HomeMy WebLinkAboutNARRATIVE OF CHANGES 2 - 20-00940 - Walmart - RemodelWAL-MART STORES, INC. STORE NO. 01878 03/25/21
PROJECT: Rexburg, ID CCD#2
PROJECT NO. 20296
Page 1 of 2
NOTE: The General Contractor shall obtain approval of the Wal-Mart Construction Manager before
beginning the Work defined in this CCD #2. If applicable, adjustment to the Contract Sum may be based
only on the method described in 7.3.3.1 of the Contract.
SCOPE: The scope of this CCD #2 is to revise the originally issued contract documents of Rexburg, ID
dated 12/04/2020 and all subsequent contract modifications, to reflect the following:
SUMMARY:
• CI 30373
DISCIPLINE
ARCHITECTURAL
SHEET C1 – COVER SHEET
SHEET INDEX
1. Added sheet A2.3 and CS8.
SHEET A2.3 – EXTERIOR ELEVATION REMEDIATION
1. Added sheet in its entirety.
MECHANICAL
SHEET M1.1 – ENLARGED MECHANICAL PLANS
DETAIL 3 – EXPANSION MECHANICAL PLAN
1. Added unit heater SOW.
ROOFTOP UNIT SCHEDULE (LENNOX)
1. Revised schedule
ELECTRIC UNIT HEATER SCHEDULE
1. Added schedule to sheet.
SHEET BAS3 – BUILDING AUTOMATION SYSTEM
DETAIL 1 – BUILDING AUTOMATION SYSTEM PLANS
1. Relocated RTU-34 temperature sensor.
ELETRICAL
SHEET E2.4 – ENLARGED POWER PLANS
DETAIL 2 – STOCKROOM POWER PLAN
1. Added circuit for UH.
SHEET E4.1 – PANELBOARD SCHEDULES
PANEL SCHEDULE
1. PANEL H4B – Revised circuits 38,40&42.
CIVIL
SHEET CS1 – DEMOLITION & SITE PLAN
1. Proposed siphonic manhole location has shifted, ref. CS4 Utility Plan changes.
SHEET CS3 – GRADING PLAN
1. Elevation at siphonic manhole has been provided to plan.
SHEET CS4 – UTILITY PLAN
1. Plan has been updated to include invert information on new siphonic manhole.
2. Existing and proposed storm pipe has been included on plan.
WAL-MART STORES, INC. STORE NO. 01878 03/25/21
PROJECT: Rexburg, ID CCD#2
PROJECT NO. 20296
Page 2 of 2
3. Proposed grease trap, cleanouts and siphonic manhole locations have been adjusted per city
comment.
SHEET CS8 – SITE DETAILS 3
1. Added sheet in its entirety.
END CCD #2