HomeMy WebLinkAboutADDENDUM NO. 2 - Civil Site Plans - 20-00866 - BYUI Engineering Technology Center (ETC) - Remodel
BYU Idaho Engineering Technology Center (ETC)
MS Project #: 20.0220
BYU Idaho Project #: 12005
BID Addendum No. 2
BID ADDENDUM NO. 2
Date: November 10, 2020
PROJECT: BYU Idaho Engineering Technology Center (ETC) ARCHITECT: Method Studio, Inc.
Rexburg, ID 160 West 2nd South, Ste. 201
Rexburg, Idaho 83440
p.208-701-0068
OWNER: BYU Idaho ARCHITECT’S
BYU Idaho Project #: 12005 PROJECT NO.: 20.0220
TO ALL BIDDERS:
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated October 27, 2020. Receipt of
this Addendum must be acknowledged to Headwaters Construction and by Headwaters Construction.
Questions / Comments:
1. None
DRAWINGS & SPECIFICATIONS:
Civil:
1. Submittal of civil drawings and specifications. Refer to attached Civil Documents
Architectural:
1. Sheet AS101 – North sidewalk, curb and drive path has been revised to match civil drawings. See attached civil drawings.
2. Sheet AS101 – South West sidewalk has been revised to match civil drawings. See attached civil drawings.
3. Sheet AS101 – Description for chain link fence finishes has been revised.
4. Sheet AE111 – Updated slab on grade in Rooms 141 to match grading elevation per civil. Civil drawings are included as part of
this addendum. See civil drawings.
5. Detail D6/AE521 – Remove drainage board and waterproofing from the foundation and provide damp proofing in its place.
Structural:
1. None
Mechanical:
2. None
Electrical:
2. None
END OF ADDENDUM TWO
Civil Site Work Specifications 1 of 15
SPECIFICATIONS FOR CIVIL SITE WORK
ENGINEERING TECHNOLOGY CENTER
BRIGHAM YOUNG UNIVERSITY – IDAHO 5 Nov 20
DESCRIPTION AND SCOPE
The civil site work for this project consists of demolishing and removing existing asphalt and
concrete interfering with new improvements; constructing new concrete sidewalks, pads, and
repairing concrete pavement areas; repairing disturbed asphalt areas and constructing new asphalt
surfacing were needed; constructing new curbs and gutter; installing chain-link fencing: installing a
4” sewer service line; constructing storm drain improvements; and replacing an existing concrete
stairway to include heating capability.
There are not any alternates for this project.
Winston Dyer, PE of The Dyer Group, LLC (208-390-9700) in Rexburg, is the Engineer of Record
for the above-described civil site work – providing engineering design, construction staking of the
designed elements, and construction observation of the associated facilities.
GENERAL PROVISIONS
Water for Construction: The University will make water available from existing facilities wherever
possible, at no cost to the contractor, provided suitable precautions are taken to prevent cross-
connections and possible contamination of the water supply system. Coordinate with University
personnel whenever drawing water from University water supplies in order to avoid potential service
disruption.
Access and Safety: At all times conduct work so as to insure to the greatest possible degree the
uninterrupted convenience and safety of the general public and access to areas adjacent to the
work. As appropriate, properly close pedestrian sidewalks and driveway/parking areas during
construction – providing appropriate signage, work area closure, and pedestrian detour routes.
Noise Impact: To minimize noise impacts on campus, do not conduct civil site work construction
activities between the hours of 10:00 p.m. to 7:00 a.m., unless approved otherwise by the Owner.
Submittals: Furnish shop drawings, equipment or materials catalog cuts, and other similar
information to the Engineer for review and approval of all equipment and materials proposed for use
on the civil site work prior to beginning construction. Promptly correct and resubmit any submittals
deemed unsatisfactory by the Engineer.
Testing: The Owner will furnish certified third party quality control testing necessary to assure the
workmanship and materials are in accordance with specified construction requirements as defined
later in these Special Provisions. This includes soil materials, compaction, and concrete and
asphalt quality. Respond to the tester’s direction given through the Engineer to correct deficiencies
identified by the testing and/or to replace defective materials and construction as appropriate to
meet the specifications.
Surveying: The Engineer has established general survey control and will provide general
construction staking for those items associated with the civil site work. The Contractor will be
Civil Site Work Specifications 2 of 15
responsible to lay out the work as needed beyond the identified construction staking. Note that
parking lot striping is not included in the project; the University will lay out and paint the parking
areas after construction.
Traffic Control: Furnish all necessary pedestrian and traffic control for this project in accordance
with the Standard Specifications and the “Manual on Uniform Traffic Control Devices” (MUTCD).
Restrict traffic and pedestrian access to the work area in accordance with the MUTCD, providing
clearly marked and delineated detours where appropriate. Closely coordinate with the Owner’s
representative to provide information on closures, schedule, and potential impacts of construction
so information can be disseminated to faculty and students.
