OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
Fisher
Fisher Hamflton 1s pleased to have had the privilege of
furnishing your laboratory equipment. This is a major
investment, arra+ year equipment is built to withstand extremes
of temperature, stress and corrasion provided you give it
reasonable care and use.
Thi's manual gives you full information for the operation and
care of fume hoods and oilier Fisher Hamilton equipment
items.
Utility and fine appearance can be assured for many years by
following simple procedures, R regular schedule of
maintenance will be most effective.
If you have a special problem or would like extra copies of this
manual, write to the Technical Service Department, Fisher
Hamilton, Two Rivers, Wisconsin 5424 1.
Table of Contents
GENERAL INFORMATION .... , .................
Y .... Y . ---
General ........... . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . .
Perchloric Acid Hoods ... . ...........
Y .......... o .
.
HODdIdentification ..............................
...
INSTALLATION•••.e••.Y..•.•.••••,....•...•••..,•-1
Fume Hood Superstructures .........................
Floor -Mounted Funs Hoods ..... ...................
–
H PE IV Fume Hoo ..........................
10-11
Air Chamber, Auxiliary Air Fume Hoods .................
11
Baffles ...... .. .. ... ...............
12-13
Safety Meld ...... .........................1
1
Blower EnclosuresY ■ e . .
Fane Hood Monitors...... Y . ...................
Y ..
1
Exhaust Filtr Assembly ............................1
I 9 n i I e l i c Gauge . . • ■ ■ . • • I . . • • e . • • •
. . • . . Y . . • • . . i -.19 .1+ar
WARN MG/OPERATiINSTRUCTIONS .•••..•••..••••.••••
20
MAINTENANCE AND ADJUSTMENTS .•••
•}•.•.■••••■.• 1 –27
General aInt , L b M e . . • . . . . • . ■ . • • •
• . . , , ■ . • • i • • , ..
1
Fume Hood I ■ . . . r . . ,. . . . ■
. . . . .. ■ ■ �■ . . ■ ■ . .
1
How to Replace Fluorescent Light Tubi
21-22
Servicing 7 um Hood Fixtures � ■ . • • Y . ■
• . l= F r i . . . • .. . .. . ■
22
Cleaning Fume Hood Interiors
.. ■ 22
Replacing O Glass and Cables
– 25
Serviclng Supplyti!hamberirFiltr...■r•F4si■■••.■...
26
Exhaust Filtr Replacement .•....•••.••••....•..•....
26
'dower RPMdI'u t nt ■ ..... ..............•........
2
7A
Manometer, on it ri n Exhaust Filters .............
Y ...
F 27
FIELD TESTING .. + . ... e ... ......................
. 28-30
TR UBLF H TIN ..............................
—.31
GENERAL
Fume hoods are exposed to extremes of temperature, reagent
fumes and working surface abuse. Regular care will prolong
service life and insure safe working conditions.
The exhaust system and blower of a fume hood mist function
properly for safety. Maintenance personnel should service the
fan and motor assembly regularly, lubricate as required, and
make sure that the exhaust system is free from obstructions.
Semiannually, accumulated deposits should be removed from
the impeller blade and housing.
A simple test with lighted match or smoke will show if the air is
being drawn into the hood. More accurate checks of air velocity
can be made with a thermal anemometer. See inspection and
Field Evaluation procedure.
Always place equipment and apparatus as far back into the
fume hood as possible since this provides greater assurance of
proper fume collection and removal.
Large, bulky apparatus or equipment should be placed in the
fume hood to permit air flaw around it, and never placed so as
to interfere with the operation of the baffle system. Raise large
A
tems an inch or two above work surface. Spilled liquids, acids,
or corrosive materials should be immediately wiped up and the
surface neutralized with water or the proper neutralizing agent
so as to prevent damage to the work surface and the hood
interior or to apparatus and equipment installed in the hoar.
Remember that special fume hoods are rewired for the
handling of Perchloft Acid. See next page.
Fisher Hamilton
2
PERCHILORIC ACID HOODS
FE IREq � LABORATORY FUME HOODS
OPERATION, 1NTENANCE AND INSTALLATION INSTRUCTIONS
The properties of perchloric acid require that a specially
designed fume hoed be set aside for exclusive use with this
material. The hood is equipped with a cold water spray device
for washdown of the interior surfaces. A trough is placed
across the back of the hood for collection and disposal of
washdown waters. operating personnel should be well trained
in the proper handling techniques and be familiar with the
characteristics of this materiad.
Frequency of washdouvn, both hood interior and exterior
system, is determined by the usage and concentration of
reagens. This can range from a weekly procedure to one that
occurs after every use. Washdown should always be followed
by an inspection to verify that all areas are ciealn and that the
wash system is functioning properly.
Some of the hazards of Perchloric acid which justify the use of
a special hood are:
1. Perchloric acid is a very strong acid, capable of producing
severe burrs when in contact with skin, eyes or respiratory
bract.
2. As an aqueous solution, it can cause violent explosions if
improperly handfed.
3. It reacts with other substances to form unstable materials
which are susceptible to exploding either by impact, friction,
or spontaneous combustion.
Persons using perchloric acid should be thoroughly familiar with
its hazards. Many reported laboratory accidents have involved
less than one gram of reactant. Listed below are some common
safety practices that should be followed-
Spilled
perchloric acid should be thoroughly washed away
with large amounts of water.
