HomeMy WebLinkAboutOBSERVATION REPORT - 98-00029 - Fire Station - Ambulance AdditionJRW & ASSOCIATES
49 PROFESSIONAL PLAZA
REXBURG, IDAHO 83440
PHONE** (208) 359-2309
Fax: (208) 359-2271
PROJECT: RExBUR
- MADISON COUNTY AMBULANCE
LOCATION: REXBURG
ARCHITECT: ,IRW & ASSOCIATES
PRESENT AT SITE:
DATE: 3 AUGUST 1998
WEATHER: CLEAmmmmmw-w�_R
OBSERVATION BF:
,TORN WATSON9 RICHARD ELLIS9 ]RANDY HILL
WORK IN PROGRESS:
TEMP.: 8 5 0F
OHNNY'V�ATSON
EXCAVATION / RELOCATE GAS LINES /FORMING CONCRETE FOOTINGS
OBSERVATIONS•
CONTRACTOR REPORTED THAT GAS COMPANY WOULD NOT BE ABLE TO RELOCATE THE
GAS METER TO THE EAST SIDE OF THE BUILDING FOR 30 DAYS. APPROVAL WAS GIVEN
BY JRW TO RELOCATE THE GAS METER BY THE FRONT (WEST) PLANTER SINCE IT
COULD BE DONE IMMEDIATELY.
MIKE WALKER REPORTED THAT THE WATER HEATER WAS NOT ADEQUATE TO PROVIDE
HOT WATER - JRW WILL REVIEW WITH DOUBLE E CONSTRUCTION.
CONTRACTOR DISCOVERED THAT TIE EXISTING PLANTER FOOTING WAS 4 FEET
DEEPER THAN AS SHOWN ON AS -BUILT DRAWINGS.. IT WILL COST APPROXIMATELY
$2,800.00 TO BRING IN EQUIPMENT LARGE ENOUGH TO REMOVE THE CONCRETE. JRW
VERBALLY APPROVED THE PROCEDURE AFTER VERIFYING THE CONDITION.
CONTRACTOR REPORTED THAT THE EXCAVATION SUBCONTRACTOR REMOVED
APPROXIMATELY 12 INCHES TOO MUCH MATERIAL IN THE FOOTING TRENCH. HE WAS
DIRECTED TO EITHER EXTEND THE FOOTING OR PROVIDE ENGINE
TQ THE OWNER.
ERED FILLATNO COST
JRW DIRECTED THE CONCRETE CONTRACTOR TO MAKE CERTAIN THE FOOTING
TRENCHES ARE COMPACTED BEFORE INSTALLING REBARs JRW WILL VERIFY
COMPACTION.