STANDARD SPECIFICATIONS AND DRAWINGS
Standard Specifications for the civil site work will follow the Idaho Standard Specifications for Public
Works Construction, 2017 edition. Standard Specifications applicable to this project are:
Section No. Description
201 Clearing and Grubbing and Removal of Obstructions
202 Excavation and Embankment
203 Soil Materials
204 Structural Excavation and Compacting Backfill
301 Trench Excavation
303 Exploratory Excavation
302 Rock Excavation
305 Pipe Bedding
306 Trench Backfill
307 Street Cuts and Surface Repairs
501 Gravity Sewers
502 Manholes
504 Sewer Services
701 Concrete Formwork
702 Concrete Reinforcement
703 Cast in Place Concrete
706 Other Concrete Construction
801 Uncrushed Aggregates
802 Crushed Aggregates
803 Plant Mix Aggregates
805 Asphalt
810 Plant Mix Pavement
1001 Construction Site Management
1002 Construction Site Housekeeping
1003 Sediment Collection
1103 Construction Traffic Control
Civil Site Work Specifications 3 of 15
2040 Fencing
2050 Construction Geotextiles
Standard Drawings applicable to this project are:
Section No. Description
SD-301 Typical Trench
SD-302 Typical Pipe Bedding Section
SD-303 Street Cuts and Surface Repair Details
SD-502 Standard manhole Type B
SD-511 Standard Sewer Service Line
SD-1000 Idaho DEQ Catalog of Stormwater BMP’s:
www.deq.idaho.gov/water-quality/wastewater/stormwater/
PROJECT SPECIFIC CHANGES OR CLARIFICATIONS TO THE STANDARD SPECIFICATIONS
The following special provisions amend, modify, change, or clarify Standard Specifications as
necessary for this project:
1) Section 202 Excavation and Embankment: Do not scarify the subgrade but do coordinate
with the Engineer concerning uniformity prior to placing separator fabric. Use Class A
(mechanical) compaction for all embankments. See Specifications herein for compaction
requirements.
2) Section 203 Soil Materials: See Specifications herein for additional information on soil
materials.
3) Section 204 Structural Excavation and Compacting Backfill: Make extra effort and
provide suitable equipment to properly and thoroughly compact around existing foundations or
structures such as catch basins and manholes.
4) Section 302 Rock Excavation: Include a total allowance of 15 yd.³ of rock removal in the
contract to address the potential for rock excavation associated with sewer and storm
drainage installations.
5) Section 305 Pipe Bedding: Use Type I pipe bedding sorted from available excavated
material; or at contractor’s option and without additional cost, furnish and use Type I or Type
III pipe bedding material for the sewer and storm drainage piping to be installed. Use Class
A-1 Bedding System.
6) Section 306 Trench Backfill: Use Type A-1 trench backfill and compaction (mechanical) in
all areas in lifts not to exceed 9”. See Specifications herein for compaction requirements.
Restore topsoil at the top of the trench backfill in landscaped areas.
7) Section 307 Street Cuts and Surface Repairs: Use the paving section detailed on the
Drawings for the asphalt repair for repairing trench cuts across existing asphalt areas,
including separator fabric and 12” of pit run gravel under the crushed gravel.
Civil Site Work Specifications 4 of 15
8) Section 703 Cast in Place Concrete: Use Class 4000A(B) or 4000A(B)F (4000 psi) for all
concrete on this project. Demonstrate reduction of aggregate ASR in the concrete mix
designs. Do not exceed 35% of the total cementitious material for fly ash, if used. Place ½”
expansion joint next to existing concrete or structures. See Specifications herein for
additional information on placing, jointing, finishing, curing, and quality control of new
concrete.
9) Section 706 Other Concrete Construction: Use the mix design parameters specified above
for Section 703 “Cast in Place Concrete”.
10) Section 801 Uncrushed Aggregate: Clarification is given that this specification refers to
uncrushed aggregates, sometimes referred to in the Specifications and Drawings as granular
borrow or pit run gravel. Use 6” gradation or finer and provide proctor for material. See
Specifications herein for compaction requirements.
11) Section 802 Crushed Aggregate: Use Type I (3/4” crushed material) gradation and provide
proctor for material. See Specifications herein for compaction requirements.
12) Section 803 Plant Mix Aggregates: Use ½” size gradation (commercial mix) and provide
Marshall Mix design or equivalent.
13) Section 805 Asphalt: Use PG 58-28 asphaltic concrete for parking lot and asphalt repair
pavement.
14) Section 810 Plant Mix Pavement: See Specifications herein for compaction requirements.
15) Section 2050 Construction Geotextiles: Use Type I - moderate survivability, non-woven
subgrade separation geotextile under all pit run gravel. Provide submittal for approval prior to
ordering material.
PROJECT SPECIFIC CHANGES OR CLARIFICATIONS TO THE STANDARD DRAWINGS
The following special provisions amend, modify, change, or clarify Standard Drawings as necessary
for this project:
1) SD-303 Street Cuts and Surface Repair Details: Use Type “P” repair with a local cut back of
12”. Use the surfacing section detailed on the Drawings for the gravel layers under the
asphalt.
2) SD-511 Standard Sewer Service Line: Use Type “A” connection.
MEASUREMENT AND PAYMENT
Measurement and payment items set forth in the Standard Specifications are superseded by the
contract arrangement for construction using cost plus a fixed fee, with a maximum cap.
