BUILDING INSPECTION SEQUENCE
Type of Inspections: For, an -site construction, from time to time the building official, upon
notification from the permit holder or his agent, shall mike or cause to be made any necessary
inspections and Ghali either approve that#,portion of the construction as completed or shall notify
11 He permi noiuer or nes agent wnerein the same Taiis io comply ►rvitn anis coae.
1. LAYO U T: Loorners staked, staking in place dor building, prior to excavation:-,
2. FOOTING: Commonly made after poles or piers are sit or trenches or basement
areas are excavated. Forms and horizontal reinforcing tied,. place,
vertical reinfarcincg cut and on job site or tied i n place.
3. F0UhIDAT10N INSPECTION.
Y rt
The foundation.1 ispeetion,---shall included �xcauations for thickened slabs
in ended for the support of bearing walls, partitions, structural supports, or
equipment and speciaVrequirements for mood foundations. All forms and
-
,A 'reinforcing steel, etc,, shall be in place,
4. PLUMBING, MECHANICAL AND ELECTRICAL:
Rough inspection.- Commonly made prior to covering or congealment,
before fixtures are set, and prior to framing inspection..
5. TRUSS INSPECTION:
Inspections of trusses.
6.Q FRAME INSPECTION.
Commonly made after the roof, all framing, firestopping, draftstopping and
171A� bracing are in place and after the plumbing, mechanical and electrical
�' rough inspections are approved. (Electrical inspection performed through
` State of Idaho Electrical Bureau) '�� ��= � _-
Lj,�� �
7. LATH AND/01R. WALLBOARD INSPECTION:
commonly made after all lathing and/or wallboard interior is in place, but
before any plaster is applied, or before wallboard joints and fasteners are
taped and finished.
8. FINAL PLUMBING AND HEATING INSP-ECTION:
All systems in place, fixtures set, ready for occupancy
9. SIDEWALK INSPECTIONS:
After forms are sed, prior to placing concrete.
10. FINAL INSPECTION:
Commonly mads after the building is completed and ready for occupancy .
11. OCCUPANCY PERMIT:
Issued when, on final inspection,- building is ready to occupy.
12. OTHER INSPECTIONS:
In addition to the called inspections above, the building department may
make or require any other inspections to ascertain compliance with this
code and other laws enforced by the building department.
INSPECTION CARD
The permit holder or his agent shall post the inspection record an the job site in ars accessible
and conspicuous place to allow the building official to make the required entries. The record
shall be maintained by the permit holder until the final 'inspection has been mads and approved.
have read the above and will comply in my requests for inspections by giving 2-4 HOUR
NOTICE prior for inspections to be made.
Electrical: 356-4830, Building: 359-3020 ex 341 or 313
Plumbing: 359-3020 ex 341 or 313 or 359-3034