• The use of organic chemicals or materiels in the hood should
be avoided.
• Goggles or other effective eye protection should be used
whenever possible, as well as utilization of the fume hood
sash for additional safety.
• Gas flames or ail baths should not be used within the hood.
organic chemicals should not be kept in storage areas sed
aide for perchloric acid storage.
A schedule should be made for regular washdawn and
inspection of load interior, ductwork and blower to guard
against abuild-up of dangerous perchloric materials.
•
Only a fluorocarbon grease should be used as a flower
lubricant, since any other type is to be considered potentially
hazardous.
• Washdown procedure should be performed after completion
of usage with all apparatus removed from hood,
HOOD IDENTIFICATION
Louver
Panel
� 1
ti
0
_ 0
Sash
ask
Acte
Panel
Lire
Item/Room No...
,Job,; Unit No_ . .
Product Nu_
escriplorl
Project Name . .
Shop Order No.
Barcode N
Fisher Hamilton Inc,
Item: 15,8C
Two Rivers, WI 54241
Ream: 207
Side
Panel
2 -Part Label
(vacated
on backside
of collar and
inside of
Iouver panel)
Tx 394381 012 Fl012M Lfnit, 0005093
FH3943810244 Entity:
Desc: 1C54L$36PD —DWG. H1301
Project Name: RICA UNIVERSITY --ULD CHEMISTRY
Shop Order #: 161914 P.O. leo.: 22492I26108
Cir:
I I! �II��� � III I I IIII� II I IIII G1
918021957
NC RATED
Placed on backside of collar
Placed on inside
of louver panel
co
C J
Dimensions are nominal and illustrations and specifications are based
0 Fisher Hamill n Cn the latest product information available at the time of publication,
The right is reserved to make changes at any time without notice. 3
SAFEAIREC"' LABORATORY FUME HOODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
FUME HOOD SUPERSTRUCTURE INSTALLATION
Side Enclosure Panels
1. Laver the side panel into the side frame of the fume hood
superstructure, engaging the frame's laver lip. While
pressing down an the two black catches, rotate the side
panel and engage the frame's upper lip. Gently apply
additional pressure to the panel and release the catches to
secure the narael to the hoed.
Catches
L
heppIng
Screws
1
2. Remove two (2) shipping screws that secure the counter-
balance weight pay to the rear top rail.
3. Remove screws from sash hall -down clips. open the sash
and remove blacking, being Careful not to damage sill or
baffles.
NOTA:
Baffles
can be installed at
this time,
or after the hoar is
in place
an the
work
surface.
See
Pages 12-13.
0
RD
4. Remove shipping screws holding the fume hood frame to
the skid. Save four (4) of these screws, No. 10 X 5/8117 to
secure hood to the work surface.
5. Place the fume hood an the work surface taking care to
protect the work surface.
6. Remove two (2) shipping screws from the top of the Lauver
panel. These screws must be removed to allow future
access to the fluorescent lights.
i. Check the following items:
That the counterweight operates free of obstructions.
• That the cables align properly in the pulleys.
• That there is proffer horizontal sash alignment and
counterweight balance.
• That the sash does not bind in the sash guides.
8. Grill two (2) each 1/8'' diameter pilot holes of each side
structural frame into the work surface and secure same
with four (4) Na. 10 X 518" screws saved from the
shipping skid.
9. Reinstall end panes.
10. Caulk hood to work surface with silicone sealant.
Dimon,5ions are nominal and illustrations and specifications are based
on the latest product information available t the tirre of publication.
The right is reserved to make changes at any time without notice.
F1 h !` Na Ilton
FE I EC"}r LABORATORY FUME MOODS
OPERATIONMAINTENANCE AND INSTALLATION IN T TI N
ASSEMBLY INSTRUCTIONS FOR KNOCKED -DOWN
FLOOR -MOUNTED FUME HOODS
General - 1IU'hen receiving fume hood assemblies, inspect for
damage immediately, If damage is noted, request the delivering
carrier to nate and describe damage on dill of lading prior to
your signature. Notify carrier immediately and request
inspection.
Open boxes and gyrates and examine for hidden damage. If
damage is noted, save containers and request an inspection.
Move all components to installation area.
1.
Attach ]off -hand side assembly (2) to back assembly (1).
Take hack panel assembly and stand vertically, as shown,
and slide into end assembly. (Angle flange of end assembly
fits between back panel and horizontal members of back
assembly). Secure each corner with two #8 7S 5f8°` PPHSMS
at mating holes an top and bottom cornea of joined
assembly. Repeat steps with right-hand end (3). Attach each
baffle support with two each #8 X 3/41, PPHTCS through
back panel into support. Do not over -tighten.
10 /8.11 PPHSMS
5 m 1ki
9
TOP
1
�d
¢X
REAR PULLEY
BRACKET ASSEMBLY
BLY
Attach tap assembly (4), as shown at left, to
hack and ends with eleven (11) #10 x 5/8"
PPHSMS. Top assembly fits underneath right-
hand rear pulley bracket assembly. Secure
exhaust collar to rear rail_
Dimensions are nominal and illustrations and specifications are based
0 on the latest �
EI1'�!'' �I�l��l��� product inf�rr���i�n available a� t�� ti��r`i� �f ubsiation.