The Drawings present quantity estimates for most scope of work items for the civil site work.
Quantities shown are “For Information Only” – contractor must verify quantities as part of
assembling the cost proposal. Immediately notify the Engineer of any discrepancies discovered.
Mobilization is not separately enumerated and thus is intended to be included in the cost of the
Civil Site Work Specifications 5 of 15
various work items described in the following sections.
SITEWORK
General: It is required to prepare the site where the new improvements are to be constructed. This
includes protection of existing utilities, some clearing and grubbing, various demolition work, and
environmental stewardship.
Products: Use 4” Schedule 40 PVC piping for extending existing utility sleeves.
Execution: Workmanship is described in the various subcategories that follow
Utilities: coordinate with Idaho Digline for the location of buried utilities prior to beginning any
construction. The University provides locates through the Digline contact. Likewise coordinate with
the construction manager on the work of other trades that may require additional or upgraded
buried utilities to the building prior to, or commensurate with, exterior construction activities.
Existing buried utilities on the site include water, sewer, and storm drainage pipelines; high-voltage
and lighting electrical conduits with conductors; communication conduits and conductors including
local fiber-optic lines and cable TV; a steam condensate line under the sidewalk to the main
entrance; and electrical snowmelt conductors in some existing concrete, including the main
concrete pad on the north of the building.
Above or at-ground utilities include vaults, valve covers, catch basins, sprinkler valve boxes, and
sidewalk lighting.
Retain and protect all existing buried and at or above ground utilities except as needed to make
connection to the existing storm drain piping, and removing and replacing a sidewalk light pole and
foundation, as detailed elsewhere in these Civil Site Work Specifications.
In the area of the driveway widening, the University will cut off and cap the water supply piping to
the existing sprinkler systems at appropriate locations, and may salvage other equipment such as
controls, valves, and valve boxes as they deem appropriate. Otherwise the remaining piping of the
existing sprinkler systems in the work area is to be abandoned in place and can be removed.
Remove any valve boxes in the work area not salvaged by the University and then backfill and
compact the void with appropriate material.
There are electrical, lighting, and sprinkler lines crossing under the west end of the north driveway,
which are located inside PVC sleeves under the driveway area. It will be necessary to extend the
sleeves for these utilities under the widening of the driveway area that will be constructed as part of
this project. Provide and install the sleeve extensions, coordinating with University personnel as
required to complete the work and minimize impact the existing utilities.
Clearing and Grubbing: perform clearing and grubbing operations in the area where the north
driveway is to be widened. Follow the standard specifications and grub to a depth of 4”. Also
remove the existing 3” caliper oak tree that is adjacent to the driveway widening area. Remove the
stump and root ball.
Remove and dispose of all grubbed materials and vegetation at an approved excess materials site.
Demolition: retain and protect all existing improvements within the site and outside the existing
Civil Site Work Specifications 6 of 15
building not specifically designated for demolition and improvement.
In areas of asphalt demolition and removal, saw cut the existing pavement along the lines indicated
in the Drawings. Cut the asphalt to full depth and do not begin disruption or removal of the asphalt
pavement until the saw cutting has been completed. Carefully remove the saw cut portion of the
existing pavement in a manner to not damage the existing pavement to remain (especially not lifting
up adjacent asphalt to remain).
For areas of existing concrete slabs to be removed, first cut and remove adjacent asphalt as
described above so that the concrete slabs can be broken up and removed without damaging the
remaining existing asphalt pavement. For concrete to be removed from existing slab areas (with
the remainder to remain), and for the end of the curb to be removed (where the existing will remain);
saw cut the concrete to full depth.
Note there is an existing snowmelt system consisting of hydronic conduits that is installed in the
main concrete slab north of the building. The conduits will be cut when saw cutting the existing
concrete for removal. It will not be necessary to install new or repair the snowmelt system.
For concrete to be removed from an existing slab area, further break up the concrete into smaller
sizes after saw cutting so that the concrete can be removed without damage to adjacent existing
concrete to remain. Likewise, remove the concrete curb and gutter by first pushing away from the
existing curb to remain before picking up sections. Remove and replace any concrete to remain
that is damaged by construction at no additional cost to the Owner.
Remove the demolished materials from the worksite and dispose of them at an approved materials
disposal site.
There is an existing building sign in the area of the north driveway widening that will be in conflict
with new construction. Carefully remove the sign and salvage it to a location as directed by the
University. The Owner will later reinstall the sign at an appropriate location after completion of the
work.
There is also an existing light pole and foundation for sidewalk lighting that is in close proximity to
widening of the north driveway. Retain and protect the light pole and base if possible during
construction; or otherwise remove, salvage, and reinstall the existing light pole and foundation after
completion of adjacent construction. Work with the University on reconnecting the existing conduit
and conductors for the light pole if it is to be reinstalled.
Erosion Control: since the area of site disturbance is less than one acre, a storm water pollution
prevention plan and notice of intent with EPA are not required. However, for proper environmental
stewardship, implement storm water best management practices (BMP's) to mitigate storm water
runoff from the site and potential erosion/sedimentation as may be appropriate or evident from
construction conditions (such as in the area of the north driveway at the existing sidewalk along
Center Street, for example).
When implementing BMP’s, use materials and follow procedures as presented in the “Catalog of
Storm Water Best Management Practices for Cities and Counties” document as published by the
Idaho Department of Environmental Quality, latest edition.
In general, conduct work and maintain the work area to minimize disturbance and potential for
storm water runoff. Control dust produced during construction by limiting disturbed areas to the
Civil Site Work Specifications 7 of 15
minimum needed and watering disturbed areas to minimize dust production.
Regularly observe and maintain any installed BMP's to assure their proper condition and
appropriate function. Promptly maintain or repair BMP’s as necessary to keep them in proper
working condition. Upon completion of construction, remove any accumulated refuse or debris, and
grade and smooth any unimproved disturbed areas.
CONCRETE SIDEWALK/PAD CONSTRUCTION AND REPAIR
General: It is required to construct new reinforced concrete sidewalk along the north end of the
existing parking lot, for the new ADA sidewalk near the southwest corner of the building, and for
filling in the planter areas in the existing sidewalk near the southwest building entrance. Exterior
reinforced concrete pads are also required for the new overhead door areas on the east and south
of the building where cars will drive in/out for repair work; and to repair the area of the existing
concrete pad on the north end of the building that will be disturbed for sewer service line
installation.
It is also required to construct non-reinforced concrete pads for the new man doors and to construct
an ADA access at the southwest building entrance as shown and detailed on the Drawings.
Work includes grading and subgrade compaction, furnishing and placing crushed gravel base
aggregate, constructing reinforced and non-reinforced concrete in these various areas as detailed
on the Drawings, and finishing and curing the concrete in accordance with this Specification.
Products: Use ¾” (Type I) crushed aggregate for crushed gravel under the sidewalk, ASTM A-615
Grade 60 reinforcing steel, and Class 4000B or 4000BF concrete. Furnish material properties,
gradations, proctors, and mix designs for the materials proposed for use. Demonstrate aggregate
ASR reduction in the mix design. Use 3”x3”x3” concrete dobie blocks (not chairs) to support steel
reinforcement (6” slab).
Use monomolecular evaporation reducer on freshly placed concrete, Confilm as manufactured by
BASF or E-CON manufactured by L & M Construction Chemicals, Inc., or Owner approved equal.
Use resin and water based curing compound on finished concrete, 1100 Clear as manufactured by
W. R. Meadows, or Owner approved equal. Use WR Meadows polyurethane NS Sealant,
limestone color, for sealing the top of completed expansion joints.
Furnish and use cast in place replaceable tactile panel system, brick red, as manufactured by ADA
Solutions, LLC (only) for the detectable warning strip at the ADA parking access.
Execution: Provide pedestrian and traffic control as appropriate to restrict access to the work area.
Assure the new concrete areas have been excavated and/or filled to the required subgrade depths
and grades necessary to accommodate the base gravel and concrete slab construction.
Furnish, place, and compact the required 6” deep crushed gravel base layer under the concrete
sections. Compact the crushed gravel to 96% of optimum density. The University will furnish the
services of a qualified materials tester and take compaction tests of the crushed gravel base section
under the sidewalk and pad areas. Copies of the test reports will be provided to the contractor via
the University’s e-Builder construction management software system. Promptly re-work any areas
of the compacted crushed gravel base that do not meet compaction requirements.
Civil Site Work Specifications 8 of 15
Follow the provisions of the Standard Specifications in constructing the new concrete sidewalks,
pads, and ADA access – matching the dimensions and specifications shown on the Drawings which
constitutes the University standard for sidewalk construction in order to accommodate snow
removal tractors and other light vehicles that will frequently travel over the completed sidewalks.
Place premolded joint filler next to existing concrete to remain, at the corners where curb radii begin
and end, and otherwise at maximum 40 ft. intervals or as directed by the Engineer. In constructing
the new sidewalk, assure a smooth and uniform transition to the existing remaining sidewalk and
that expansion joint material does not protrude above the sidewalk surface in any location.
Furnish and place the reinforcing steel grid in the new reinforced concrete areas as shown on the
Drawings, using wired dobies (not chairs) to support the rebar grid sufficient to assure the
reinforcement remains up in the middle of concrete section and cannot be depressed to the bottom
during construction. Note that reinforcement goes through expansion joints as shown on the
Drawings.
In the areas of repairing the existing concrete slab, drill into the adjacent concrete and epoxy grout-
in rebar dowels tied to each of the similarly oriented steel reinforcement bars in the reinforcing bar
grid to provide appropriate continuity and load distribution capability.
Construct full width, tooled contraction control joints with rounded edges in the sidewalk and pads at
5 foot intervals or as directed by the Engineer. Take special precaution to place additional control
joints at any re-entrant corners or penetrations of the new sidewalk such as light pole or fence post
foundations, valve boxes, utility covers, etc. to address the likely cracking that will occur at such
areas without proper additional jointing.
The University will provide concrete testing including slump and entrained air content from the first
truckload of delivered concrete each day and then again after placement of every 30 yd.³ of
concrete placed that day. One set of three concrete test cylinders will be taken for every 30 yd.³ of
concrete and tested for compressive strength, one at seven days and the remaining two at 28 days.
