HomeMy WebLinkAboutBroadbandUpdate_CC_2022-04-20 PPBroadband Update
Rexburg City Council
2022-04-20
Construction Progress
Bore: 2,934 ft (& conduit placed)
Plow: 0 ft
Rock: 100 ft
Handholes: 7
To date, after 12 days of construction -- not including today.
Western has bored and buried 2,934 ft of conduit. (average 244 per day)
Haven’t plowed anything yet, but schedule to begin plowing by the high school on Friday or Monday.
They could plow about 2000 ft per DAY
Rock boring began this week on 3rd East. Through 100 ft of solid rock in the first day.
No conduit or handholes place yet.
Current average = 244 per day
Require 322 ft per day to stay on schedule.
plowing will make up the difference in a hurry.
Bore Progress
Red lines depict progress between April 4 and April 20
Typical stake marking a future handhole.
These go in the ground 1-2 weeks prior to construction beginning.