HomeMy WebLinkAboutNARRATIVE OF CHANGES - 20-00940 - Walmart - RemodelWAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 1 of 11
NOTE: The General Contractor shall obtain approval of the Wal-Mart Construction Manager before
beginning the Work defined in this ADD#1. If applicable, adjustment to the Contract Sum may be based
only on the method described in 7.3.3.1 of the Contract.
SCOPE: The scope of this ADD#1 is to revise the originally issued contract documents of Rexburg, ID
12/04/20 and all subsequent contract modifications, to reflect the following:
SUMMARY:
• Revised ID Plan (2)
o Pickup expansion
o Pickup Parking stall count
o Relocate RX drive through
• Garden Center Slider and Gate
DISCIPLINE
ARCHITECTURE
SHEET C1 – COVER SHEET
DRAWING INDEX
1. Revised schedule in its entirety.
GENERAL SCOPE OF WORK
1. Revised OGP SOW.
2. Added PHARMACY DRIVE_THRU SOW in its entirety.
SHEET SP1 – SITE PLAN
KEYNOTES
1. Added keynotes in its entirety.
DETAIL 1 – SITE PLAN
1. Revised 2-OGP1 to 2-OGP4.
2. Revised OGP parking layout.
3. Added 2-SP1 callout.
DETAIL 2 – PHARMACY DRIVE-THRU SITE PLAN
1. Added detail in its entirety.
SHEET SP2 – ENLARGED SITE PLAN AND DETAILS
DETAIL 12 – PAVING SECTION
1. Added detail in its entirety.
SHEET OGP1 – EXPANSION PLANS
1. Revised sheet in its entirety.
2. Revised sheet name.
SHEET OGP2 – CMU EXPANSION ELEVATION
1. Added sheet in its entirety.
SHEET OGP3 – OGP DETAILS
1. Added sheet in its entirety.
SHEET OGP4 – OGP SITE PLAN
1. Added sheet in its entirety.
SHEET D1 – DEMOLITION PLAN
DETAIL 1 – DEMOLITION PLAN
1. Remove 126 Seasonal Shop egress door and added corresponding note.
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 2 of 11
2. Remove rack in Outdoor Storage and added corresponding note.
3. Revised the extent and content of the OGP parking to be demo’d.
4. Revised 1-OGP1 callout to 1-OGP4 and its extents.
5. Revised location of OGP1 callout to include demo of the existing OGP expansion.
6. Relocating dollies, OGP managers cabinet, printer and printer stand and added corresponding
notes.
7. Remove portion of CMU and bollard from the pharmacy drive-thru and added corresponding note.
8. Relocating Pneumatic customer unit, Pneumatic tubing and awning and added corresponding
notes.
9. Remove scupper where new pharmacy drive-thru wall is to be located and added corresponding
note.
