation, reasonable attorneys' fees, the fees and costs of experts and
consultants, copying, courier and telecommunication costs, and deposition costs and all
other costs of discovery) incurred by such party or parties in such suit or action, including,
without limitation, any post -trial or appellate proceeding, or in the collection or enforcement
of any judgment or award entered or made in such suit or action.
17. Waiver of Jury Trial. TO THE FULLEST EXTENT PERMITTED BY LAW, EACH OF THE
PARTIES HERETO WAIVES ANY RIGHT IT MAY HAVE TO A TRIAL BY JURY IN
RESPECT OF LITIGATION DIRECTLY OR INDIRECTLY ARISING OUT OF, UNDER OR
IN. CONNECTION -WITH THIS CONTRACT. EACH PARTY FURTHER WAIVES ANY
RIGHT TO CONSOLIDATE ANY ACTION IN WHICH A JURY TRIAL HAS BEEN WAIVED
WITH ANY OTHER ACTION IN WHICH A JURY TRIAL CANNOT BE OR HAS NOT BEEN
WAIVED.
18. Entire Agreement. This Contract contains the entire agreement of the parties with respect
to the subject matter, and replaces and supersedes in their entirety all prior agreements
between the parties related to the same subject matter. This Contract may be modified
only by a subsequent written amendment or agreement executed by both parties.
LIBERTY GMC
By
signature
NAME (type or print legibly) TITLE
DATE
5 of 5
ROCKY MOUNTAIN POWER
By
signature
Aaron Hancock Manager
NAME (type or print legibly) TITLE
DATE
Customer's Mailing Address for Executed
Contract
ATTENTION OF
ADDRESS
CITY, STATE, ZIP
EMAIL ADDRESS
1 of 5
Rocky Mountain Power's Mailing Address
for Executed Contract
170W2"dN
ADDRESS
Rexburg. ID 83440
CITY, STATE, ZIP
EMAIL ADDRESS
PACIFICORP
Pacific Power I Rocky Mountain Power
ELECTRIC SERVICE REQUIREMENTS AGREEMENT - NON-RESIDENTIAL SHEET 1
Customer name/location: LIBERTYGMC
Legallbusiness name:
Name of subdivision:
Request # 7016583
Contact person: Phone #
Lot # Subdivision location:
Load Information (Commercial load sheet, electric one -line drawing, site plan, and CAD drawing required.)
service panel size: 200 amps phases: s voltage: 277/480 sq. ft.: motor/heat pump / AC size:
number of lots: number of phases of development:
temporary service required: no 0 yes ❑ (fee of$ will appear on first monthly bill)
party responsible for temp: voltage requested: how many temps?:
General Information
• Line extension policy explained. M
• Customer to call for locates? yes [j] no ❑ N/A ❑
• Customer will accept $250 Contract Administration Credit? yes ❑ no ❑ decide later 0 N/A ❑
• Customer given link to ESR Manual? yes [j] no ❑
• Route (including poles, trench route and equipment locations) staked out and / or explained.
• Route maybe forwarded upon completion of design. ❑ Read the back of this sheet for additional line extension information.
Trench and Conduit (The Customer shall provide a flat pull fine(preferred) or pol, rope ; ��� ��i ), 1,00' tom, fes rninb um,
for all condu# installations.)
• Customer to install: trench E conduit El vault ❑
• Primary/secondary/service trench dimensions 40/30 " deep x " wide, per ESR Manual or Power Company rep.
• No. of runs of primary conduit required 1 diameter 4 "(Schedule 40 gray electrical grade PVC, HDPE, or
fiberglass or as indicated on Power Company drawings)
• Number of primary sweeps 900 " 450 0 radius lf fiberglass/steel (] PVC ❑ (factory quality bend)
• No. of runs of secondary/service conduit required diameter 4 " (Schedule 40 gray electrical -grade PVC,
HDPE, or fiberglass or as indicated on Power Company drawings)
• No. of secondary/service sweeps 90° a 45°= radius"=" fiberglass/steel ❑ PVC E] (factory-qualitybend)
Notes
Riser location marked on pole ❑ N/A (]
Secure 1,000 Ib. pull line inside the conduit and cap with 6 feet of extra line at both ends Q
Vault spec provided. ❑ Top of vault to beat final grade level? yes ❑ no ❑
Read the back of this sheet for additional information on trenching and conduit installations.