Copies of concrete quality and strength reports will be provided to the Contractor via e-Builder.
Construct the ADA access at the location shown on the Drawings, incorporating necessary
transition slopes and not exceeding the maximum slopes specified for the ADA access. Measure
and verify the slopes in the field just after concrete placement and screeding to verify compliance
with this requirement.
Furnish and place appropriately sized detectable warning panel(s) in the freshly placed ADA access
to the ADA parking area, strictly following the manufacturer's directions.
Do not add additional water to the concrete mix in the delivery trucks without the express
knowledge and approval of the Engineer. Do not “soup up” the concrete mix to aid in or facilitate
placement and finishing. Similarly, the use of concrete tampers or other similar devices to force
aggregate away from the concrete surface to facilitate finishing is strictly prohibited.
Place new concrete and consolidate with concrete vibrators or tampers operated in a vertical
direction – do not use vibrators to move or “flow” new concrete to areas away from initial placement.
Screed concrete to the required lines and grades after placement and consolidation of the concrete.
Immediately after placement, consolidation, and screeding of the concrete, apply the specified
monomolecular evaporation reducer in accordance with the manufacturer’s directions and float the
Civil Site Work Specifications 9 of 15
constructed sidewalk section with a magnesium float – do not use steel finishing tools and do not
trowel new concrete surfaces. Take particular care in changing directions of bull floats at the front
and back of the slab to avoid inadvertently creating humps or dips in the concrete surface.
Tool the top slab edges and contraction joints to produce smooth, rounded edges.
Apply a light broom finish, perpendicular to the long axis of the sidewalk. Then immediately after
brooming, apply the specified curing compound in accordance with the manufacturer’s directions,
thoroughly covering all surfaces, including the vertical faces of the placed concrete immediately
after form removal.
Provide construction candles and string out construction warning tape to keep pedestrians and
vehicles well away from and out of the newly constructed sidewalk and pad areas.
Furnish a laborer to stay with the newly placed and finished concrete for a minimum of 4 hours after
placement of the curing compound to assure protection of the concrete and curing compound from
vandalism and/or trespass by humans or animals. Promptly remove and replace any newly
constructed concrete that is damaged, at no additional cost to the Owner.
CURB AND GUTTER CONSTRUCTION
General: It is required to construct new curb and gutter along the new sidewalk on the north edge
of the parking lot, and also along the south side of the widened north driveway as shown in the
Drawings. Work includes construction of new concrete curb and gutter which includes grading and
subgrade compaction, furnishing and placing crushed gravel aggregate, constructing reinforced
concrete curb and gutter as detailed on the Drawings, and finishing and curing the concrete in
accordance with this Specification.
Note there are two types of curb on this project: Type A which is a standard curve with gutter
section; and Type B which is a straight vertical curb.
Products: Use ¾” (Type I) crushed aggregate for road base under the curb, ASTM A-615 Grade 60
reinforcing steel, and Class 4000A or 4000AF concrete (low slump). Furnish material properties,
gradations, proctors, and mix designs for the materials proposed for use. Demonstrate aggregate
ASR reduction in the mix design.
Use monomolecular evaporation reducer on freshly placed concrete, Confilm as manufactured by
BASF or E-CON manufactured by L & M Construction Chemicals, Inc., or Owner approved equal.
Use resin and water based curing compound on finished concrete, 1100 Clear as manufactured by
W. R. Meadows, or Owner approved equal. Use WR Meadows polyurethane NS Sealant,
limestone color, for sealing the top of completed expansion joints.
Execution: Construct the gravel portion of the asphalt repair section (or new pavement gravel
section in the new construction area) through and under the curb and gutter area. Furnish, place,
and compact the required 6” crushed gravel base layer under the new curb and gutter section to
96% of maximum density. The University will provide compaction testing.
Follow the provisions of the Standard Specifications in constructing the new concrete curb and
gutter. Match the dimensions shown for the curb and gutter on the Drawings. Match into existing
curb and gutter elevations and profile where tying into existing curb and gutter or other existing
features. Dowel matching connections.
Civil Site Work Specifications 10 of 15
Place premolded joint filler at the beginning and end of the construction area, at the corners where
curb radii begin and end, and where tying into existing curb and gutter.
The University will provide concrete testing including slump and entrained air content from the first
truckload of delivered concrete each day and then again after placement of every 30 yd.³ of
concrete placed that day. One set of three concrete test cylinders will be taken for every 30 yd.³ of
concrete and tested for compressive strength, one at seven days and the remaining two at 28 days.
Copies of concrete quality and strength reports will be provided to the Contractor.
Construct contraction joints in the curb and gutter at 10 foot intervals, tooling the edges of the joints
and taking care to make sure no "humps" associated with constructing the joints are left in the
gutter flowline. Check the flowline and for proper drainage with a string line and level.
After placement, consolidation, and screeding of the concrete; immediately apply the specified
monomolecular evaporation reducer in accordance with the manufacturer’s directions and float the
constructed curb and gutter section with a wood or magnesium float – do not use steel finishing
tools and do not trowel new concrete surfaces.