SHEET A1 – FLOOR PLAN
DETAIL 1 – FLOOR PLAN
1. Added 126D, 502B, and 949A door tags.
2. Added 1-GC1 callout.
3. Added tactile exit sign and corresponding keynote.
4. Revised 1-GA2 detail bubble extents.
5. Added 2-OGP1 detail bubble callout.
6. Added 3-OGP1 callout.
7. Added dimensions for new CMU wall.
8. Added OGP expansion.
SHEET A1.1 – FLOOR FINISH PLAN
DETAIL 1 – FLOOR FINISH PLAN
1. Added 2-OGP1 callout.
SHEET A2 – EXTERIOR ELEVATIONS
DETAIL 1 – FRONT ELEVATION
1. Added OGP expansion.
DETAIL 6 – LEFT ELEVATION
1. Added OGP expansion.
2. Relocated location of the pharmacy drive- thru.
3. Added 3-PH1 callout.
4. Added 1-OGP2 callout.
5. Added new scupper and corresponding note.
6. Removed P134E paint callout.
7. Removed P134E CAP paint callout arrow.
SHEET A4 – ROOF PLAN
ROOF LEGEND
1. Added RTU to legend.
KEYNOTES
1. Added keynotes in its entirety.
DETAIL 1 – ROOF PLAN
1. Added 1-A4.1 callout.
2. Added existing roof hatch and corresponding note.
3. Added new scupper, scupper keynote, and corresponding dimension.
4. Added 9-A4 section marker.
5. Added 2-PH1 section marker.
6. Relocated seam metal roof awning and added corresponding note.
DETAIL 4 – RCU/RTU UNIT ON CURB
1. Revised detail name.
2. Added RTU text to the detail.
DETAIL 6 – PAD LAYOUT (TYP ALL UNITS)
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 3 of 11
1. Added RTU pad information.
DETAIL 8 – SCUPPER ELEVATION
1. Added detail in its entirety.
DETAIL 9 – THROUGH WALL OVERFLOW SCUPPER
1. Added detail in its entirety.
DETAIL 10 – FLASHING MEMBRANE
1. Added detail in its entirety.
SHEET A4.1 – ENLARGED ROOF PLAN AND DETAILS
1. Added sheet in its entirety.
SHEET A6 – REAR OFFICE PLAN
DETAIL 1 – REAR OFFICE FLOOR PLAN
1. Revised eyewash stripping to appear as existing and removed 9.90 keynote.
SHEET A8 – DOOR AND ROOM FINISH SCHEDULE
DOOR AND FRAME SCHEDULE
1. Added door 126D
2. Added door 502B
3. Added door 949A
FINISH KEY
1. Added AM2.
DETAIL 1 – DOOR TYPES
1. Added A1 door type.
2. Added W1 door type.
3. Added C1 door type.
DETAIL 5 - THRESHOLD
1. Added detail in its entirety.
DETAIL 6 - HEAD
1. Added detail in its entirety.
DETAIL 7 - JAMB
1. Added detail in its entirety.
DETAIL 8 – SLIDING DOOR THRESHOLD EXTERIOR MOUNTED
1. Added detail in its entirety.
DETAIL 9 - SLIDING DOOR JAMB EXTERIOR MOUNTED
1. Added detail in its entirety.
DETAIL 10 - SLIDING DOOR HEAD EXTERIOR MOUNTED
1. Added detail in its entirety.
SHEET BR1 – BREAKROOM PLAN AND DETAILS
DETAIL 2 – ENLARGED BREAKROOM FLOOR PLAN
1. Added new Time Clock and dimensions, and revised associated note.
2. Revised location of Pay Stub Printer.
SHEET VC1 – VISION CENTER
DETAIL 2 – VISION CENTER FLOOR PLAN
1. Revised focal and non-focal wall location millwork.
2. Removed P208 paint callout.
DETAIL 4 – EXTERIOR ELEVATION
1. Revised elevation to include slat wall and added corresponding notes and dimensions.
SHEET VC1.1 – VISION CENTER ELEVATIONS
DETAIL 1 – OPTICAL SALES ELEVATION
1. Revised to include focal wall millwork and added corresponding note.
DETAIL 3 – OPTICAL SALES ELEVATION
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 4 of 11
1. Revised to include non-focal millwork.
2. Removed notes for focal wall millwork.
3. Removed P208 paint callout, dimensions of paint extents and paint line notes.
4. Added note for the frame board.
SHEET VC3 – EQUIPMENT (FOR REFERENCE ONLY)