Fhe right is reserved to male changes at any Urne without notice.
5
SAFEAIREO" LABORATORY FUME HOODS
OPERATION5 MAINTENANCE AND INSTALLATION INSTRUCTIONS
ASSEMBLY INSTRUCTIONS FOR KNOCKED -DOWN FLOOR -MOUNTED FUME HOODS
3. Attach lett rear pulley assembly (5) using three (3) #S X 5/8''
PPHSIVIS. Attach right rear plate assembly (6) using three (3)
#8 X 5/81, PPHSMS. Slide 311 sheave (7), then 2" sheave (8)
over threaded stud. Loosely fasten with 1/4-20 KEPS nut.
Install right-hand cable retainer support (27) using two (2)
#8 X 5/81, PPHSIVS.
4. Remove pieces of tape (9). holding top panel extrusion in
place. Lift header panel (11) and place bottom in right-hand
and left-hand baffle cliffs (10) . (Short header panel - bypass
hoods, does not have baffle clips). Bottom extrusion on
header panel faces outward. Fasten tai of header panel to
angle with #8 7( 5!8" PPHSIVIS.
# 5/8" PP
Dimensions are nominal and illustrations and specifications are ba -sed
on the latest r)r du t Information available at the lime of publication.
6 The right is reserved to male charges at any time without notice.
u
Fisher Hamilton
En
Lwn
SAFEAIRE° LABORATORY FUME HOODS
OPERATION5 MAINTENANCE AND INSTALLATION INSTRUCTIONS
ASSEMBLY INSTRUCTIONS FOR KNOCKED -DOWN FLOOR -MOUNTED FUME HOODS
5. Instal! four (4) baffles as indicated.
Install baffles with notches down.
Proceed from bottom to upper baffle
(1 2, 13, 145 15). If remote central is
included with hood, place
intermediate baffle (14) in already
installed remote control baffle arm
(1G). Lower and intermediate baffles
are the same size. Insert upper baffle
into collar extrusion per Detail `jB".
Test remote control baffle adjuster for
function.
6.
Install rear top sash (17) in right-hand and left -Band rear
sash guides. Sashes ars installed from the tap of the hoed.
Lower the sashes into the sash guides. The rear tap sash
mist be located above the stops located approximately half
way up the sash guides. Locate the front bottom sash (18)
the front right-hand and left-hand sash guide. Remove the
tape from the cable assemblies that are taped to each gash.
Uncoil the gable and place on toy of hood,
(b Fisher Hamilton
COLLAR
r
D'Imensions are nornrn-i'7-i l and illustrations and specifications are based
on the latest prodLict -Information available at the time of publication.
The right 'is reserved to make changes at any time without notice, 7
SAFEAIRE`�" LABORATORY FUME HOODS
OPERATION5 MAINTENANCE AND INSTALLATION INSTRUCTIONS
ASSEMBLY INSTRUCTIONS FOR KNOCKED -DOWN FLOOR -MOUNTED FUME HOODS
Retainer Must 0.06216
Not Touch
w
Sheave
DETAIL `055
7. Before hood is pushed against walk, place tap rear sash
cable (19) over pulleys as shown in instructions. Brace
bottom of sash about 6`1 above sash stops,. with 2 x 4 or
similar, to allow for a more manageable cable. Attach weight
(20) to cable, Detail "'C". Fasten cable clamp (23) and two
(2) 114-20 X 3l4 HHTCS (24}, do not completely tighten
screws. Repeat process with front bottom sash cable (21).
Test sash level, alignment and travel. Make any necessary
atljustment. If necessary, fine tune weight pan. Fasten clamp
screws tightly. Attach all cable retainers (22, 25). Do not
aver -tighten retainers — allow 1/16" for pulley movement. Sege
Detail "D'`. The nylon gape (25) at the cable loops at the ends
of the sash pull is no danger necessary, remove and discard.
S. Position flume hard in a permanent location. Have qualified
personnel attach all required electrical devices and plumbing
fixtures. Lower the side panel (27) onto the side frame of the
fume hood, engaging the frame's lower lip. While pressing
dawn an the two black catches, ratan the side panel and
engage the frame's upper lip. Gently apply additional
pressure to the panel and release the catches to secure the
panel to the hood.
I
F
FRONT
OF
,O'H00D
Dimensions are norninal and illustrations and specifications are based
an the [atest product information available at the tine of publication.
8 The right is reserved to make changes at any time without notice.
Fisher Hamilton
C!n
SAFEAIREG' LABORATORY FUME HGODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
ASSEMBLY INSTRUCTIONS FOR KNOCKED -DOWN FLOOR -MOUNTED FUME HOODS
9. Attach lintel panel (28) to tront of hood. Fngage top of
panel with studs on top, inside of front access panel and
fasten bottom of panel to angles on front access panel with
#8 X 5/8" PPHSMS. Drive screws as shown.
10. Make sure hood is square and aligned.
Fisher
Hamilton
# 8 X5/8 III
Dimensions are nominal and illustrations and specifilcations are based
1Dn the latest product inficirmation. available at the time of publication..