Apply a light broom finish, parallel to the length of the curb. Then immediately after brooming, apply
the specified curing compound in accordance with the manufacturer’s directions, thoroughly
covering all surfaces including the vertical faces of the curb base (immediately after form removal if
need be).
Furnish a laborer to stay with the newly placed and finished concrete for a minimum of 4 hours after
placement of the curing compound to assure protection of the curb and gutter and curing compound
from vandalism and/or trespass by humans or animals. Promptly remove and replace, at no
additional cost to the Owner, any newly constructed concrete that is damaged.
REPLACE CONCRETE STAIRS
General: It is required to reconstruct the stairway on the main west entrance to the building so that
the stairway will have hydronic snowmelt capability. This will include reconstructing the existing
stairway, a short piece of landing to the west, and the landing to the east going back to the building
entrance. A unique feature of this work is that there is an existing steam tunnel beneath the walk
and stairway and thus constructing the new concrete will require the installation of deck pans
across the top of the tunnel with some shoring beneath to support the construction loads.
Work includes demolition of the existing walk and landings, installation of shoring, and construction
of the reinforced concrete landings and stairway – including installation of the hydronic heating
system as described in the mechanical specifications.
Products: Use concrete and reinforcement specifications as set forth in the “Concrete
Sidewalk/Pad Construction and Repair” specification. Use conventional lumber or other approved
materials for the temporary construction shoring system.
Use 16 gauge galvanized concrete deck pans, corrugated or dovetail style to support the concrete
placement above the steam tunnel. Secure deck pans to angle irons with tack welding or self-
tapping stainless steel screws as per manufacturer’s recommendations.
Provide galvanized A36 3” x 3” x ¼” steel angle iron to support the deck pans at the existing
concrete walls. Secure with 5/8” stainless steel bolts drilled and anchored into the existing concrete
Civil Site Work Specifications 11 of 15
walls.
Furnish the hydronic heating system and appurtenances as per the mechanical specifications.
Execution: Carefully remove the existing railing on each side of stairway and salvage for
replacement and the new stairway. Wire brush the base areas of the rail posts to remove rust and
deteriorated paint. Sand with 200 grit to prepare the surface and then paint with two coats of paint
to match existing prior to reinstallation of the railings in the new stairway construction.
Demolish the existing concrete stairs and landing areas in accordance with the specifications for
concrete demolition set forth in the “Demolition” section of the “Site Work” specification. Demolition
is to include removal of the existing deck pans. Remove any demolition material that falls into the
tunnel beneath, and dispose of all demolition material at an approved excess materials site.
Install the angle irons at the top interior of the existing tunnel concrete walls in a manner and at the
location to provide support for the edges of the concrete deck pans to be used to support concrete
during construction. Secure the angle irons to the existing concrete walls with 5/8” stainless steel
bolts properly anchored into the existing walls at 12” on center.
Construct shoring along the centerline of the tunnel to support the deck pans at mid-span of the
distance between the adjacent concrete walls of the tunnel. Take precaution to avoid and not
disturb existing steam lines or other utilities in the tunnel in erecting the shoring. A new, closer
access to the steam tunnel is being constructed inside the building as a part of the architectural
improvements to facilitate access to the steam tunnel area.
Place the galvanized that deck pans on the angle irons and across the mid-span shoring to support
concrete during placement. Follow manufacturer’s directions for installing the deck pans, including
appropriate overlap and securing the panels. Secure the ends of the deck pan panels to the newly
installed angle iron supports by tack welding in accordance with industry standards or the use of
stainless steel self-tapping screws per manufacturer’s recommendations.
Place any heat reflecting sheets (see mechanical plans and specifications) on the deck pans and
then place the reinforcing steel in accordance with the Standard Specifications. Reinstall the
handrails. Furnish and place the hydronic heating coils in accordance with the mechanical plans
and specifications.
Then construct the concrete stairs and landings in accordance with the Standard specifications and
additional directions given in the “Concrete Sidewalk/Pad Construction and Repair” specification.
Likewise finish the concrete in accordance with the “Concrete Sidewalk/Pad Construction and
Repair” specification presented earlier in this document.
Remove the temporary construction shoring from the steam tunnel after construction.
ASPHALT REPAIR
General: It is required to repair areas of existing asphalt parking lot removed or disturbed for
construction of improvements as detailed on the Drawings, and to construct pavement in the
widened area of the existing north driveway. Work includes excavation, grading to proper
subgrade, placement of separator fabric and base gravels, and plant mix paving.
Civil Site Work Specifications 12 of 15
Products: Use Type I – moderate survivability non-woven subgrade separation and drainage
geotextile fabric on top of the subgrade, 6” minus material or finer for granular borrow (uncrushed
aggregate) above the fabric, ¾” minus crushed gravel for road base (crushed aggregate) above the
granular borrow, and ½” minus crushed aggregate for plant mix pavement with PG 58-28 asphaltic
concrete above the crushed gravel for parking lot pavement and asphalt repairs (commercial mix).
Furnish material properties, gradations, proctors, and mix designs for the materials proposed for
use.
Execution: Restrict traffic and pedestrian access to the work area.