DETAIL 1 – VISION CENTER EQUIPMENT PLAN
1. Revised focal wall and non-focal wall millwork location.
2. Revised casework tags PNFW3 and PWF-1.
3. Added mirror notes.
SHEET PH1 – PHARMACY DRIVE-THRU PLAN, ELEVATION AND DETAILS
1. Added sheet in its entirety.
SHEET GC1 – GARDEN CENTER PLAN
1. Added sheet in its entirety.
SHEET GA1 – FRONT GROCERY PLAN
EQUIPMENT NOTES
1. Revised notes 10 and 15.
SHEET GA2 – REAR GROCERY PLAN
DETAIL 1 – VENLARGED REAR GROCRY FLOOR PLAN
1. Revised crop extents of detail to exclude the existing PICKUP STORAGE.
STRUCTURAL
SHEET S0 – GENERAL STRUCTURAL INFORMATION
1. Entire sheet added
SHEET S1 – PLANS GENERAL NOTES AND DETAILS
DETAIL – GENERAL NOTES
1. Moved to sheet s0
DETAIL – DESIGN LOADS
1. Moved to sheet s0
DETAIL – STATEMENT OF SPECIAL INSPECTIONS
1. Moved to sheet s0
SHEET S1.1 – FOUNDATION AND FRAMING PLANS
1. Entire sheet added
SHEET S2 – FOUNDATION DETAILS
1. Entire sheet added
SHEET S3 – ROOF FRAMING DETAILS
1. Entire sheet added
SHEET S4 – GENERAL SCHEDULES AND DIAGRAMS
1. Entire sheet added
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 5 of 11
SHEET S5 – PLANS AND DETAILS
1. Entire sheet added
FIRE PROTECTION
SHEET FP1 – FIRE SITE UTILITY PLAN
PIPE DIMENSION TABLE
1. Update table to reflect new size of pipe that will be
used. DETAIL 1 – FIRE SITE UTILITY PLAN
2. Revise building footprint to reflect expanded area.
SHEET FP2 – OVERALL FIRE SPRINKLER PLAN
DETAIL1 – OVERALL FIRE SPRINKLER PLAN
1. Add callout for Existing Dry Riser.
2. Add box note for updated system size.
3. Revise Pickup Storage Sprinkler system.
4. Add bulk dry riser feed main.
5. Provide sprinkler protection in Pickup Cooler/Freezer.
NFPA 13 PROTECTION CRITERIA
1. Add Pickup Cooler/Freezer protection criteria to table.
SPRINKLER SYMBOL LEGEND
1. Revise total sprinklers required quantity.
2. Add TY5255 dry pendent sprinkler.
3. Add “MAKE” column.
4. Update total sprinklers required for TYCO TY5151 sprinkler.
SHEET FP2.1 – ENLARGED FIRE SPRINKLER PLANS
DETAIL 2 – PICKUP EXPANSION
1. Change detail 2-FP2.1 name from “Pickup Storage” to “PICKUP
STORAGE/COOLER/FREEZER SPRINKLER PLAN”.