The right is re -served to make changes at any time without notice. 9
SAFEAIRE° LABORATORY FUME HOODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
HOPEC IV FUME HOOD INSTALLATION
1. Install and level two fume hood base cabinets with rear
fillers and kneespaGO panel as required.
2. Depending an height requiremen#s, instal either the tai filler
frame assembly alone or in combination with the optional -
height filler frame.
If the TOP FILLER FRAME ONLY IS
REQUIRED, insert rough assembly into top,
filler frame and locate front lower edge of
trough flush with cabinet or optional height
filler. Secure to the base cabinet using
eight (8) No. 10 X 5/81' PPHS MS through
the side returns of the Top Filler Frame into
the front and reap returns of the base
cabinet.
if the OPTIONAL HEIGHT FILLER FRAME
IS REQUIRED, it is installed by aligning
it's bottom 3/4'' return on the base
cabinet and securing with (4) No. 10 X
518" PPHSMS screws. Insert through
assembly into Top Faller Frage and locate
brant lower edge of trough flush with
cabinet or optional height t1iler. Attach the
Tip Filler Frame to the Optional Filler
Frame using eight (8) No. 10 X 5/811
PPHS,MS through the side returns of the
Tap Filter Frame into the front and rear
returns of the base cabinet.
in
HOPED I` Hood
3611
Work Surface
Height
End view showing HOPEC HOPEIV hood,
Top Filler Frame and Base Cabinet.
End view shoving HOPEC IV hood,
Top Filler Frame, Optlonal Height
Filler and Base Cabinet.
Tr
f� `
4U.
Work
ace
If
Run silicone
sealant head
on back flange
trough. Place work
surface into frame
and onto trough
flange.
urface
ht
Lower front —
edge of trough
should be flush
with f rnt of
cabinet
Trot
.r
1
Tod Filler
Frame
Base
Cabinet
10
'T
Trim silicone s
sealant bead
on back flange of
trough. Rau work
surface into frame
and c roto trough
flange.
O ptlonal
Height Filler
Dimensions are nor sinal and illustrations and specifications are based
oil the latest product information available at the ti.rne of publication.
The right is reserved to make changes at any time without notice.
i
�0
Top Filler,
Frame
7
Base
Cabinet
0 Fisher Hamilton
D
ka
SAFEAIRE®R LABORATORY FUME HOODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
HOPEG IV FUME HOOD INSTALLATION (cont..)
Trough Frornt Work Surf ac a
Horruntaf Ralf
Drain Tues
Mush BeFlush
Top Filler
Frame
Base
Cabinet
3. Set the fame hood trough onto the tai filler frame. The rear
edge of the trough wIl( set over the front horizontal rail and
the return edge on the trough will secure it in place.
NATE: If a drain tube is required, it should be installed at
this time. The tube is located at the left end of the trough
and is fed through the fop of the left Viand base cabinet into
a one gallon container.
4. Install poly vent, if required, through pre -drilled hales in the
backs of base cabinets. The tail piece of the vent is supplied
with a double compression assembly to lock it in place.
5. Seal the tap edge of the trough assembly with a RTV silicon
or other applicable sealer and thin place the fume hood
words surface into the Top Filler frame. If base cabinet poly
Ve11f5 are used, align them to the pre-cut holes. in the work
surface.
6. Install cupsinks if require. The fumy hood bass cabinets are
supplied with ire -punched Boles in the back panels above
the stony liner for cupsink drains. Cupsink assemblies are
supplied with the sink, an extension pipe, an elbow, and a
pipe section that protrudes through the hole in the base
cabinet back. The cupsink assembly is designed to fit two
conditions.
A. When the fumy hood assembly is supplied with the
Optional Height Filler Frame, the cupsink assembly is
fished through the sink cutout hale in the work surface
and the train line hole at the rear of the base cabinet.
B. When the fume hood is supplied with only the Tap Filler
Frame, the extension pipe below the cupsank is removed
to maintain alignment with the base cabinet rear drain
hale. The pipe extension should be saved in the event
that the Optional Height filler Frame be required at a later
date.
7. Move the HOPFC IV fume hoar to the area of installation.
Perform Steps 1-10 an Page 4.
(V Fisher Hamilton
INSTALLING AIR CHAMBER — AUXILIARY AIR
FUME HOODS
Up
r
31ot
1. With hood on work surface, lower air make-up tubing to
expose four (4) mounting Holes in galvanized frame. Install
screws into upper mounting hales, tightening halfway.
2. Lift the air chamber up and onto the upper mounting screws.
Two people are required for this Procedure, vfle at each end
of the chamber. While chamber is supported by the upper
screws, install the lower mounting screws. Tighten SII
maunting screws securely.
3. Lift make-up sir tubing
back up and
into FVC
elbows at ends
of air chamber. Secure
with screws
provided
with
elbows.
Filler
Front -----_____
Access
Post
Screws
4. Instill the left- and right-hand fillers along with two (2}
screws each side, accessible from inside the air chamber.
Screw 4
5. install louver panel by hooking tai edge into studs in
chamfer. Secure with three (3) screws.
6. Install sash enclosure by hooking top frame flange onto
offset angle on back of air chamber.
Dfinerion-s are nominal and Illustrations and specifi[cations are based
on the latest product information available at the time of publication.
