HomeMy WebLinkAboutSPECIAL INSPECTIONS 3 - Teton River Flats Community HousingProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Teton River Flats
20075
Headwaters Construction
Thompson Excavation 1-14-2021
10:30 AM 2:30 PM
Building:B1
Contractor was over excavating footings approximately 1' and replacing excavated material with
approximately 1' of imported pit run and compacting.
Digitally signed by Tyson Falls DN: cn=Tyson Falls, o=Connect Engineering, email=tfalls@connectengr.com, c=US Date: 2021.01.22 14:27:11 -07'00'2080711
B. Ball
Inspection Date
02/23/2021
File Name
30075DFR02232021Ns
Inspector's Signature Inspector's Name
N. Steiner
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
02/23/2021
9402C6D8-DA10-4314-BD88-AB905FAC30A2 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
09:15 AM
Client
Headwater's Construction
Contractor
Thompson excavation
Time End
11:30 AM
Inspection Type(s)
Concrete Placement
Location(s)
Breezeway between east buildings
Observations/ Remarks
I arrived on site 9:15 and began my inspection and observation. I looked at the forms to make sure
they were at the correct height and made sure they were placed correctly. The pour then began. I
tested the concrete and the concrete was up to spec. The contractor was in general conformance to
project documents.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date
02/17/2021
File Name
20075DFR02172021DFA
Inspector's Signature Inspector's Name
D. Aust
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
02/17/2021
e875ea11521d0ef1-1613575015195 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
06:30 AM
Client
Headwater's Construction
Contractor
Alpha Concrete
Time End
08:45 AM
Inspection Type(s)
Concrete Placement
Concrete Reinforcement
Cold Weather Concrete
Location(s)
Slab on grade of northeast building
Observations/ Remarks
I arrived on site at approximately 6:50 AM. I observed that the contractor had placed a blue moisture
barrier, as well as steel reinforcement, in preparation for the concrete slab. I noticed that there were
not any dobies, or risers, under the steel reinforcement. I informed the contractor that he would have
to wet set them, which I observed being done throughout the duration of the pour. I tested the first
truck, and remained for the duration of the pour.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
New Multi Photo
Inspection Date
02/17/2021
File Name
20075DFR02172021DFA
Inspector's Signature Inspector's Name
D. Aust
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
02/17/2021
e875ea11521d0ef1-1613575015195 2
Inspection Date
02/17/2021
File Name
20075DFR02172021DFA
Inspector's Signature Inspector's Name
D. Aust
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
02/17/2021
e875ea11521d0ef1-1613575015195 3
Inspection Date
03/22/2021
File Name
20075DFR03222021BB
Inspector's Signature Inspector's Name
Ben E. Ball
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/22/2021
A184949A-8BB2-42AA-990C-0FED43BCA46E 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
12:00 PM
Client
Headwater's Construction
Contractor
Thompson
Time End
03:30 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
Interior of building A4 approximately 2’ below
finish floor
Observations/ Remarks
Arrived on site approximately 12:30 pm. Nuke gauge was not working. Had to return to lab and get a
second gauge.
Picked up proctor samples for sanitary sewer backfill.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date
03/15/2021
File Name
20075DFR03152021JPC
Inspector's Signature Inspector's Name
Jacob Christensen
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/17/2021
6c77d085ef10af70-1615933191982 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
03:30 PM
Client
Headwater's Construction
Contractor
Thompson Excavation
Time End
05:30 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
Building B3
Observations/ Remarks
I arrived on site as requested by Thor (Headwaters Construction) to observe the bottom of excavation
or bottom of footings for building B2. I observed that the soil was in a moist condition and was plastic.
I observed that if the contractor were to apply any compaction efforts to this soil that it would cause
liquefaction and therefore be unsuitable to build on. I notified the contractor of my observations prior
to leaving.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
New Multi Photo
Inspection Date
03/24/2021
File Name
20075DFR03242021BB
Inspector's Signature Inspector's Name
Ben E. Ball
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/26/2021
DF9D4E65-3830-44F1-8660-6412DB237595 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
12:24 PM
Client
Headwater's Construction
Contractor
Thompson
Time End
04:30 PM
Inspection Type(s)
Earthwork Inspection
Water/ Sewer/ Storm Drain
Location(s)
Sanitary sewer service to buildings A1-4
Observations/ Remarks
Contractor was backfilling sanitary sewer service trenches with native material in one foot lifts and
compacting.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
New Multi Photo
Inspection Date
03/24/2021
File Name
20075DFR03242021BB
Inspector's Signature Inspector's Name
Ben E. Ball
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/26/2021
DF9D4E65-3830-44F1-8660-6412DB237595 2
Inspection Date
03/24/2021
File Name
20075DFR03242021BB
Inspector's Signature Inspector's Name
Ben E. Ball
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/26/2021
DF9D4E65-3830-44F1-8660-6412DB237595 3
Inspection Date
03/30/2021
File Name
20075DFR03302021NS
Inspector's Signature Inspector's Name
N. Steiner
Reviewer's Signature Reviewer's Name
W. Moffat
Reviewed Date
03/30/2021
19B8E666-FEC9-4B71-BA02-AACF2C3201FC 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
10:30 AM
Client
Headwater's Construction
Contractor
Thompson excavation
Time End
01:30 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
Man hole south end of site in between the two
sets of boukdings
Observations/ Remarks
I arrived on site at approximately 10:45 and began my inspection. I arrived and they were in the
process of putting the man hole in. I then watched them compact the dirt till they met compaction. The
contractor was in general conformance to project documents.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date
04/05/2021
File Name
20075DFR04052021NS
Inspector's Signature Inspector's Name
N. Steiner
Reviewer's Signature Reviewer's Name
E. Vail
Reviewed Date
04/05/2021
3E763374-EFE2-426E-8074-F8B76C51925E 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
12:50 PM
Client
Headwater's Construction
Contractor
Thompson excavation
Time End
02:00 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
Building B2
Observations/ Remarks
I arrived on site at approximately 1:00PM and began my observation. I observed the contractor
compact the 3/4 material until it met compaction requirements. I then tested and they passed. The
contractor was in general conformance to project documents.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date
04/05/2021
File Name
20009UDFR04052021NS2
Inspector's Signature Inspector's Name
N.Steiner
Reviewer's Signature Reviewer's Name
E. Vail
Reviewed Date
04/05/2021
B8D4427E-7F30-43D0-902E-19D176CCF32F 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
02:00 PM
Client
Headwater's Construction
Contractor
SETHCO
Time End
03:00 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
500 feet north of Larch road and 50 feet south of
Larch road
Observations/ Remarks
I arrived on site at approximately 2:15pm and began my observation. The contractor had already
compacted the pit run so I took my tests and they passed. The contractor was in general conformance
to project documents.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date:
05/28/2021
File Name:
20075DFR05282021CTL
Inspector's Signature:Inspector's Name:
Chase Lake
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/02/2021
B9BA0468-2A37-47EC-87FB-D18F1C37E894 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
09:45 AM
Client:
Headwater's Construction
Contractor:
Headwaters
End Time:
03:00 PM
Inspection Type(s):
Earthwork Inspection
Location(s):
Building B4 foundation pad
Observations/ Remarks:
Arrived at 9:45am, they were still compacting the native soil before pit run was placed. We tested the
soil and it passed quickly. We were told by Don to return around 12:00pm to test the first lift of pit
run. Then at 1:30pm, we tested the 2nd lift of pit run. Both the hand compactor and the roller machine
were used on the lifts.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date
05/28/2021
File Name
20075DFR05282021
Inspector's Signature Inspector's Name
Leland Steiner
Reviewer's Signature Reviewer's Name
E. Vail
Reviewed Date
06/01/2021
D46F23EB-82E1-4003-9403-0F00E7263A63 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name
Teton River Flats
Time Start
07:15 AM
Client
Headwater's Construction
Contractor
Alpha Concrete Construction
Time End
10:45 AM
Inspection Type(s)
Concrete Placement
Concrete Reinforcement
Location(s)
Foundation Walls
Observations/ Remarks
I arrived at the lab at 7:04 AM and began to load up my gear. I then left the lab at 7:17 and made my
way to the job site. I arrived there at 7:31 AM and began my inspections. After looking at the rebar I
began to set up my equipment. I then waited for the first truck to arrive, which happened at 7:55 AM.