Meter Base or Termination Equipment, Installed by Customer (Location as agreed upon, no variation without estimator
approval) Regular, safe, level, and unobstructed access to the meter for the purposes of meter reading and maintenance is required by tariff.
• Underground -fed 0 Overhead -fed ❑
• Manual link bypass req'd ❑ safety socket req'd 0 C.T
• Switchgear service entrance required above 801 amps?
• Specifications or drawings provided:
enclosure required ❑ dimensions: (per ESR)
yes � no �( Net metering? yes ❑ no F-_1
Read the back of this sheet for additional information on meterinq installations.
Before Service Can Be Provided (Caa us at to inform us of yourprogress on the following.)
• Tree trimming required, to be done by: Customer ❑ Power Company ❑ N/A F11
• Required electrical inspection discussed with Customer. (Customerto contact City, County or State permitting office) El
• Right-of-way required and explained. ❑ N/A 2 (additional widths maybe required)
• Contractor Letter of Agreement required and explained. Q N/A ❑
• Trench and conduit to be mandrel'd under Power Company supervision and inspected? yesE no ❑ N/A ❑
(Call 270-2806 for trench inspection with minimum 48 hrs notice.)
• Other information needed from Customer before design can take place:
Read the back of this sheet for additional information on requirements.
Notes: Is this agreement accompanied by a sketch sheet (sheet 2)? yes E no ❑
ESR Link to the power companies construction requirement standards;
https://www.rockymountainpower. net/content/dam/pacific_powerldoctContractors_Suppliers/Electric_Service_Requirements/2016_ESR_2E.pdf
Changes to this agreement must be communicated and agreed to by the Estimator or Manager. Your estimate is good
for 90 days. If you request changes to the estimate or design, or if it must be recreated after cancellation, the Power
Company may require a non-refundable re-engineering fee (minimum of $200), payable in advance.
PacifiCorp representative's signature and P# Customers (or representative's) signature Date
Form PC07 Revision date: 10/7/2016
PACIFICORP
Pack Power I Rocky Mountain Power
Load Information - The load information you provide is used in sizing the Company facilities to meet your electrical demands. Ii
is imperative that you provide accurate information and notify your estimator of any changes as quickly as possible.
General Information
• Line Extension Policy information can be found online at www.pacifrcpower.net or www.rockymountainpower.net by
navigating as follows: Business > Rates & Regulation > Choose your State > Approved Tariffs, Rate Schedules or Rules.
• The Customer shall call 8-1-1 (Call Before You Dig) for underground utility cable locations at least 48 hours (two full
working days) prior to any excavation.
• By accepting the $250 Contract Administration Credit, you waive your right to future refunds (if applicable).
• Contact the Estimator if you wish to relocate the route as designed. Do not relocate the Estimator's stakes.
• The Customer is responsible for following the specifications in this document, as well as those in the Six -State Electric
Service Requirements Manual (ESR). The ESR can be found online at www.pacificlyower.net/ESR or
www. rockvmo untain p ower. n et/ESR.
Trench & Conduit
Electric utilities (cable TV, telephone) shall
have at least 12" of horizontal clearance
from primary and secondary cables.
Non -electric utilities (Gas, Water, Sewer,
etc.) and privately -owned facilities shall
not be installed in the power trench
without prior approval by the power
company.
Contact your Estimator if you plan to
change the route of the service, install
more sweeps, or increase the length.
Note: Ten feet (10') of level ground, free
from obstructions, is required in
front of equipment pads. Three feet
(3') of clearance is required on the
remaining three sides.
Main Trench
final grade
LEGEND
other cable utilities
E
o
`
Osecondary/service
o
Oprimaryconduit/cable
1 R" min. R" mina
-- o -f
! > v l backfill
backfill surrounding conduit
Z10�\n undisturbed earth
�SL _-. -.
Minimum Minimum Minimum
Conduitr Cover Trench Depth Burial Depth
Cable (in.) (in.) (in.)
Primary 30 36 48
Secondary/Service 24 30 48
Additional General Requirements (See the ESR Manual for all requirements.)
• The height of the meter shall be no greater than 72". The socket's center shall be no less than 48" above the ground.
• In installations with two or more units, each metered service shall be permanently labeled with the Customer's address with a
metal or hard plastic engraved label.
• For an overhead service, a 24" minimum tail is required to be left out of the service mast.
• For an overhead service to a meter pole, the pole shall be no less than 5%" in diameter at the top, treated, set at least 60"
deep, and the bottom of the weatherhead shall be located within 12" of the top of the pole. Used poles must be approved.