The right is reserved to make changes at any time without notice_
I I
FE I RE','�' LABORATORY F E FOODS
PER TI N 9 MAINTENANCE ANCA INSTALLATION IN TRU TI N
BAFFLE INSTALLATION AND ADJUSTMENT
Fisher Hamilton provides two choices of baffle design
concepts:
1. Multi -position fixed.
2. Remote exterior control
Baffle Installation
Install baffles according to information ars the net page.
Seg label located on interior riga-hand wail for repositioning
instructions for Multi -Position Fixed Baffle. See label located
an right front past for Remote Exterior Baffle adjustment
instructions.
A — Normal Exhaust.
Requirements
i)
I
I'
B — High Feat Loads or
Lighter -Than -Air ban -Air Gases
Baffle Adjustment
Fisher Hamilton fume hoods have three baffle settings:
A. Normal or Average.
B. Lighter -than -Air or high thermal loading.
C. Heavier -Than -Air
Position. A is for normal exhaust requirements. Locate baffle in
center of movement arc. All slots are functional. This baffle
position is suitable for most fume generating activities.
Baffle position B is for lighter -than -air gases, or' high heat
loads. The tap slot is open to maximum. The upper portion of
perimejer slot is operational. The intermediate horizontal slat is
operational and bottom slot is restricted. Fume hood air flow is
concentrated in the upper portion of enclosure for efficient
capture and exhaust of 'lighter -than -air fumes and hot gasps.
The baffle at position C provides maximum air flow across the
work surface for the collection and removal of fumes generated
at the work surface and heavier-than-air gases. In this POSMOn,
perimeter slot and intermediate slot remain open and
operational, top slot is closed.
— Heavier -Than -Air Gases
and Surface Fumes
Dimensions are nominal and illustrations and specifications are based
on the latest product 'information available at the time of publication.
12 The right is reserved to make charges at any tirtle without notice.
Fisher Hamilton
0
SAFEAIREf� LABpRATORY FUME HODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
BAFFLE INSTALLATION AND ADJUSTMENT (cont..)
Installing Multi -Position Fixed Baffle
1. Place top baffle into position by engaging top edge into
front exhaust collar extrusion. Lift baffle up and into upper
support brackets to lack into position.
2. Place center baffle iota desired exhaust position by engaging
top edge into appropriate slats on bottom of uppermost
baffle support brackets, see positioning label on right-hand
side panel, Lift and lack baffle into position.
3. Place lower baffle into proper position. Lift and lack baffle
into lower support brackets.
Exhaust Collar Extrusion
Top
Baffle
Upper Support Bracket
Battle Posrtjon[ng Label
Center
Baffle
Lower Support Bracket
Lower
Baffle
Installing Remote Exterior Control Baffle
Place top baffle 1into position by engaging top edge into
brant exhaust collar extrusion. Lift baffle up and into upper
support brackets to lock into position.
2. Align forked end of remote arm with any of three (3) slots in
right-hand upper baffle support bracket. Lift Center baffle up
and into slats in upper baffle supports, being sure to capture
right-hand edge of baffle between fingers of remote control
arm. Lift and Irick baffle into position.
3. Place lower baffle into proper position. Litt and lock baffle
into lower support brackets.
Dimensions are nomin � and illustrations and specifications are loosed
Fl h r Hamilton on the latest product information available at the ti -me of pubiication.
The right is reserved to make changes at anytime without notice.
Top Baffle
Center Baffle
(Remote)
Center Baffle
(Fixed)
and Lower Baffle
13
SAFEAIRE' LABORATORY FUME HOODS
OPERATION,, MAINTENANCE AND INSTALLATION INSTRUCTIONS
INSTALLING SAFETY SHIELDS IN RESTRICTED BYPASS, CONSTANT VOLUME BYPASS, AND RADIOISOTOPE
FUME HOODS
1.
Locate
shown.
ower track assembly according to dimensions
2. Use lower track assembly as template for locating holes.
Drill .128" diameter holes in sill as illustrated, through
existing holes in track assembly.
3. fasten track with No. 8 X 318" PPHSMS.
Left Bumper
Hood Width
34.6211
Right Bumper
Retainer
60-011
46.62" 48.5611
72.011 58.621 60.5611
96.011 6214 84-5611
91''
4, Locate upper retainer n roar flange olouverecl panel.
Locate retainer .91" (29/321 from inside edge of front
vertical panel. Drill .128" diameter moles using retainer
template. Fasten, with No. 8 X 3/81, PPHSMS.
. Position and fasten bumpers using No. 8-32 X 3/4" PPHM ,
washers and hex nuts.
6. Install safety ,mild by inserting top into upper retainer
h nn l then lowering bottom (with rollers) into lower track
assembly.
' linen i ns are nominal and illustrations and pecificationc; are based
tri th2 latest product inforrnation available, at ith t`me of publi ation, Fisher Hamilton
14 The right is reserved to make charges at any tirne without notice.
4L
SAFEAIRE° LABORATORY FUME HOODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
INSTALLING SAFETY SHIELDS IN AUXILIARY AIR FUME HOODS
1. Locate lower track assembly according to dimensions
sawn.
2. Use lower track assembly as template for locafing holes.
Drill .128" diameter holes in sill as illustrate, through
existing holes in track assembly.
