Welcome & Introductions
Presenters: Zak Johnson; ITD, Eli Robinson; ITD, Mike McKee; Horrocks Engineers, Rosemary Curtin; RBCI
Participants: business owners and managers
Zak Johnson, ITD
Note: emergency exits, restrooms, etc.
2
Purpose of meeting
Communicate directly with the business community
Invited businesses within a 1-mile radius of each interchange
Goal
Keep businesses informed
3
Agenda
Project background
Overview of final design plans
Preliminary construction information
Next steps
4
Project Background
Zak Johnson, ITD
5
Project need
Unacceptable delays
Traffic counts:
6
Background
Completed technical analysis
Evaluated five design options
Gathered public input:
- Dec. 2020 & Mar. 2022
7
Design options
8
Choosing a Diverging Diamond Interchange (DDI)
Reviewed input from the public
Completed additional technical work (impact time, right-of-way, cost, future growth, expansion)
9
DDI Design Plans
Mike McKee, Horrocks
10
DDI benefits
State and national data clearly show that the DDI design improves safety.
Left-turning traffic uses a “crossover” lane instead of waiting for oncoming traffic to stop.
The design reduces the number of potential conflict points (a traditional diamond interchanges has 26, while a DDI has 14).
The DDI design reduces the opportunities for head-on collisions.
11
Diverging Diamond Interchange (DDI)
12
13
Exit 332 - Final Design Plan
14
Exit 333 - Final Design Plan
15
The DDIs in Rexburg will:
Reduce congestion
Improve safety and reduce injuries
Move high volumes of left-turning traffic
Not require the interchange structures to be rebuilt, reducing costs
16
Questions/Q&A
What questions do you have about the Diverging Diamond Interchange (DDI) design?
What would be the best way to educate the Rexburg community about the DDIs and how to drive them?
17
Construction Plans
Mike McKee, Horrocks
18
Anticipated schedule
ITD anticipates construction will occur in summer 2024.
19
Anticipated construction
Each interchange will be fully closed, one at a time
Each closure will last for approximately 6 weeks
One interchange will remain open as a detour route
US-20 will remain open during construction
20
Schedule benefits
Crews will be able to complete both interchanges in one construction season.
ITD will be able to construct the University Blvd. (exit 332) interchange while Madison High School is out for summer break and when BYU-Idaho will be least impacted.
Full closures will allow crews more room to work, improving safety.
The time period of traffic impacts to drivers is shortened.
21
What comments or questions do you have about construction plans?
Do you have any suggestions on how ITD can best inform the community about construction?
Questions/Q&A
22
Next Steps
Eli Robinson, ITD
23
Next steps:
Public meeting tomorrow:
March 1 | 4:30 – 6:30 p.m. |Madison High School
Meet again before construction begins
Spring 2024: begin construction
24
Comment Sheets
Questions:
DDI design, educating the community
Construction plans, keeping the community informed
Input:
Your comments will help ITD move forward with construction plans
25
Thank you!
Contact: Zak Johnson, ITD Project Manager
(208) 239-3363
itdprojects.org/us20rexburg
*Don’t forget to turn in your comment sheet to the project team.