2. Update Hydraulic Design Block for Pickup Storage.
3. Add Hydraulic Design Block for Pickup Cooler/Freezer Calculation.
4. Add dry system hydraulic block.
5. Revise Pickup Storage sprinkler system.
6. Provide sprinkler protection in Pickup Cooler/Freezer.
DETAIL 4 – EXISTING DRY RISER
1. Add detail to sheet.
KEYNOTES
1. Add keynotes 13.913, 13.914, 13.933, 13935, 13936, 13.937, 13.940, 13.941 and 13.942.
SHEET FP3 – ENLARGED FIRE SPRINKLER PLANS
DETAIL 1 – EXISTING SPRINKLER RISER
1. Add note to update Existing Zone Map.
2. Add nodes to System 5 Riser.
DETAIL 4 – EXISTING DRY RISER
1. Add detail to sheet.
DETAIL 7 – PICKUP COOLER/FREEZER ELEVATION
1. Add detail to sheet.
AIR COMPRESSOR SCHEDULE
1. Add schedule to sheet.
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 6 of 11
PLUMBING
SHEET P1 – OVERALL PLUMBING PLAN
DETAIL 1 – OVERALL PLUMBING PLAN
1. Added callout for OGP Expansion Plumbing Plan.
SHEET P1.2 – ENLARGED PLUMBING PLANS
KEYNOTES
1. Added keynotes 15.403, 15.404, 15.405, 15.411, 15.422, 15.429, 15.444 to sheet.
DETAIL 2 – OGP EXPANSION PLUMBING PLAN
1. Added detail to sheet.
SHEET P2 – PLUMBING DETAILS & SCHEDULES
TOILET PLUMBING FIXTURE SCHEDULE
1. Revised manufacturer information
FLOOR DRAIN SCHEDULE
1. Added FD2, FD4SS, FD10 to schedule
CLEANOUT SCHEDULE
1. Added WCO and YCO to schedule.
DETAIL 5 – GREASE INTERCEPTOR – UPC
1. Added detail to sheet
DETAIL 6 – HUB DRAIN
1. Added detail to sheet
DETAIL 7 – YARD CLEANOUT
1. Added detail to sheet
MECHANICAL
SHEET BAS3 – BUILDING AUTOMATION SYSTEM
1. Added sheet to set.
SHEET BAS4 – BUILDING AUTOMATION SYSTEM
1. Added sheet to set.
SHEET M1 – OVERALL MECHANICAL PLAN
DETAIL 1 – OVERALL MECHANICAL PLAN
1. Added SOW for new RTU per revised ID
SHEET M1.1 – ENLARGED MECHANICAL PLAN
DETAIL 3 – EXPANSION MECHANICAL PLAN
1. Added detail to sheet
DETAIL 4 – GAS CONNECTION/SUPPORT
1. Added detail to sheet
DETAIL 5 – ROOF TOP PIPE BLOCKING
1. Added detail to sheet
DETAIL 6 – ROOFTOP GAS REGULATOR
1. Added detail to sheet
DETAIL 7 – RTU DROP BOX
1. Added detail to sheet
SHEDULES – AIR DEVICE SCHEDULE
1. Added schedule to sheet
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 7 of 11
REFRIGERATION
SHEET BAS1 – BUILDING AUTOMATION SYSTEMDETAIL 1 – REFRIGERATION BUILDING
AUTOMATION PLAN
1. Add OGP walk-ins
2. Add callout for Sporlan wiring detail.
DETAIL 2 – REFRIGERATION BAS ONE-LINE DIAGRAM (EXISTING)