3. Fasten track with Na. 8 X 3/811 PP.HSMS,
4. Locate upper retainer on rear flange of louvered panel.
Locate retainer .91" (29/32") from inside edge of front
vertical panel. Drill .128" diameter holes using retainer as
template, Fasten with No. 8 X 3/8" PPHSMS.
5. Position and fasten dumpers using No. 8-32 X 3/41, PPHMS,
wasters and hex nuts.
fi. Install safety shield by inserting top into upper retainer
channel, then lowering bottom (with rollers} into lower track
assembly.
0 Fisher Hamilton
Left Bumper
Hood
Width
Dimensions era-nominai and Illustrations and spe6fications are based
on the latest product Information available at the time of publication_
The right is reserved to make changes at any time, withcwt notice,
31"
Lower
Right Bumper
Upper
Track Retainer-
34.62
etarn r4. EI 36.56
46..62,1
621.1
82,62"
48.5611
60,56"
84,5611
on
1.87"
15
SAFEAIRET' LABUHHlunt' ruivllc nvwu0
QPERATlOW, MAINTENANCE AND INSTALLATION INSTRUCTIONS
INSTALLING CEILING ENCLOSURE TO FUME HOODS OTHER THAN AUXILIARY AIR AND POSTLESS SASH
Hardwire
included:
1 - Front
panel
1 - Front
panel-removable
2- Side panels
2- Front
support brackets
2- Rear
support brackets
1 -
Bag assembly
Tools required:
#2 Phillips screwdriver.
Di r�
{
.f
� P
ti• k
1. Fasten support brackets (1) in front top of frame assembly in
holes provided. Use 1/4-20 X 3/4.11 hex head thread cutting
screws (HHTCS) (2) furnished in bag assembly to fasten
buckets.
2. Fasten rear supporl (3) to year tap of frame assembly. Use
No, S X 51S" Phillips. pan head sheet. metal screws (PPHSMS)
(4) furnished in bag assembly.
3. Install right-hand (5) and left-hand (6) side panels to
supports using Na. S X 5/81' PPHSMS (4).
tis �
S
k
4. Install front pane! (7) to side panels with No. 8 X 5/$"
PPHSMS.
5. Subassemble thumb screws (8) and push retainers (9) to
removable panel (1U).
6. Insert hole fasteners (11) in larger hole in flange of side
panels.
7. insert dap flange of removable panel under and behind front
panel. Fastin thumb screws and tighten.
Dimensions are nom;nal and illustrations and specification are based
on the latest product information °vol t t� time of pu�li�ati��,
The right is reserved 1c) make changes at any time without notice.
usher Hamilton
D
FEAIRE'L�' LABORATORY FUME HOODS
OPERATIONS MAINTENANCE AND INSTALLATION INSTRUCTIONS
INSTALLING CEILING ENCLOSURE TO AUXILIARY AIR FUME HOODS
Hardware included:
I - Frost panel -removable
2 -Side panels
2 -Fant support brackets
2 -Rear support bracket
1 -Bag assembly
Tools required:
#2 Phillips screwdriver.
ir
1.
Fasten support brackets (1) in front tap of frame assembly in
holes provided. Use 114-2Q X 3/4'' hex head thread
cutting screwy (HHTCS) (2) furnished in bag assembly to
fasten brackets.
2. Fasten rear support (3) to rear top of frame assembly. Use
No. 8 X 5/8" Phillips pan head sheet metal screws
(PPHSMS) (4) furnished in bag assembly.
3. Install right-hand (5) and left-hand (6) side panels to
supports using No. 8 X 5/8" PPHSMS (4).
Fisher Hamilton
4. Install clips (12) into top square holes of removable pane!
(1.0).
5. Subassemble thumb screws (8) and push retainers (9) to
removable panel (10).
6. Insert hole fasteners (11) in larger hale in flange of side
panel.
7. Insert clip of tap flange of removable panel into square holes
of side panels. Fasten thumb screws and tighten.
Dirnenslons are norninal and ilfustrations and specifrcations are based
on the latest product information available at the time of publication.
The right is reserved to male Changes at any tune without notice.
17
SAFEAIRE(�) LABORATORY FUME HOODS
OPERATIONy MAINTENANCE AND INSTALLATION INSTRUCTIONS
INSTALLING CEILING ENCLOSURE TO POSTLESS SASH TYPE FUME HOODS
Hardware included:
2 - Front panels
2 -Front panels -removable
2 - Side panels
2 -Front support brackets
2 -Rear support brackets
2 - Middle support brackets
1 -Bag assembly
Tools required:
#2 Phillips screwdriver.
1. Fasten support brackets (1) in front tap of frame assembly in
holes provided. Use 114-20 X 314.. hex head thread
cutting screws (HHTCS) {2} furnished in bag assembly to,
fasten brackets.
2. fasten rear support (3) to rear top of frame assembly. Use
X10. 8 X 5/81' Phillips pan head sheet metal screws
(PPHSMS) (4) furnished in bag assembly.
3. Install right-hand (5) and lefl-hand (6) side panels to
supports using No. 8 X 5/8'' PPHSMS (4).
4. Install two middle supports
No. 8 X 5/8" PPHSMS (4).
