Daily Field Report
Project Name
The Grove
Time Start
09:45 AM
Client
Stillwater Equity Partners
Contractor
Hill and sons
Time End
01:30 PM
Inspection Type(s)
Other
Location(s)
Densities on sidewalk base for buildings: Linden,
black oak, and hickory.
Observations/ Remarks
We shot densities for the 3/4 base, at first they were failing but with added water and compaction they
passed.
Items observed are in general conformance with approved project documents and jurisdictional requirements.