The Engineer will provide general boundaries, elevation control, and grade stakes where
appropriate such as at grade breaks and critical grade areas. Lay out the work from there,
including determining proper subgrade elevations and grades.
Follow the provisions in applicable sections of the Standard Specifications for excavation, gravel
material furnishing and placement, and paving.
Excavate out the base gravel in repair areas and excavate to the subgrade elevation in the area of
new construction. Remove all excess excavated material as required and properly dispose of it at a
contractor-furnished excess material site.
Shape and compact the subgrade. After Engineer’s field review and acceptance of the subgrade,
furnish and place the geotextile separator fabric assuring proper overlap of joints, full coverage
under base gravels, and lap up the sides of any excavated areas.
Then furnish, place, and compact the pit run material in accordance with the Standard
Specifications, taking care not to disturb or damage the separator fabric. Likewise furnish, place,
and compact the ¾” crushed gravel material and plant mix pavement in accordance with the
Standard Specifications.
Compact granular materials to 96% of maximum density and plant mix pavement to 92% of
maximum theoretical density as established by a Marshall Mix design (or equivalent). Use a
straight edge or string line to assure uniform grade and no humps or “bird baths” in the finished
asphalt pavement surface.
The University will provide the compaction testing. Re-compact and re-test any areas not meeting
compaction specifications until acceptable results are obtained and do so without additional cost to
the Owner.
Layout and painting of the parking area striping will be furnished by the University.
SEWER SERVICE LINE
General: It is required to connect to the existing 8” buried sanitary sewer pipeline on the site and
extend a new 4” sewer service line over to grease trap and silt separator vaults to be installed at the
north side of the existing building. Work includes making the connection; and then providing
excavation, installation, and backfill of the new sewer service line.
Products: Use a 4" InsertaTee fitting for making the connection to the existing 8" PVC gravity
sewer pipeline. Use ASTM D-3034 SDR 35 PVC sewer pipeline and associated fittings for the
Civil Site Work Specifications 13 of 15
sewer service line from the point of connection to over to the grease and silt trap vaults. The vaults
are specified and furnished under the mechanical plans and specifications.
Use a traffic rated cleanout at the bend on the sewer service line, Zurn or approved equal, with
countersunk operator on the metal, traffic-rated cleanout plug.
Execution: Call Digline to have the location of the existing sanitary sewer main marked. There is
an existing manhole approximately 50 ft. south of the point of connection that will assist in
determining alignment and elevation of the existing sewer main. Then determine a pipeline route
that will bring the new sewer service line from the grease trap and silt separator to a point of
connection with the existing 8" gravity PVC sewer line as shown on the Drawings.
Perform exploratory excavation to determine the location and condition of the existing sewer line at
the point of connection. Carefully excavate to expose the sewer line and such additional space as
is required to properly make the connection and begin installing the new sewer service line.
Install the InsertaTee connector in strict accordance with the manufacturer's directions. When
drilling, use a cutting grease recommended by the drill manufacturer. Take precaution to recover
the pipe coupon upon drilling the hole for the sewer service connection fitting.
Perform excavation and backfill, and install the sewer service line over to the grease and silt
structures in accordance with the Standard Specifications. Install with at least 5 ft. of cover over the
pipeline. Plan for the potential of 10 yd.³ of rock excavation and removal in the sewer service line
trench excavation, and include the cost thereof in the costs allocated for the sewer service line
installation.
At the grease and silt structures, make an appropriate watertight connection to their outlet piping in
accordance with the Standard Specifications. Install the cleanout indicated on the Drawings at the
45° fitting in the sewer service line in accordance with industry standards, and assure proper
vertical positioning of the cleanout cap in the repaired asphalt surface. Take reference
measurements to the cleanout location to two permanent landmarks (building corners, etc.) and
report the information on the as-constructed drawings of the sewer service line installation.
STORM DRAIN IMPROVEMENTS
General: it is required to construct a new catch basin and curb inlet for the new curb and gutter
along the north sidewalk, and remove an adjacent existing drain inlet and replace it with a concrete
manhole. Together these two work items constitute the “Storm Drain Improvements” shown on the
Drawings.
Work includes excavation and backfill, furnishing and installing the catch basin and manhole with
associated materials, connecting the new catch basin to the new manhole, and connecting existing
storm drain pipelines the new manhole as detailed on the Drawings.
Products: use the following materials for the storm drainage systems:
• ASTM D-3034 SDR 35 PVC pipe and fittings for storm drain
• ASTM C-858 precast reinforced concrete boxes for catch basins
• ASTM C-478 precast reinforced concrete manhole
• Flexible watertight pipe to catch basin and manhole boot style connections, Press-Seal PSX
or Kor-N-Seal 106
Civil Site Work Specifications 14 of 15
• Heavy duty cast iron frame, grate, and curb style inlet on catch basin, Neenah R-3067-L (only)
Execution: begin by conducting exploratory excavation around the existing drain inlet structure to
determine pipeline type and size, and confirm pipeline elevations so that the new manhole structure
that will replace it and the new catch basin structure can be constructed accordingly. This work will
need to be accomplished prior to constructing the new catch basin and manhole structures so that
they can be built to the proper elevation (note the manhole has a flat cover and will be very
shallow).