1. Add KE2 controllers and existing MinIO to one line.
SHEET BAS2 – BUILDING AUTOMATION SYSTEM
DETAIL 2 – TEMPERATURE SENSRO LOCATION
1. Add detail.
RACK RCU4 TEMPERATURE AND DEFROST PARAMETERS
1. Add schedule.
RACK RCU5 TEMPERATURE AND DEFROST PARAMETERS
1. Add schedule.
SHEET BAS3 – BUILDING AUTOMATION SYSTEM
1. Add Sheet
SHEET R1 – PARTIAL REFRIGERATION PLAN
OWNER FURNISHED REFRIGERATION EQUIPMENT
1. Add equipment to schedule.
SHEET R2 – PARTIAL REFRIGERATION PLAN
KEYNOTES
1. Add keynote 15.604, 15.606, 15.607, 15.608, and 15.636.
PIPING SCHEDULE RCU4
1. Add schedule.
PIPING SCHEDULE RCU5
1. Add schedule.
DETAIL 2 – REFRIGERATION PLAN - OGP
1. Add detail.
DETAIL 3 – OGP REFRIGERATION DEMOLITION PLAN
1. Add detail.
WALK-IN EVAPORATOR COIL SCHEDULE
1. Add schedule.
COMPRESSOR HOUSE AND/OR CONDENSER SALVAGE REQUIREMENTS
1. Add notes.
SHEET R3 – REFRIGERATION SCHEDULES
1. Revise refrigeration system schedule RCU1, RCU2, RCU3 for formatting purposes.
2. Add refrigeration system schedule RCU4 Schedule
3. Add refrigeration system schedule RCU5 schedule
SHEET R4 – REFRIGERATION DETAILS
DETAIL 7 – EVAPORATOR FAN/COIL UNIT
1. Add detail.
DETAIL 7 – EVAPORATOR COIL CONDENSATE PIPING
2. Add detail.
ELETRICAL
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 8 of 11
SHEET E1 – OVERALL LIGHTING PLAN
1. Added callouts 1/2-E1.3 for OGP STORAGE SOW.
SHEET E1.2 – LIGHTING DETAILS & SCHEDULES
LIGHT FIXTURE SCHEDULE
1. Added type 1, 18 & 50 lights to schedule.
SHEET E1.3 – ENLARGED LIGHTING PLANS
1. Added sheet.
SHEET E2 – OVERALL POWER PLAN
DETAIL 1 – OVERALL POWER PLAN
1. Added callouts 1/2-E2.4 for OGP STORAGE SOW.
2. Added callout 3/E2.4 for new dry riser SOW.
3. Removed callout 5/E2.2
SHEET E2.2 – ENLARGED POWER PLANS
DETAIL 5 – OGP STOCKROOM POWER PLAN
1. Removed view.
SHEET E2.4 – ENLARGED POWER PLANS
1. Added sheet.
SHEET E4.1 – PANELBOARD SCHEDULES
PANEL SCHEDULE – H4B
1. Revised circuits 19,21,23
RACKING
SHEET FXS1 – FIXTURE ANCHORAGE PLAN AND NOTES
DETAIL – ANCHORAGE BILL OF MATERIALS
1. Revised bolt counts
DETAIL – RACK FRAME AND ANCHORAGE SCHEDULE
1. Entire schedule added
DETAIL – RACK FIXTURE SCHEDULE
1. Entire schedule added
DETAIL 1 – FIXTURE ANCHORAGE PLAN
1. Revised ogp mod expansion layout
SHEET FXS2 – FIXTURE ANCHORAGE DETAILS
DETAIL 5 – TYPICAL ANCHOR AT RACK FRAMES
1. Added ogp baseplate
SHEET FXS3 – FIXTURE FRAMING DETAILS
1. Entire sheet added
CIVIL
SHEET CS1 – DEMOLITION AND SITE PLAN
1. Added sheet in its entirety.
SHEET CS2 – GRADING PLAN
1. Added sheet in its entirety.
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 9 of 11
SHEET CS3 – UTILITY PLAN
1. Added sheet in its entirety.
SHEET CS4 – SITE SIGNAGE PLAN
1. Added sheet in its entirety.
SHEET CS5 – DETAIL SHEET 1
1. Added sheet in its entirety.
SHEET CS6 – DETAIL SHEET 2
1. Added sheet in its entirety.
SHEET SSM-1 – STOP SIGNS AND MARKINGS PLAN
1. Added sheet in its entirety.
SHEET SECP-1 – DEMOLITION AND SITE CONSTRUCTION PLANS
1. Added sheet in its entirety.
SHEET SECP-2 – DEMOLITION AND SITE CONSTRUCTION PLANS
1. Added sheet in its entirety.
SHEET SECP/SSM DETAILS-1 – SECP AND STOP SIGNS AND MARKINGS DETAIL SHEET
1. Added sheet in its entirety.
SHEET SECP/SSM DETAILS-2 – SECP AND STOP SIGNS AND MARKINGS DETAIL SHEET
1. Added sheet in its entirety.
SHEET CSS-1 – SPECIFICATION SHEET
1. Added sheet in its entirety.
SHEET CSS-2 – SPECIFICATION SHEET
1. Added sheet in its entirety.
SPECIFICATIONS
00010 – TABLE OF CONTENTS
1. Added sections:
a. 03312 – Cast-In-Place Concrete Slabs (Interior)
b. 04200 – Unit Masonry Assemblies
c. 04910 – Masonry Restoration and Repair
d. 05210 – Steel Joists
e. 05300 – Metal Deck
f. 07500 – Membrane Roofing
g. 10725 – Metal Awnings
h. 14580 – Pneumatic Tube System
00010 – TABLE OF CONTENTS (CIVIL)
