Loading...
HomeMy WebLinkAboutLightbridge Report 2022-12-21 Lightbridge Progress Report 2022-12-21 Middle-Mile Construction Construction officially ended on December 9 62,073 feet of conduit was buried (63%) 161 handholes were placed (69%) Increased Footage & Handholes Original footage: 95,556 feet Change orders have increased it to 98,469 feet. Widdison = 3,600 feet additional Original handholes: 234 We’ve added/deleted handholes along the way Current total handholes: 235 Dry Creek expected to be here for 4 months boring rock It took them almost 8 months to complete the rock on the hill. Outstanding Issues (to be addressed in the spring) John Ferguson (205 N 3rd E) - sprinkler Shayla Webb (17 S 5th W) - lawn Fiber Huts Huts should arrive before end of January Concrete pads have been poured Some electrical equipment is arriving (transfer switches) WideOpen Networks progress Remodeling of the retail space (15 E. Main) is progressing Carpet coming mid-January WideOpen planning to begin staffing the space February 1 Invitations have gone out to ISPs Planning to be providing services to customers in May 2023 Middle-Mile Construction Status as of 2022-12-09