Daily Field Report
Project Name:
The Grove
Start Time:
05:15 AM
Client:
Stillwater Equity Partners
Contractor:
Kevin Virgin Construction
End Time:
09:00 AM
Inspection Type(s):
Concrete Placement
Location(s):
Northeast valley gather of building #6.
Observations/ Remarks:
I arrived at the site at 5:50 am. However the contractor started the pouring at 5:00 am. I tested and
reported the test results to both the contractor and the truck driver.
Items observed are in general conformance with approved project documents and jurisdictional requirements.
Inspection Images:
Inspection Date:
06/16/2021
File Name:
20001CP06162021YK
Inspector's Signature:Inspector's Name:
Yannick kabwika
Reviewer's Signature:Reviewer's Name:
E. Vail
Reviewed Date:
06/17/2021
345b909c5362d83b-1623852628528 2