Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Madison Baseball Field
20052
Madison School District
JM Masonry 09/04/2020
warm, sunny
9:30 AM
77
12:30 PM
I arrived on site at approximately 9:50 AM. I then started my inspection on the re-bar. They placed re-bar
every fourth hole and across on th top cinder blocks and around the corner. After the re-bar inspection they
began to pour the grout. They vibrated the holes with the re-bar to consolidate the grout. They then finished
off the top
Digitally signed by Jacob P Christensen
Date: 2020.09.13 14:49:27 -06'00'
N. Steiner
Page 2 of 2