Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
MACU Call Center
20023
Mountain America Credit Union
Big-D 09-24-2020
Windy
10:30 AM
70
12:30 PM
I arrived on site at approximately 10:30 AM. I observed that the contractor had rolled the parking lot area
and was prepared to roll the water truck over it. I observed the ground deflection as the truck rolled over
and observed that the ground was firm and unyielding.
Digitally signed by Jacob P Christensen
Date: 2020.09.25 21:38:35 -06'00'
●
D. Aust
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: