From: Brett Gulash < bg u lash@ h illside-architectu re.com >
Sent: Friday, January 13, 2023 1:39 PM
To: Mike Massey via Bateman -Hall, Inc.
Cc: Mike Massey
Subject: RE: 01013BG RFI 017 Building B stem wall on 1 line at loading dock - Rexburg U -Haul
Please see response from structural::
Brett,
I spoke with Mike on this and it will be acceptable as long as the building wall is braced temporarily until
the truck dock wall can be placed. Or, the building wall can tie into the truck dock strip footing
monolithically and then it will be able to retain the building pad soil.
David Sansotta, P.E., S.E.
R',q 0
/LJL
iwai�i�sxa
5509 N Glenwood St
Boise, ID 83714
0:208-501-2289
c: 208-863-8290
e: David SC@Stru turalEd Qe.com
www.structura[edge.com
Brett Gulash, AIA, NCARB
Direct: 775-722-1682
bgulash(a hillside-architecture.com
111SIC
architecturE
Please note that Hillside Architecture, PLLC will be moving on 1/30/2023. We will likely not be able to respond to emails
or answer the office phones during this time as our server will begetting moved at the same time. Our plan is to be up
and running again on 2/1/2023 in our new location. Thanks for your understanding.
From: Mike Massey via Bateman -Hall, Inc. <cmicio@cmiccloudrl2.com>
Sent: Friday, January 13, 2023 10:57 AM
To: Brett Gulash <bgulash @hillside-architecture.com>
Subject: 01013BG RFI 017 Building B stem wall on 1 line at loading dock - Rexburg U -Haul
BATEMAN-HALL,
CONSTRUCTION MANAGER
[CMiC] RFI: 017 Building B stem wall on 1 line at loading dock
Frol-W Mike Massey
To: Brett Gulash
CC: Drex Johnson, Shay Moon
This RFI from Mike Massey at Bateman -Hall, Inc regarding U -Haul Rexburg, ID requires Brett
Gulash's attention.
A response to this RFI is due on 2023-01-18.
Section 41S1.2 shows the loading wall retaining wall footer and wall poured and backfilled up
to the stem wall footing. We would like to drop the footing on the stem wall to the retaining wall
elevation and pour the wall taller to complete the building foundations sooner in order to start
the building shell as scheduled mid February. Is this acceptable? Please see attached
highlighted drawing with comments.
Suggestion:
Answer:
Cost Impact:
Potentially