Daily Field Report
Project Name:
Teton River Flats
Start Time:
02:45 PM
Client:
Headwater's Construction
Contractor:
Thompson
End Time:
04:30 PM
Inspection Type(s):
Earthwork Inspection
Location(s):
Buildings B7 and D1 foundation pads
Observations/ Remarks:
Arrived just after 3pm, talked to Don and one of his tractor operators. I tested the 1st lift of pit run on
the building D1 foundation pad, then tested the 3/4” base on the top of B7 footing elevation of
foundation pad. Informed Don, Manny and the tractor operator of the passing results.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/28/2021
File Name:
20075DFR06282021CTL
Inspector's Signature:Inspector's Name:
Chase Lake
Reviewer's Signature:Reviewer's Name:
W. Moffat
Reviewed Date:
06/29/2021
F9469782-3B3F-408F-92D5-30950323DCE0 2