Loading...
HomeMy WebLinkAboutBroadbandUpdate_CC_2022-04-20 PPBroadband Update Rexburg City Council 2022-04-20 Construction Progress Bore: 2,934 ft (& conduit placed) Plow: 0 ft Rock: 100 ft Handholes: 7 To date, after 12 days of construction -- not including today. Western has bored and buried 2,934 ft of conduit. (average 244 per day) Haven’t plowed anything yet, but schedule to begin plowing by the high school on Friday or Monday. They could plow about 2000 ft per DAY Rock boring began this week on 3rd East. Through 100 ft of solid rock in the first day. No conduit or handholes place yet. Current average = 244 per day Require 322 ft per day to stay on schedule. plowing will make up the difference in a hurry. Bore Progress Red lines depict progress between April 4 and April 20 Typical stake marking a future handhole. These go in the ground 1-2 weeks prior to construction beginning.