I then grabbed the ticket and some water and finished setting up my gear. I then grabbed my sample
at 8:15 AM and began my testing. Everything passed without difficulty, and was within spec. After
finishing my testing and cleaning up my gear, I stayed and observed the rest of the pour. I then left
the job site at 10:12 AM after observing the duration of the pour. I then arrived back that the lab at
10:32 AM.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date:
06/01/2021
File Name:
20075DFR06012021MAS
Inspector's Signature:Inspector's Name:
Mitch Singleton
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/02/2021
D477CB11-C021-467E-8917-C40D174927DF 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
01:00 PM
Client:
Headwater's Construction
Contractor:
Thompson’s Excavation
End Time:
03:15 PM
Inspection Type(s):
Earthwork Inspection
Location(s):
Edge of inside of foundation on the 3rd building
from the west end of plot.
Observations/ Remarks:
I arrived on site at approximately 1:30. I made contact with Leland to take over for him and find out
the area to take densities on. The first lift was the edge on the inside of the foundation. I watched as
they compacted the soil. When they were ready I took a shot of where they compacted and observed
that the compaction was above 95% compaction.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date:
06/01/2021
File Name:
20075DFR06012021LC
Inspector's Signature:Inspector's Name:
L. Clifford
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/02/2021
84AD7034-F874-4531-A830-C14D3F90950B 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
04:00 PM
Client:
Headwater's Construction
Contractor:
Thompson Excavation
End Time:
05:30 PM
Inspection Type(s):
Other
Location(s):
Unit B5
Observations/ Remarks:
Density testing for unit B5, arrived on site around 4:30 PM and spoke with Don from Thompson
excavation, density tests were taken at each of the four corners of unit B5 and passing density test
results were reported to Thompson technician on site. Left site around 5:15 PM
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Date:
06/02/2021
File Name:
20075DFR06022021AS
Inspector's Signature:Inspector's Name:
Alan Schiess
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/03/2021
88e4e71eb0d121c0-1622652313049 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
09:30 AM
Client:
Headwater's Construction
Contractor:
Thompson Excavation
End Time:
03:00 PM
Inspection Type(s):
Earthwork Inspection
Location(s):
I tested two trenches using the proctor of 108.1.
The trenches are oriented north to south from
main sewer line to the four-plex’s.
I also tested the main sewer trench.
Observations/ Remarks:
I informed Don about the results. I stayed and tested/watched as the contractor filled the trench in.
The trench was filled in one foot lifts. I used the native silt proctor of 108.1.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/02/2021
File Name:
20075DFR06022021AS
Inspector's Signature:Inspector's Name:
Alan Schiess
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/03/2021
88e4e71eb0d121c0-1622652313049 2
Inspection Date:
06/03/2021
File Name:
20075D06032021YK
Inspector's Signature:Inspector's Name:
Yannick Kabwika
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/04/2021
345b909c5362d83b-1622751411666 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
10:45 AM
Client:
Headwater's Construction
Contractor:
Headwater's Construction
End Time:
04:45 PM
Inspection Type(s):
Earthwork Inspection
Location(s):
Subgrade and subbase of building 6
Observations/ Remarks:
At 11:20 am when I got on the site the compaction on the native soil (subgrade) was pretty low. I had
contractor work on it again before getting it to pass.
