September 30, 2009
Permit Number: 08 00362
Project Name: Springhill Suites Marriott Hotel
Project Type: Commercial New Construction - Over 2 Million
P.O Box 280
19 E. Main St.
Rexburg, Idaho 83440
Phone(208)359-3020
Fax(208)359-3022
Review Item Actions Required for Approval
Approved
2 way communications as per IBC Section
1007.6.3.
Height and Area Review
Miscellaneous
Waste Water Grease Trap Form
Waste Water Application
Energy Conservation Compliance Review
Building Code Fire Compliance Review
Mechanical Review
Structural Review
Section 508.3.2.2 Of the 2006 IBC states the
following: "The allowable area and height of the
building or portion thereof shall be based on the
most restrictive allowances for the occupancy
groups under construction for the type of
construction of the building..." The most
resctrictive height requirements for this building
is three stories. This requirement is found in
Table 503 under A-2 and A-3 as a two story
allowable height. With sprinklers the allowable
height is raised to three stories. Nonseperated
mixed use is not allowed under these
conditions. Seperate the occupancies as per
Table 508.3.3. Provide details.
Glazing in the pool area must be safety type.
Provide energy review..
Provide details that identify how steel beams
and columns are being fire rated as per Table
601. Fire barriers are required between
different occupancies as per Table 508.3.3.
Provide details and rated doors. Rated doors
must be self closing.
Meets code requirements.
Special inspections are required for concrete
foundation, high strength bolting, sprayed on fire
proofing, and any structural fill. Please provide
letter from the firm that will be providing these
services. Also please provide truss details and
soils report.
r I 7 Y 0 P
R EXBURG
1rr r;tas f";ttn } Camtirz=tit),
Review Action
September 30, 2009
P.O Box 280
19 E. Main St.
Rexburg, Idaho 83440
Phone (208) 359-3020
Fax (208) 359-3022
Permit Number: 08 00362
Project Name: Springhill Suites Marriott Hotel
Project Type: Commercial New
Construction - Over 2 Million
Review Item
Actions Required for Approval
Approved
Fire Department Review
Required Fire Flow
See site plan review.
08/21/2008
Water Supply
See site plan review.
08/21/2008
Fire Access Roads
See site plan review.
08/21/2008
Fire Extinguishers
Fire extinguishers are required for this
08/21/2008
occupancy. All extinguisher are required to be
installed before final fire inspection.
Automatic Fire Extinguishing Systems
Submit automatic fire sprinkler to the State Fire
08/21/2008
Marshall for plan review. Plans are required to
be approved before installing any part of the
sprinkler system. Submit letter of intent from a
certified fire sprinkler contractor.
Standpipes
All stand pipe systems are required to
08/21/2008
submitted with the fire sprinkler plans to the
State Fire Marshall for approval before
installing.
Commercial Cooking
All commercial cooking is required to meet the
08/21/2008
standards of the International Fire Code 2006
edition and the International Mechanical Code
2006 edition. All cooking appliances and kitchen
Alarm Systems
equipment must have approval before installing.
Submit fire alarm plans to the City of Rexburg
08/21/2008
for review and approval before installing any
part of the fire alarm system. Letter of intent is
Other Comments
require from a certified fire alarm contractor.
A lock box is required for this occupancy.
08/21/2008
Forms are available at the Rexburg Fire
Department. Location of lock box is required to
be appproved by the fire department.
4 f f.:Y1SU1.,
(;C7'y' 0 g
REXBURG
A r a a> ; arm y C:omrn;rrit;.
Review Action
September 30, 2009
Permit Number: 08 00362
Project Name: Springhill Suites Marriott Hotel
Project Type: Commercial New Construction - Over 2 Million
P,0 Box 280
19 E. Main St.
Rexburg, Idaho 83440
Phone (208) 359-3020
Fax(208)359-3022
Review Item Actions Required for Approval Approved
Planning Staff Review
--_Pp
Development Standards Review Exterior colors were not listed on Page 200 of
plans. As a note, the following standard must
be adhered to: Facade colors shall be low
reflectance, subtle, neutral, or earth tone colors.
The use of high intensity colors, metallic colors,
black or fluorescent colors is prohibited.
Parcel #'s RPRXBCA0367250
GITy (}f:
`8
REXBURG
- Amer;ca's F�m;fy Comfr:s.nity
Review Action
P.O Box 280
19 E. Main St.
Rexburg, Idaho 83440
Phone (208) 359-3020
Fax (208) 359-3022
September 30, 2009
Permit Number: 08 00362
Project Name: Springhill Suites Marriott Hotel
Project Type. Commercial New Construction - Over 2 Million
Review Item Actions Required for Approval
Building Department Review Approved
Electrical Circuits Review
Electrical Service Review
Accessibility Review
Building Type Compliance
Water and Sewer Service
Plumbing Sewer Drain Review
Plumbing Storm Drain Review
Plumbing Potable Water Review
Exiting Review
Outlet spacing is required to meet the 2008
NEC section 210.60 (A and B) in the
suites/rooms. Make sure that this is wired to the
2008 NEC. The pool equipotential bonding is
required to meet the 2002 NEC section 680.26
requirements. Any questions on the current
State of Idaho code adoptions/modifications
contact Bret at 359-3020x332.
Meets code requirements.`
Building is VA construction.
All plumbing services are required to be tested
and inspected before covering.
All drain lines are required to be installed
according to the the Uniform Plumbing Code
2003 edition.
No San tees are allowed in horizontal venting.
Every fixture is required to be vented. No air
admittance valves are allowed.
All drains are required to be tested and
inspected before covering.
All storm drains are required to be tested and
inspected before covering.
All water lines are required to be sized
according to the Uniform Plumbing Code 2003
edition.
All water lines are required to be protected from
cross contamination. All backflow devices are
required to be install, tested and inspected
before covering.
Occupant load must be posted in each
Assembly occupancy as per IBC Section
1004.3. Area of refuge in stairwells must have
08/01/2008
08/01/2008
08/20/2008
08/20/2008
08/21/2008
08/21/2008
08/21/2008
08/21/2008