(12) to louver panels with fain
k
I �
I �
k
I �
k
5. Install front panels (7) to side panels and middle supports
using No. 8 X 5/81, PPHSIVIS (4).
6. Subassemble thumb screws (8) and push retainers (9) to
removable panels (10).
7. Insert We fasteners (11) in larger hale in flange of side
panels.
8, Insert top flange of removable panels under and behind front
panels. Fasten thumb screws and tighten.
Dimensions are norninal and illustrations arld pecificatiorls are based
on the latest product information available at the CME) of publication.
18 The. right. is reserved to make changes at any time without notice_
Fisher Hamilton
0
FE I BE'��' LABORATORY FUME E DODOS
OPERATION9 MAINTENANCE AND INSTALLATION IN TR TION
FUME HOOD MONITOR
Models 54L0335 and 54L0405
proper flume hood operation is key to laboratory safety; comfort
and energy management. OSHA requires that iaboratories take
measures to ensure proper and adequate operation of fume
hoods. Recommendations include the use of a continuous air
monitoring device, The ANSI Z9.5 and NFPA 45 standards
reinforce these requirements.
Fisher Hamilton monitors have the ability to monitor true fame
hood face velocity using thermal sensors located in the
instrument. The thermal sensors are exposed to clean
laboratory air only. They can be surface -mounted in minutes
eliminating the need for expensive panel cutouts.
Each model is equipped with indicator lights that illuminate
based on apre-determined set -point. An audible 85dB
piezoelectric alarm sounds and a red indicafor light illuminates
to warn of potentially dangerous low air flow conditions.
54LO405
Low flow set point
— Audible and uisual alarm
1/0 options
54LO335
Analog meter
Audible and visual alarm
VO control
Fisher Hamilton fume hood monitors are shipped with operation
manuals
(1V Fisher NamiftQn
EXHAUST FILTER INSTALLATION
Product Numbers 54L296, 54L297, 54L298 aod
54L299
Pre -1
COVE
ilt r
r
The prefilter cover faces
forward on Restricted
Bypass and Constant
Volume Bypass hoods.
The pre -filter cover faces to
the left on Auxiliary Air
hoods.
Securely attach the filter inlet collar to hood exhaust transition
using same method as followed in the duct system. Filter outlet
may be attached to dict using flexible connector or carne as
inlet Connection.
INSTALLATION OF MINIHELIC GAUGE
ensor blocand sensor tube,
two raga each
Connect to low side of
Mipihe.Nc Gauge
Thiel -wall vin I laboratory
` trl h i n, cut to ngth
Miriih�C Irl rar��a �Ij_r1
r� ' .C., leads fi to r- pressure drop
onnet'y.. r
h i h,a h..i e of
"MiNhelic Gauge Front Post
Replacement filter sets consist of one rough and one NEPA
filter.
Product Number 54L302 — Filter set dor 54L296 or 54L298.
Product Number 54L300 -- Filter set for 54L.297 or 54L299.
Dimensions are nominail and illustrations and -pecifi ations are based
on the latest product information available at the time of publication.
The right is reserved to nnake changes at any firne without rictice,
IR
SAFEAIRE0 LABORATORY FUME HOODS
OPERATION9 MAINTENANCE AMD INSTALLATION INSTRUCTIONS
WARNING/OPERATING INSTRUCTIONS
Refer to Operation
Instructions on left-hand
front post, Data from the
.AAs Manufactured" test
should be fogged In this
area along with any
further Held Test results,
(See Pae 28 and 29)
WARNING
This product is intended for use with certain chemicals that
can cause serious injury or illness through inhalation or
physical Contac#. While this product is intended to minimize
exposure to certain hazardous chemicals when selected,
installed and operated properly, its performance and the safety
of the user is affected by a number of factors. These include the
HVAC
system, the spec+tic chemicals and processes being used,
proper operation and the condition of the room.
Before using this fume hood, consult the owner's industrial
!hygienist or safety representative to make sure: 1) the specific
fume hood alarms, controls and the HVAC system have been
properly selected and are operating correctly, 2} the food has
been tested after installation and routinely thereafter to ensure
the fume food is providing the proper containment for the
specific chemicals and processes being used, 3) there has
been appropriate training on the correct use of the fume hood
and handling of the specific chemicals and the fume hood
operating instructions haus been reviewed, 4} any personal
protective devices that are required are properly selected and
provided, and 5} the fume hood is being operated at the
appropriate face velocity. The fume hood should never be
operated with the sash in the full open Position.
OPERATING INSTRUCTIONS
Failure to fallow these instructions could result in physical
injury or illness.
Caution: Da not use hood for perchloric acid procedures,
1. Do not use this fumy hoed unless you have received proper
training from the owner's industrial hygienist or safety
representative.
3. Verify that the fume hood exhaust system and controls are
operating properly and providing the necessary air flaw. If in
doubt, the owner's industrialhygienist car safety
representative should be consulted. It is recommended that
the hood be equipped with an air flow morlitoring device.
Before using the fumy food, verify that the manitar iS
operating properly by testing the monitor.
4. The hood should not. be operated with the sash in the full
Open (set-up) position. When the hood is, in use, the opening
of the sash glass should be kept at a minimum. On a
vertical rising sash, the sash glass should be no higher than
18", Horizontal sliding panels an combination sashes mast
be closed when sash is raised verficaliy. The sash should
remain closed when the hood is not in use.
