HomeMy WebLinkAboutRexburg WWTP FPS PowerPoint Presentation v4City of Rexburg WWTP Facilities Planning Study August 17, 2022 1 WWTP Facility Purpose: Evaluate Existing Conditions Estimate Future Needs Propose Capital Improvements 2 Planning Periods Requirements 3 Influent Water Quality Note: 2021 Data * High strength domestic WW, Metcalf & Eddie fifth edition Table 3-16 •Rexburg’s average influent concentrations of biochemical oxygen demand (BOD5), chemical oxygen demand (COD), and total suspended solids (TSS) were significantly higher than what is typically observed in high-strength domestic wastewater. 4 Design Parameters 5 Headworks • The Headworks building consists of an Influent Parshall flume, Mechanical Step screens, and a grit removal chamber 6 Headworks Deficiencies Parshall Flume Inaccurate Readings for Influent Flow Mechanical Screens Insufficient current Capacity Grit Chamber Insufficient Capacity for Planning Period 7 Headworks Expansion • Replace Parshall flume with new flowmeter or Parshall flume. • Add 2 new Step Screens and keep current Mechanical Screens as redundant units. • Install new Vortex grit chamber. • Enlarge headworks building to fit new equipment 8 Bio-Tower • A Bio-Tower is part of the primary biological treatment processes. Wastewater is sprayed at the top of the Bio-Tower and flows through a trickling filter. • The Bio-Tower was designed to remove 50% of the influent BOD or a maximum removal of 10,500 lbs/day and have a bacterial yield coefficient of Y=0.6. However, the facility has been tested recently and the structure was shown to remove 6,064 lbs/day of BOD with a yield coefficient of Y=0.8. 9 Oxidation Ditches The oxidation ditches consist of Blowers, Basins and Mixers. There are four existing oxidation ditches. Blowers have recently been replaced 10 Oxidation Ditches Deficiencies or Problems High Solids Retention Time – Average 35 days High Mixed Liquor Suspended Solids – Average 7000 mg/L Food to Microbe Ration is low – 0.05 Average No Redundancy Insufficient Capacity for Future Demand 11 Biological Treatment Recommendations Address Downstream Processes Construct 2nd Bio-Tower Increased loading Capacity to treat BOD Construct (2) Oxidation Ditches Provide Redundancy Provides Additional nutrient removal 12 Secondary Clarification A set of three clarifiers carries out secondary clarification where solids suspended in the liquid can settle to the bottom while water overtops a weir. The solids are then pumped towards the RAS/WAS pump station. RAS is returned to the Oxidation Ditches and returns to the Clarifiers. WAS is sent to the Bio-Solids Treatment. 13 Clarifiers Clarifiers 1 and 2 have a 65’ diameter and have a design capacity of 1.72 MGD. Clarifier 3 has an 80’ diameter and a 2.59 MGD design capacity. Design Loading Capacity 29 lbs/ft^2/day 14 Clarifiers Deficiencies No Redundancy Any unit that is offline will cause the remaining Clarifiers to be overloaded. Currently exceeding loading Capacity 15 Clarifiers Recommendations Address Downstream Processes Add (2) 80’ Clarifiers Add 1st Clarifier by 2024 Add 2nd Clarifier by 2027 or when the influent flow exceeds 4.2 MGD. 16 U.V. Disinfection • U.V. Disinfection is the last treatment process for the clarified water. The water flows around a series of Ultraviolet emitting lamps that render microorganisms inert or sterile. The lamps are contained in modules and two modules make a bank. There are 4 banks; two are in operation and two are on stand-by. There is room to add more banks in the future. 17 Bio-Solids Treatment Bio-Solids Treatment includes the WAS and RAS Pump Station, a Solids Holding Tank, a Gravity Belt Thickener, a Thickened WAS Storage Tank, Pasteurization Tanks, an Anaerobic Digester, Solids Dewatering, and Solids Storage. Updated during current project 18 Pasteurization Tanks • The Rexburg facility has three Pasteurization tanks that each hold 2,650 gal of sludge currently at 3% concentration the design capacity states that each tank will hold 2,650 gal of sludge at 6% concentration. 19 Processing Bio-solids The Pasteurization process is the unit that produce the Class A Bio-Solids for the Rexburg WWTP. The Pasteurization Unit was part of the 2016 facility upgrade. 20 Anaerobic Digester The 2016 design states a VSS destruction of 62% or 6,021 lbs/day According to statements from the operators, the digester does not provide a significant reduction in solids. 21 Biosolids Deficiencies Pasteurization Unit Design Capacity Processing 14,311 dry lbs/day 25,740 gallons per day Current Conditions (2021) Processing 13,252 dry lbs/day Generation 16,970 dry lbs/day Future Demand (2041) Processing 29,504 dry lbs/day Anaerobic Digester 30 Years old Capacity SRT of 20 days No live Bacteria in the System 22 Biosolids Recommendation Increase Class A Capacity 23 Proposed WWTP Facility Upgrades 24 25 Summary of facility upgrades Headworks – Expansion (1) Flowmeter (2) Mechanical Screens (1) Grit Chamber Biological Processes (1) Bio-Tower (2) Oxidation Ditches Clarification (2) 80 ft Clarifiers UV Disinfection Channel depth modification Bio-Solids (1) Dryer 26 Projected Schedule 2023 Design Class A Capacity Upgrades 2023 Design Headworks Upgrades 2023 Design Clarifier Upgrades 2024 Construction Class A Upgrades 2024 Construct Headworks Upgrades 2024 Construction of additional 80’ Clarifier Design and Construction Oxidation Ditches and Bio-Tower when ADF exceeds 4.7 MGD 2027 Construction of additional 80’ Clarifier or when ADF exceeds 4.2 MGD 2032 UV Channel upgrades or when ADF exceeds 4.7 MGD 27 Forsgren Associates, Inc. 208-356-9201• Forsgren.com Dave Noel • dnoel@Forsgren.com Kevin Harris • kharris@Forsgren.com Jason Broome • jbroome@Forsgren.com 28