SUMMARY INSPECTION REPORT
This letter is to confirm that, in accordance with Chapter 17 of the 201 8 International Building Code, the project
specifications, and the project scope of services, Atlas Technical Consultants personnel have performed special
inspections of the following items:
Geotechnical inspection and recommendations
Structural fill density testing
Reinforced concrete testing and inspection
We confirm that, to the best of our knowledge, the requirements of the 2018 International Building Code and the
approved plans and specifications have been complied with, insofar as meeting the portion of the aforementioned
inspections requiring special inspection under Chapter 17 of the IBC, except as noted below:
c7177rev – Placement time exceeded and slump did not meet project requirements.
o 28-day strengths found to meet project requirements.
Final acceptance to be determined by the Engineer.
c1573rev – 28-day strengths did not meet project requirements.
o 56-day strengths found to meet project requirements.
Final acceptance to be determined by the Engineer.
c8459, c8510, c8577 – 28-day strengths have not been obtained at the time of this report.
o 7-day strengths found to meet project requirements.
Final acceptance to be determined by the Engineer.
C8651 – 28-day strength have not been obtained at the time of this report.
o 7-day strength is at 92% of the specified project requirements.
Final acceptance to be determined by the Engineer.
Tests and inspections were performed only when Atlas was scheduled to do so. A guarantee that the
contractor has necessarily constructed the structure in full accordance with the plans and specifications
is neither intended nor implied.
If there are questions concerning this letter (Summary Inspection) or if Atlas can be of further assistance, please
contact the project manager at (208) 529-8242.
Respectfully submitted,
Atlas Technical Consultants, LLC
1753 Precision East Drive Idaho Falls, ID 83402 (208) 529-8242 Fax (208) 529-6911
oneatlas.com
Colton Bedke, P.E. Reviewed by: Derrick Fontes
Transportation Engineer Idaho Falls Branch Manager
cc: Joseph Carson; Matthew Hill, Keller Associates;
12/23/22