Daily Field Report
Project Name
The Grove
Time Start
08:30 AM
Client
Stillwater Equity Partners
Contractor
Headwaters Construction
Time End
10:30 AM
Inspection Type(s)
Epoxy Embeds/ Anchors
Location(s)
Linden Building
Observations/ Remarks
I arrived on site and began my observations for the HDU's at various locations (HDU5, HDU8) on the
first floor. I observed that the contractor had cleaned out the holes with a wire brush and air. I
observed the contractor use Hilti 200 and placed sufficient epoxy in each hole prior to placing the bolts
with a twisting motion. I notified the contractor of my observations prior to leaving.
Items observed are in general conformance with approved project documents and jurisdictional requirements.