Daily Field Report
Project Name:
Adam's Elementary
Start Time:
10:15 AM
Client:
Madison School District
Contractor:
Thompson Excavation
End Time:
12:00 PM
Inspection Type(s):
Earthwork Inspection
Other
Location(s):
Trench along the north edge of the property
Observations/ Remarks:
I arrived on site at approximately 11:00 am but they were still compacting the dirt. Once they were
finished I tested compaction throughout the trench and informed the super of the results.
Items observed are in general conformance with approved project documents and jurisdictional requirements.