5. place chemicals and other work materials at least six (6)
inches inside the sash.
6. Do not restrict air flaw inside the hood. Do not put large
items in front of the baffles. large apparatus should be
elevated on blacks. Remove all materials not needed for the
immediate work. The hood must not be used for storage
purposes.
7. Never place your head, inside the hood,
8. External air movement can affect the performance of the
hood. Do not operate near open doors, open windows or
fans. Avoid rapid lady movements. Do not open the hood if
there are cross -drafts
or turbulence in front of the hood. Do not open the sash
rapidly.
9. If this hood is equipped with adjustable baffles, do not
adjust the baffles without consulting the owner's industrial
hygienist or safety representative.
10. Wear gloves and over protective clothing if contact with
contaminants is a hazard.
11. Glean spills immediately.
12, if fumes or odors are present, stop operating the hood;
close the sash and contact the owner's industrial hygienist
or safety representative immediately.
13. It is recommended that this turns hood be tested and
certified annually by the owner according to applicable
industry and government standards.
2. TThis fume hoodis riotmend to be used with all chemicals
or all chemical processes. Consult the owner's industrial
hygienist or rep
rer re rpt ti to determine whetie r the
hood is appropriate for thecals and
ud.
Demensbns are nominal and illu:strations and specifications are fused
on the latest product information available at the time of publication.
20 The righ=t is reserved to make changes at any time without notice.
(*)Fisher Hamilton
D
FE .II E LABORATORY FUME HOODS
OPERATION, MAINTENANCE AND INSTALLATION INSTRUCTIONS
GENERAL MAINTENANCE OF FUME HOODS
Fumy hood maintenance procedures consist primarily of ciean-
up, adjustment, lubrication, and replacement of worn, damaged
or nen-functioning parts. Lubrication of sash guides, cables,
pulley wheels, and other working parts should be accomplished
as required and replacement of broken, warn, or non-
functioning parts as needed. The following items should be
inspected and serviced at feast semi-annually:
• Liner and baffles for condition and cleanliness.
• Law air flow detectors.
Service fixtures and lights.
Pulleys and belts.
• Sash operation and counterbalance cables [ncluding a
complete visual check of the entire system.
Make sure there is a 1116" clearance between cable
keepers and pulley sheaves.
Velocity and pressure sensing detectors.
• Low or no flow alarms, both visile (lights) and audible
(horns or bells).
• Signal transmission for alarms designed to activate signals
at more than one location.
• Instrument verification of fume hood face velocity and
determinafion of usage by observation and interview.
• Ductwork and blower.
WARNING
Use only fluorocarbon grease on blower since any ether
type is to be considered potentially dangerous,
�
WARNING
Frayed or broken cables should be replaced to avoid
personal injury or damage to fume hood. Not all cable
manufacturer's cables are the same quality and cycle life.
We can only warranty cables furnished by Fisher hamilto-111,
Clean-up should be accomplished by, or under the supervision
of, a knowledgeable technician and should include removal of
all baffles for clean-up at all interior surfaces.
Flush all spills immediately using neutralizing compounds as
required and clean thoroughly. Use good housekeeping in
laboratory fame hoods at all times.
FUME HADD INSPECTION PROCEDURES
Safety considerations require that a schedule of inspection and
documentation be set up for every laboratory fame hood at
least annually.
An inspection record should be maintained. This record may be
I
n the form of a label attached to the fume hood, or a lag heli
by the laboratory director or health safety director.
Inspection procedures should include instrument verification of
fame hood face velocity and a determination of usage by
Nsher Hamilton
observation and interview. These procedures should also
consist of a physical examination of Inner condition and
cleanliness, baffle and sash operation and condition,
counterbalance cables, fight operation and condition, and
service fixture function.
Inspecfion results should be recorded and reported to the
proper authority or any required action.
NATE: Special purpose fume hoods such as those used with
radioactive materials or perchloric acid require additional
inspection procedures to cover special equipment and
requirements.
Options, such as low air flow detectors, when installed, should
be inspected at least annually. Where extreme hazardous or
corrosive conditions exist or when filters ars present in the
system, the inspection frequency should be increased
appropriately. Velocity and pressure sensing detectors should
be tested at each inspection. Low -flow of no -flow alarms of the
visible (lights) or audible thorns or beefs} hype should be tested
for
correct operation at least at each inspection. Signal
transmission dor alarms designed to activate signals at more
than one location should be verified at each location during
each inspection. Frayed or broken belts should be replaced
promptly.
FLUORESCENT LIGHT TUBE REPLACEMENT —
BENCH TOP, HI -LINE AND FLOOR -MOUNTED
HOODS
Rem ova
two screws
1, Remove sash enclosure if applicable.
2. Remove two (2) screwy securing bottom of louver panel to
front hosts. Pull louver panel up to disengage from studs
and remove panel.
3. Squeeze bottom edge of lamp housing to disengage from
galvanized channel. Rotate lamp housing up to expose
bulbs. Replace bulbs with same type as in unit_ turn on light
switch to verify connections.
4. Reverse Steps 1--3 t4 return hood to usably condition.
Dimensions are nominal and illustrations and spedications are loosed
on the latest product information availiable at the time of Publication.