HomeMy WebLinkAboutSPECIAL INSPECTION 14 - 21-00119 - Adams Elementary School - AdditionInspection Date:
09/07/2021
File Name:
21020DFR09072021YK
Inspector's Signature:Inspector's Name:
Yannick kabwika
Reviewer's Signature:Reviewer's Name:
Steve Anderson
Reviewed Date:
09/07/2021
345b909c5362d83b-1631024443062 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Adam's Elementary
Start Time:
05:35 AM
Client:
Madison School District
Contractor:
Mills Concrete
End Time:
08:45 AM
Inspection Type(s):
Concrete Placement
Location(s):
Interior slab at few spots in the extension building
as shown on the pictures.
Observations/ Remarks:
I arrived at the side at 5:55 AM. The pouring didn't start until 6:50 AM. The results were reported to
both the Mills Concrete supervisor and the truck driver.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
09/07/2021
File Name:
21020DFR09072021YK
Inspector's Signature:Inspector's Name:
Yannick kabwika
Reviewer's Signature:Reviewer's Name:
Steve Anderson
Reviewed Date:
09/07/2021
345b909c5362d83b-1631024443062 2
Inspection Date:
09/07/2021
File Name:
21020DFR09072021YK
Inspector's Signature:Inspector's Name:
Yannick kabwika
Reviewer's Signature:Reviewer's Name:
Steve Anderson
Reviewed Date:
09/07/2021
345b909c5362d83b-1631024443062 3