Lightbridge Progress Report
2022-12-21
Middle-Mile Construction
Construction officially ended on December 9
62,073 feet of conduit was buried (63%)
161 handholes were placed (69%)
Increased Footage & Handholes
Original footage: 95,556 feet
Change orders have increased it to 98,469 feet.
Widdison = 3,600 feet additional
Original handholes: 234
We’ve added/deleted handholes along the way
Current total handholes: 235
Dry Creek expected to be here for 4 months boring rock
It took them almost 8 months to complete the rock on the hill.
Outstanding Issues (to be addressed in the spring)
John Ferguson (205 N 3rd E) - sprinkler
Shayla Webb (17 S 5th W) - lawn
Fiber Huts
Huts should arrive before end of January
Concrete pads have been poured
Some electrical equipment is arriving (transfer switches)
WideOpen Networks progress
Remodeling of the retail space (15 E. Main) is progressing
Carpet coming mid-January
WideOpen planning to begin staffing the space February 1
Invitations have gone out to ISPs
Planning to be providing services to customers in May 2023
Middle-Mile Construction Status as of 2022-12-09