• Poles must be accessible to Power Company power -lift aerial equipment.
• The Electrical Inspector (State, County, or City) is the proper person to answer most questions regarding your wiring and
equipment beyond the interconnection with the Power Company's supplied service.
Before Service Can Be Provided
• If overhead primary service is to be installed, trees and limbs shall be cleared 10' from each side of the line.
DO NOT TRIM TREES WITHIN 10' OF EXISTING OVERHEAD PRIMARY LINES. Walk the route with your Estimator to
determine acceptable vegetation and appropriate clearances.
• The Power Company will prepare easement documents. The Customer shall return the signed easement and pay any
associated costs.
• Underground cable and conduit installations shall not be energized until the proper select backfill over the cable or conduit has
been inspected by the Power Company representative. The Customer is responsible for providing the backfill and the final cover
of the trench.
• The Power Company's schedule for construction on your project depends on the project's size, the type of material ordered
(some materials have long lead delivery dates), the workload of the Power Company in your area, and changes to the initial
design. Work shall not be scheduled until you have met all of the requirements detailed on this form and the ESR
(www.oacificpowecnet/ESR or www.rockvmountainoower.net/ESR). and have called in to inform the Power Company.
Form PC07 Revision date: 10/7/2016
LEGEND
other cable utilities
(telephone, cable tv)
Osecondary/service
Oprimaryconduit/cable
-- o -f
! > v l backfill
backfill surrounding conduit
Z10�\n undisturbed earth
�SL _-. -.
Minimum Minimum Minimum
Conduitr Cover Trench Depth Burial Depth
Cable (in.) (in.) (in.)
Primary 30 36 48
Secondary/Service 24 30 48
Additional General Requirements (See the ESR Manual for all requirements.)
• The height of the meter shall be no greater than 72". The socket's center shall be no less than 48" above the ground.
• In installations with two or more units, each metered service shall be permanently labeled with the Customer's address with a
metal or hard plastic engraved label.
• For an overhead service, a 24" minimum tail is required to be left out of the service mast.
• For an overhead service to a meter pole, the pole shall be no less than 5%" in diameter at the top, treated, set at least 60"
deep, and the bottom of the weatherhead shall be located within 12" of the top of the pole. Used poles must be approved.
• Poles must be accessible to Power Company power -lift aerial equipment.
• The Electrical Inspector (State, County, or City) is the proper person to answer most questions regarding your wiring and
equipment beyond the interconnection with the Power Company's supplied service.
Before Service Can Be Provided
• If overhead primary service is to be installed, trees and limbs shall be cleared 10' from each side of the line.
DO NOT TRIM TREES WITHIN 10' OF EXISTING OVERHEAD PRIMARY LINES. Walk the route with your Estimator to
determine acceptable vegetation and appropriate clearances.
• The Power Company will prepare easement documents. The Customer shall return the signed easement and pay any
associated costs.
• Underground cable and conduit installations shall not be energized until the proper select backfill over the cable or conduit has
been inspected by the Power Company representative. The Customer is responsible for providing the backfill and the final cover
of the trench.
• The Power Company's schedule for construction on your project depends on the project's size, the type of material ordered
(some materials have long lead delivery dates), the workload of the Power Company in your area, and changes to the initial
design. Work shall not be scheduled until you have met all of the requirements detailed on this form and the ESR
(www.oacificpowecnet/ESR or www.rockvmountainoower.net/ESR). and have called in to inform the Power Company.
Form PC07 Revision date: 10/7/2016
. qXa
C7% Ln
0
ZZ
N
DD
Lq o
o�
00
0
D '
oCID
T4Q
Vl'oO O T
w .1 N O M
M o p X
T 0 N
.o `
V
Ln
O
L% wo
X
20
w iu
O
3
T
N T
D �
00,
r
-- — -- - - �/nz�
^� ,
D /
RXB 16 0° RXB 16 -1 /
Np 1-2-5-3#2=A ,N# -A�
o -,�'� N -N v, N 1500 W
�� o
�
V)
0 � o
0
Foreman Emp # Job Start Date PAC I F I CO R P
Z A BERKSHIRE HATHAWAY ENERGY COMPANY
CC# WC#t /REQ# Map String Job Comp Date
11471 007016583 03106039.0 m
Customer: Liberty GMC Circuit Post Jobs ❑ EST ID# Print Date Scale
Vis: 896W Main St, Rexburg, ID RXB 16 posted o P21040 2/28/2023 I " = 81.92'