Later on I tested the pit run. I observed that the contractor used a roller compactor and water added
the soil. I reported the results to contractor.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/03/2021
File Name:
20075D06032021YK
Inspector's Signature:Inspector's Name:
Yannick Kabwika
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/04/2021
345b909c5362d83b-1622751411666 2
Inspection Date:
06/07/2021
File Name:
20075DFR06072021ADS
Inspector's Signature:Inspector's Name:
Andrew Sweet
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/08/2021
4a2d02640bacf398-1623082086711 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
08:45 AM
Client:
Headwater's Construction
Contractor:
Thompson
End Time:
10:30 AM
Inspection Type(s):
Earthwork Inspection
Location(s):
This duplex building from the West.
Observations/ Remarks:
I arrived on site at 9:15 a.m. I observed that they had already compacted the southeast and
southwest corners of the 5th duplex building from the West. The compacted 3/4” base was very dry as
it had been sitting over the weekend. My first test on the Southeast corner came up short at around 92
with only about 2% moisture. The numbers were similar on the southwest corner. I suggested that
they add more water and compact it one more time; they did so with a plate compactor, doing passes
running east to west and north to south. When I tested the southeast and southwest corners after that
compaction run i got passing scores of about 96 with about 4% moisture. I observed that they
compacted the other two corners in a similar manner, and they each passed.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/07/2021
File Name:
20075DFR06072021ADS
Inspector's Signature:Inspector's Name:
Andrew Sweet
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/08/2021
4a2d02640bacf398-1623082086711 2
Inspection Date:
06/07/2021
File Name:
20075DFR06072021DFA
Inspector's Signature:Inspector's Name:
D. Aust
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
e875ea11521d0ef1-1623108247101 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
02:30 PM
Client:
Headwater's Construction
Contractor:
Alpha Concrete
End Time:
05:00 PM
Inspection Type(s):
Concrete Placement
Concrete Reinforcement
Location(s):
Northeast building.
Observations/ Remarks:
I arrived when the concrete driver had approximately 5yds left of concrete. The contractor did not
schedule testing before the pour, which caused a lapse in observation of the pour. I tested the
concrete and found the results to be within tolerance. I observed the contractor wet setting the anchor
bolts and leaving large gaps between the concrete and bolts. I informed the foreman that that practice
was not acceptable, and that he needed to fill in the gaps to maintain structural integrity. I observed
the contractor rectify the issue. I observed the contractor utilizing a mechanical vibrator to consolidate
the concrete.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/07/2021
File Name:
20075DFR06072021DFA
Inspector's Signature:Inspector's Name:
D. Aust
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
e875ea11521d0ef1-1623108247101 2
Inspection Date:
06/07/2021
File Name:
20075DFR06072021DFA
Inspector's Signature:Inspector's Name:
D. Aust
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
e875ea11521d0ef1-1623108247101 3
Inspection Date:
06/08/2021
File Name:
20075DFR06082021AS
Inspector's Signature:Inspector's Name:
Alan Schiess
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
88e4e71eb0d121c0-1623166205884 1
4103 E 605 N Suite 1 Rigby, ID 83442 208.881.0081 www.connectengr.com
Daily Field Report
Project Name:
Teton River Flats
Start Time:
08:15 AM
Client:
Headwater's Construction
Contractor:
Affordable Concrete
End Time:
12:30 PM
Inspection Type(s):
Concrete Placement
Concrete Reinforcement
Location(s):
The interior slab of building B4 was poured.
Observations/ Remarks:
I arrived at 8:30, and waited until 9:45 for concrete to arrive. Pictures show the rebar that was used.
The concrete did have super plasticizer in it, making the slump of 7 acceptable. I reported the results
to David. The first two trucks arrived relatively close together, but the third followed the second by
about 45 minutes I did not observe any vibrating of the concrete to prevent a cold joint.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/08/2021
File Name:
20075DFR06082021AS
Inspector's Signature:Inspector's Name:
Alan Schiess
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
88e4e71eb0d121c0-1623166205884 2
Inspection Date:
06/08/2021
File Name:
20075DFR06082021AS
Inspector's Signature:Inspector's Name:
Alan Schiess
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/09/2021
88e4e71eb0d121c0-1623166205884 3