BUILDING INSPECTION SEQUENCE
Type of Inspections: For on-site construction, from time to time the building official, upon
notification from the permit holder or his agent, shalt make or cause to be made any necessary
inspections and shall either approve that portion of the construction as completed or shall notify
the permit holder or his agent wherein the same fails to comply with this code.
1. LAY -OUT: Lot corners staked, staking in place for building, prior to excavation:
2. FOOTING: Commonly made after poles or piers are set or trenches or basement
areas are excavated. Forms and horizontal reinforcing tied in place,
vertical reinforcing cut and on job site or tied in place.
3. FOUNDATION INSPECTION:
4.
5.
6.
The foundation inspection shah included excavations for thickened nabs
intended for the support of bearing walls, partitions, structural supports, or
equipment and special requirements for woad foundations. ASI farms and
reinforcing steed, eta,, shadl be in place.
PLUMBING, MECHANICAL AND ELECTRICAL:
Rough inspection: Commonly made prior to covering or concealment,
before fixtures are set, and p
TRUSS INSPECTION:
inspections of trusses.
FRAME INSPECTION:
rior to framing inspection.
Commonly made after the roof, all framing, firestopping, draftstopping and
bracing are in place and after the plumbing, mechanical and electrical
rough inspections are approved. (Electrical �nspecfion performed through
State of Idaho Electrical Bureau)
7. LATH AND/OR WALLBOARD INSPECTION.q
Commonly made after all lathing and/or wallboard inferior is in places but
before any plaster is applied, or before wallboard joints and fasteners are
taped and finished.
8. FINAL PLUMBING AND HEATING INSPECTION:
All systems in place, fixtures set, ready for occupancy
9. SIDEWALK INSPECTIONS:
After forms are set, prior to placing concrete.
10. FINAL INSPECTION:
Commonly made after the buildingis completed and ready for occupancy.
11. OCCUPANCY PERMIT:
Issued when, on final inspection, building is ready to occupy.
12. OTHER INSPECTIONS,
In addition to the called inspections above, the building department may
maks or require any other inspections to ascertain compliance with this
cede and other laws enforced bv the building department.
INSPECTION CARD
The permit holder or has agent shall post the inspection record on the doh site in an accessible
and conspicuous place to allow the bL.A;`11ding official to make the required entries. The record
shalt be maintained by the perm 't holder until the final inspection has been made and appraved.
have read the above and will comply in my requests for inspections by giving 24 HOUR
NOTICE prior forinspections to be made.
Electrical: 624-3767 Building.- 359-30213 ex 325 or 313
Plumbing: 359-3020 ex 32Por 313 or X59-3(334
Signature.7.,
Date: