HomeMy WebLinkAboutSTAFF REPORT - 08-00536 - Hemming Corp - 130 & 124 W 1st S, 226 S 1st W - Rezone to Hemming ProZoneCommunity Development Department
STAFF REPORT
12 North Center
Rexburg, ID 83440
SUBJECT:
APPLICANT:
PROPERTY OWNER(S):
PURPOSE:
PROPERTY LOCATION:
PROPERTYID:
COMPREHENSIVE PLAN:
CURRENT ZONING:
garyi@rexburg.org Phone: 208.359.3020 x314
www.rexburg.org Fax: 208.359.3024
Rezoning Application, file # 08 00536
Hemming Corp
Lane Hemming
3113 W 1000 N
Rexburg, ID 83440
CITY OF
REXBURG
04
Amerlw' Family Community
Request to rezone area from MDR Iand HDRI to the Hemming PRO Zone,
a mixed use zone.
130 & 124 West 15` South, and 226 South 15I West
RPRRXB10404650, RPRRXB10404630, RPRRXB10540010,
RPRRXB10540030, RPRRXB10540730, RPRRXB10541450
Mixed -Use
Medium Density Residential 1 (MDR 1)
High Density Residential 1
PROPOSED ZONING: Hemming PRO Zone (Project Redevelopment Option)
SURROUNDING LAND USES
AND ZONING: Dormitory housing (north portion of application), High Density
Residential 1 (HDR I), and Hemming PRO Zone. Dormitory housing
(south portion of application), Medium Density 1 (MDRI), and Hemming
Pro Zone.
APPLICABLE CRITERIA: City of Rexburg Development Code (Ordinance Code 926)
§ 6.14 Amendments to this Ordinance
§ 3.30 Project Redevelopment Option (PRO)
AUTHORITY § 6.14 (E) "The Commission may recommend that the amendment be
granted as requested, that it be modified, or that it be denied"
§ 3.30.050(B) "The Planning Commission may recommend and the City
ouncil may adopt, modifications to PRO regulations and standards proposed by and applicant who, in the
pinion of the approving authority, is needed to meet the intent and requirements of this chapter. "
Case No. 08 00536
Page 1
1 I. BACKGROUND
The application is for a continuation of the previously approved Hemming PRO zone, which the
Council approved on August 6th, 2008. This proposal is contiguous with the existing Hemming PRO
Zone both on the north and south sides of the Hemming PRO Zone.
A PRO zone allows for the establishment for an entirely new zoning category within the City's
Development Code (Currently Ordinance #926). The PRO must address all standards found in other
zones such as setbacks, lot coverages, building heights, etc. The proposal is to continue with what
was approved with the original Hemming PRO Zone. No change to the ordinance is being proposed,
only the boundaries.
The Rexburg Development code allows for the Commission to make recommendations to the City
Council regarding whether or not the property should or should not be rezoned based on the criteria
found in section §6.14 (E)(1), and §3.30.050(B)
II. SITE DESCRIPTION
The site is located in two areas and they are not connected to each other, but are contiguous with the
Hemming PRO Zone. The north request is located on W Vt South, a local street, and is between s l'
West and S 2"d West. The south portion of the request is located at the south west intersection of S ls`
South and W 2"d South.
The total area involved in this re -zoning request is approximately 1.5 acres, which if approved will
result in a Hemming PRO Zone that equals 12.5 acres of land. There are several tax lots involved in
this request; these lots are currently being used as dormitory housing.
The surrounding area is a mix of residential and some commercial uses. The University is generally
within a block from the site. To the west, but across S 2"d West, is Porter Park, a 10 -acre city park.
III. ANALYSIS
As a PRO Zone, the request would normally require the Commission and Council to review the
proposal against two sets of criteria, one set is for the request to rezone, the other set is criteria that a
PRO Zone is specifically required to address. However, as this request is to only change the
boundary. Below, staff has provided all the criteria listed by Ordinance 926 (Development Code) that
are required to be addressed, followed by staff's analysis of each criterion.
Criteria Rezone Requests (46.1400)):
a. Be in conformance with the City's Comprehensive Plan
The comprehensive plan map, or preferred land use map, designates the subject property as
Neighborhood Commercial/Mixed-Use.
b. The capacity of existing public streets, water and sewer facilities, storm drainage facilities,
solid waste collection and disposal, and other utilities.
The proposal is for an area of existing and functioning infrastructure. New construction will
require a review and analysis by the City Engineer to determine adequate capacity of
infrastructure. This criterion is therefore met.
Case No. 08 00536
Page 2
c. The capacity of existing public services, including but not limited to, public safety services,
public emergency services, schools, and parks and recreational services..
As an infill project, the area currently has access to all public services described, therefore this
criterion is met.
d. The potential for nuisances or health and safety hazards that may adversely affect adjoining
properties.
The Commission should review the language of the approved Hemming PRO Zone and make a
determination as to whether or not this proposed boundary change will have an adverse affect on
adjacent property, and the surrounding neighborhood. A determination should be based on
compatibility issues that generally relate to zoning requirements such as building setbacks,
building heights, lot coverage, amount and location of landscaping, parking lot standards, etc.
Staff has a provided a review of the proposal and has provided proposed conditions of approval
that are intended to increase the proposal's likelihood of being compatible to adjoining properties
and the neighborhood.
The Commission should make a finding as to whether or not this criterion is met.
e. Recent changes inland use on adjoining properties or in the neighborhood of the map
revision.
Due to the original Hemming PRO Zone approval, much of the surrounding area has been
rezoned to this new zone. However, the Planning Commission during the original hearing
recommended a condition that the approximate 11 acres of proposed Hemming PRO zone be
limited to only a Phase 1. This was to enable the City to see if the Hemming PRO Zone was
accomplishing its intent before additional phases were to be approved. The applicant, at that time,
stated that they understood the Commission's concerns and would be agreeable to limiting the
rezone to only one phase for a period of time. However, at the Council level this proposed
condition was not included in the approval of the Hemming PRO Zone and all 11 -acres were
included in the approval.
A condition of approval that was approved was the condition that states,
"As the developer and the City are prepared, the applicant can come forward with an additional
to be rezoned to the Hemming PRO zone. The Hemming PRO Zone is allowed to be extended as
long as it is determined that the zone is being utilized to create a cohesive development and
neighborhood, not just to utilize the flexibility of setbacks and parking standards. Each additional
boundary modification should be based on a specific proposal."
"If the Hemming PRO zone is not moving forward with actual construction of buildings and uses
that are substantially the same as proposed and intended during the rezone request, then the City
shall initiate a reversion to the previous zoning (most recent prior to the PRO Zone designation).
This time limit should include an 18 month period. The time shall begin at the adoption of the
Hemming PRO zone or at each phase. Within the 18 month period a building permit shall be
submitted that requests approval of a substantial building that is consistent with the intent of the
Hemming PRO zone. No new phases should be considered until at least fifty (50) percent build
out has occurred on previous phases."
Case No. 08 00536
Page 3
Staff would point out that no projects have been completed within the Hemming PRO Zone
boundaries, and a 50% build out has not occurred of the other areas designated Hemming PRO
Zone.
The Commission should determine whether or not this proposed Hemming PRO Zone boundary
expansion as conditioned will impact or be impacted by adjoining properties or the
neighborhood.
Criteria use for PRO Zone requests (43.30.050(C)):
A proposed PRO Zone application and associated preliminary project plan shall be approved only if,
in the opinion of the approving authority, development proposed on the property will:
f. Further applicable provisions of the Vision 2020 Comprehensive Plan and any applicable
master plan, particularly provisions which establish density limitations.
The 2020 Comprehensive Plan is not yet adopted, but as was mentioned, the proposal is
consistent with the comprehensive plan map designation of mixed-use. This criterion is therefore
met.
g. Conform to applicable chapters of this Title and except as may be specifically amended by the
adopted PRO Zone text.
Where the Hemming PRO Zone has not modified standards, all applicable Development Code
standards will still govern the property. It was not intended that the Hemming PRO Zone be
exempt from the architectural design standards found within the City's Development Code.
Therefore, where the Hemming PRO Zone does not offer specific guidance on design standards,
then the default standards are those found in the City's Development Code.
h. Preserve and enhance the subject property and neighborhood by achieving integrated planning
and design.
This criterion was discussed at the original public hearing and a determination by the
Commission and Council was made that the proposal as written will achieve integrated
development within itself and with the neighborhood that it is located, and will it enhance the
area. The Commission should determine if the proposed boundary change continues to advance
this criterion.
i. Be compatible with development on adjoining and nearby property, both existing and as
envisioned by the Rexburg Comprehensive Plan.
Within the staff report prepared for the original establishment of the Hemming PRO Zone, staff
made the following comments:
"It does not appear that there are any foreseeable impacts by this proposal, as conditioned.
However, staff would recommend limiting the area to be rezoned. A better approach would be to
limit the rezoned area to only a "phase 1" of a multi -phased approach. This would allow the
developer to proceed with a limited area of development as well as allow the City to find out if
there are any unintended consequences to this Hemming PRO zone category. Staff would
recommend limiting the proposed zone change to the southwest area of the proposal. Specifically
to the areas of mixed-use development on both sides of W 2nd South, and the proposed
Hotel/Lodge area (see proposed conditions of approval)."
"As the developer and the City are prepared, the applicant can come forward with the next phase
to seek a rezone. Staff would recommend that in the future, the Hemming PRO Zone be allowed
to be extended as long as it is determined that the zone is being utilized to create a cohesive
development and neighborhood, not just to utilize the flexibility of setbacks and parking
standards. Each additional boundary modification should be based on a specific proposal."
Case No. 08 00536
Page 4
The City should not continue to expand the boundaries of a zone that has not yet shown that it
will satisfy this criterion. With a zone that has such flexabilility, the City should move forward
cautiously to avoid any unintended consequences. As the Hemming PRO Zone develops and
shows that by using the PRO zone that better development can be achieved as is compatible,
further boundary changes could be explored.
j. Minimize the effect of traf lc congestion and improve parking and air quality, including
providing opportunities for alternative modes of transportation such as walking, bicycling, or
transit.
As originally conditioned, this criterion and many others are addressed.
IV. STAFF RECOMMENDATION
The Commission should review the Hemming PRO zone proposal and the applicable criteria. Staff
recommends that the Commission take public testimony, and determine if the proposed re -zoning
request satisfies the above criteria. However, staff points out that the original conditions for the
Hemming PRO Zone prohibit the expansion of the zone until certain criteria are met including
development occurring, and not until a 50% build -out has occurred. Currently the City has only
approved a building for the Hemming PRO Zone, albeit a significant building for the project.
However, there is a tremendous amount of the existing Hemming PRO Zone not yet addressed. In
addition, a Hemming PRO Zone expansion should not occur unless a specific project is represented,
and none has been proposed with this application. The City should hold off on any approvals of
Hemming PRO Zone expansions until the above mentioned conditions are met.
If the Commission can make a finding that the criteria for approving this PRO zone expansion are
met, then a recommendation of approval, or approval with modifications/conditions should be made
to the City Council.
Proposed Conditions of Approval
1. All conditions of approval that were applied to the original approval of the Hemming PRO
Zone shall apply to this proposal.
MITNUtxhBihIhbiiM
Page 5