1. Added section in its entirety.
02230 – SITE CLEARING
1. Site Clearing specification has been added to the site specifications.
02300 – EARTHWORK
1. Earthwork specification has been added to the site specifications.
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 10 of 11
02340 – SOIL STABILIZATION
1. Soil Stabilization specification has been added to the site specifications.
02535 – SANITARY SEWAGE SYSTEMS
1. Sanitary Sewage Systems specification has been added to the site specifications.
02536 – SEWER MANHOLES, FRAMES, AND COVERS
1. Sewer Manholes, Frames, and Covers specification has been added to the site specifications.
02630 – STORM DRAINAGE
1. Storm Drainage specification has been added to the site specifications.
02715 – BASE COURSE
1. Base Course specification has been added to the site specifications.
02740 – ASPHALT CONCRETE PAVING
1. Asphaltic Concrete Pavement specification has been added to the site specifications.
03311 – SITEWORK STRUCTURAL CONCRETE
1. Sitework Structural Concrete specification has been added to the site specifications.
03312 – CAST-IN-PLACE CONCRETE SLABS (INTERIOR)
1. Added spec in its entirety.
04200 – UNIT MASONRY ASSEMBLIES
1. Added spec in its entirety.
04910 – MASONRY RESTORATION AND REPAIR
1. Added spec in its entirety.
05210 – STEEL JOISTS
1. Added spec in its entirety.
05300 – METAL DECK
1. Added spec in its entirety.
05500 – METAL FABRICATIONS
2.1 OWNER FURNISHED PRODUCTS
1. Added the section.
3.3 SCHEDULE
2. Added the following sections:
a. H – Interior Stainless steel Bollards
b. I – Interior Galvanized Steel Bollards
c. J – Bollard Base Plate
d. K – Steel Pipe Railings
e. L – Handrail Brackets
07500 – MEMBRANE ROOFING
1. Added spec in its entirety.
08710 – DOOR HARDWARE
3.4 HARDWARE SCHEDULE
1. Added the following doors to the schedule:
a. 126D Seasonal Shop
b. 949A Pickup Storage
WAL-MART STORES, INC. STORE NO. 01878 01/11/21
PROJECT: REXBURG, ID ADD#1
PROJECT NO. 20296.00.002.03.00
Page 11 of 11
10725 – METAL AWNINGS
1. Added spec in its entirety.
13900 – FIRE SUPPRESSION
1. Add section 2.3 MAINTENANCE AIR COMPRESSOR
14580 – PNEUMATIC TUBE SYSTEM
1. Added spec in its entirety.
15050 - BASIC MECHANICAL MATERIALS AND METHODS – 01878
1. Added Specifications section to project
15100 - BUILDING SERVICES PIPING AND EQUIPMENT – 01878
1. Added Specifications section to project
15160 - SIPHONIC PRIMARY ROOF DRAIN SYSTEM – 01878
1. Added Specifications section to project
15190 - FUEL GAS PIPING – 01878
1. Added Specifications section to project
15600 – REFRIGERATION SYSTEMS
1. Add section 3.11 evaporator coil start-up
15700 – AIR DISTRIBUTION – 01878
1. Added drop box to Specifications
APPENDIX A
1.1 SUMMARY, SECTION B
1. Added the following sections:
a. 05210 – Steel Joists
b. 05300 – Metal Deck
c. 08710 – Door Hardware
SECTION 05210 – STEEL JOISTS
1. Added the section in its entirety.
SECTION 05300 – METAL DECK
1. Added the section in its entirety.
SECTION 05300 – METAL FABRICATIONS
1. Added the section in its entirety.
SECTION 08710 – DOOR HARDWARE
1. Added the section in its entirety.
APPENDIX B
1. Revised in its entirety.
APPENDIX B FOR CEC EDITS
1. Owner testing, Inspections and Observations has been added to the site specifications.
END ADD#1