Daily Field Report
Project Name
Madison Fieldhouse
Time Start
02:15 PM
Client
Madison School District
Contractor
Thompson paving
Time End
03:30 PM
Inspection Type(s)
Earthwork Inspection
Location(s)
Sidewalk between field house and tennis courts
on the East side of the building.
Observations/ Remarks
We loaded the gauge into the truck at 2:20pm and arrived at the site out of proximity 2:50 PM. We got
four passing tests on the three quarter base and informed the superintendent. We left the site at
approximately 3:15 pm to return to the lab to return the gauge at approximately 3:30 pm.
Items observed are in general conformance with approved project documents and jurisdictional requirements.