Matt Nielson
From:Bret Stoddard
Sent:Tuesday, December 13, 2022 11:57 AM
To:Jed Platt; Matt Nielson; Keith Davidson
Subject:RE: Romance Theater BUILDING PROJECTS
Jed, Matt, and Keith, I have made notes below of some things we may need to look closer at.
ROMANCE THEATER Second Phase Renovation
Backstage/Dressing rooms (approx. 1300 sq ft)
Auditorium storage closets
Proposed Budget: $50k - $43k is my estimate, but I would ask for $50k in case things go over. Do we need to plan for
paying Building Dept. for some labor throughout the project? Matt will know best on this.
LABOR
General: $14,000 – we estimated 2 months of labor to be $16,000 ($50/hour*320 hours)
Plumbing: $12,000 – I think this is a fairly high number if the sewer line is located where it was marked. Could be more
like $4000.
*Sub/in house (demo, electrical): $3000 – This number is ok for labor only.
MATERIALS
Materials: $6000
Flooring: $8000 – I think the flooring could be less expensive than this. Depends on what is chosen.
Fixtures: $7000
PROJECT 1: RESTROOM
Demo divider wall
Expose brick (south wall)
Frame door to utility area
*Electrical, lighting
Drywall
Paint
Fixtures—toilet, urinal, sink, mirror, paper dispensers – Do we need to include a urinal and a toilet, or just a toilet?
PROJECT 2: BOILER AREA/MAKEUP & COSTUMING
Remove boiler – maybe should plan for some budget for paying PW? $1000? And what about labor for Building Dept.?
Demo wall
Leave rock wall exposed – We planned to fur out the wall with studs and drywall it?
Relocate heating unit
Open door to outside stair, assess stairway access
Build up, level/float concrete floor
Reframe wall
Shelves
*Electrical, lighting
Drywall
Paint
Cabinetry
Mirror
2
PROJECT 3: DRESSING ROOM 1
Expose brick (south wall)
*Electrical, lighting
Framing
Drywall
Paint
Mirror
Hanging rod
PROJECT 4: DRESSING ROOM 2
*Electrical, lighting
Drywall
Paint
Mirror
Hanging rod
PROJECT 5: GREEN ROOM
Leave ceiling exposed
Level/float concrete floor
*Electrical, lighting
Frame closet
Drywall
Paint
Cubby storage
Kitchenette--cabinets, counter, sink, fridge, microwave
PROJECT 7: STORAGE CLOSETS
Frame closets (east and west sides) under balcony seating for storage of tables and chairs – I think we push this to the
last item in case we run out of budget and/or time?
Please review and let me know your thoughts on these highlighted items.
Thanks,
Bret Stoddard | Building Official
Rexburg Building Department
35 North 1st East
Rexburg, Idaho 83440
(208)372-2332 W
(208)716-1332 C
From: Jed Platt <jed.platt@rexburg.org>
Sent: Monday, December 12, 2022 12:13 PM
To: Bret Stoddard <Bret.Stoddard@rexburg.org>; Matt Nielson <mattn@rexburg.org>; Keith Davidson
<Keith.Davidson@rexburg.org>
Cc: Jedidiah Willis <Jedidiah.Willis@rexburg.org>
Subject: Romance Theater BUILDING PROJECTS