HomeMy WebLinkAboutEXTENSION REQUEST - 07-00312 - Madison Middle School - CUP for Modular ClassroomsJune 12, 2009
Planing and Zoning Commission
City of Rexburg
Re: Conditional Use Permit - 07 00312 - Extension Request
Middle School Modular Classrooms
Background;
The original CUP was granted to the Madison School District to augment student class rooms in
the Middle School. This permit was issued 8/24/2007 and was set to expire in two (2) years,
August 2009. Since the time of issuance the student population at the Middle School has
increased to an enrollment of 1020 students for the school year just completed. In that period of
time the District passed a bond that has allowed construction to begin on a new High School.
With the completion of the new High School (slated for opening at the beginning of the 2010 -
2011 school year) it will allow the moving of student from the exiting High School and the
second phase of remodeling to begin on the existing High School. This remodel is expected to
be completed during the summer of 2011. When completed the students at the current Jr High
School will be relocated to the New Jr High School (old High School). Once this move is
completed the 7" grade will also then be moved from the Middle School to the new Jr. High
School. This change will decrease the student population at the Middle School by
approximately 350 students and the District need for modular classrooms at the Middle School
will be eliminated.
Request;
The District is hereby requesting an extension to the existing CUP through the end of the 2010 -
2011 school year to allow construction and remodeling complete and the relocation of students to
take place.