When the precast structures are available, carefully excavate around the existing drain inlet
structure to expose it and a sufficient length of presently connecting piping to make proper
connection. Cut the existing piping as close to the existing drain inlet as possible and then remove
the existing drain inlet structure.
Install the new catch basin in the proper location (Engineer will provide offset stakes) assuring the
subgrade is thoroughly and properly compacted to support the structure in its final position.
Likewise install the new manhole, taking extra precaution to assure the top of the structure will be in
the proper position to accommodate the new sidewalk to be built above it and having the ring and
cover installed flush with the new sidewalk grade.
Construct piping connections between the new catch basin and new manhole, and also from the
existing storm drain pipes to the new manhole at the required elevation and grade. Follow
manufacturer’s recommendations for the boot connections, using proper torque to assure a
watertight connection.
Furnish and place the required catch basin inlet grate, adjusting it to proper grade to coincide with
the curb and gutter (with grate 0.10 ft. below normal gutter line) by using shims under the grate
frame and installing solid concrete grout to fill all voids between the top of the catch basin structure
and the grate frame. Similarly furnish and place the manhole ring and cover on top of the manhole
lid, using shims under the frame to adjust the top of the manhole cover to the elevation and slope of
the new sidewalk to be constructed.
Backfill and thoroughly compact around the new catch basin and manhole structures. Proper
compaction is critical to prevent future settling around these structures that will undoubtedly occur
without proper attention to backfill and compaction. Compact to 96% of optimum density for the
backfill material. The University will provide testing for the compaction.
Finish the backfill at the required elevation to accommodate the crushed gravel materials under the
new curb, gutter, and sidewalk.
CHAIN LINK FENCING
General: It is required to construct new 6’ high chain link fencing and gates around the north
parking area as shown on the Drawings. The fence will be 6’ high with privacy slats and powder
coated rails, posts, and fittings. Work includes furnishing and installing the fencing materials, post
foundations, and double swing traffic gates in the locations shown on the Drawings.
Products: Use 2 inch mesh ASTM A-392 fencing fabric of 9 gauge wire, galvanized after weaving,
7 gauge zinc coated tension wire at the bottom, 9 gauge aluminum tie wire, galvanized truss rods
and tension bars; Schedule 40 galvanized steel (Class 1) fence posts, 2-3/8” line posts, 2-7/8”
corner and end posts, 4” gate posts, and 1-5/8” top rail; all with end caps.
Civil Site Work Specifications 15 of 15
The posts, rails, and fittings are to be powder coated in a color to be selected by the Owner. The
fence mesh is to be galvanized (not colored).
Use Class 3000 or 3000F concrete for the 3’ deep x 12” diameter fence post foundations (3.5’ deep
x 12” diameter for the gate and end posts).
Use knuckle configuration for mesh selvage at top and bottom. Mesh grounding is not required.
Furnish with full height PVC privacy slats throughout, color by Owner. Provide locking gate latches,
drop bar, and receiver for double swing drive gates. Furnish gate stops for securing the gates when
in an open position.
Execution: the Engineer will stake out the corners of the fencing. Pull offsets as required to locate
the fence in the proper position while still having appropriate survey control. The fence is to be
placed in the southerly 6” of the new concrete sidewalk to be constructed – so the fence location
and alignment are critical.
Grade and smooth the area along the fence alignment to produce a uniform grade, consistent with
what will be the finished grade along the fence line. Install the fence and gate posts in concrete
foundations as detailed on the Drawings. With wind loads against a chain-link fence with privacy
slats, adequate foundation is a critical item for appropriate construction and long service life.
Furnish and install the fencing materials and system in accordance with the Standard
Specifications, industry-standard practice, and manufacturer’s recommendations. Brace all
corners, ends, and gates. Tie the new fencing to the northwest corner of the existing fenced-in
enclosure at the northwest corner of the building.
Install lockable gate latches, drop rods, and receivers in an appropriate location and manner to
properly secure the closed gates. Likewise, furnish and install gate stops to secure gate panels
when they are in the open position.
-- End of Civil Site Work Specifications –
F
S
T
S
T
S
N/
S
N/
S
N/
S
N/S
N/S
N/R
N/S
N/R
N/R
N/
S
CAM
CAM
CAM
CA
M
CAM
CAM
CA
M
CA
M
CA
M
CAM
CA
M
CAM
CAM
CA
M
CAM
CA
M
F
F
F
F
F
DC
DC
DC
F
F
F
FF
F
F
CRCR
C
R
F
F
F
CR
F
F F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
J
J
J
F
CR
DC
F
CR
UP
RE
F
.
REF.
S
S
S
S
S
S
EE E
E
E
E
E
SD
SD
SD
SD SD SD
SD
SDSDSD
SS
SS
AUXILARY SERVICE BUILDING
SS SS SS
02.12
03.03
03.0403.0403.04
03.05
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
26
27
29
30
32
33
25 28 31 34
35
36
37
38
39
40
42
43
44
45
46
47
41
48
49
(ELECTRIC CHARGING
STATION)
(ELECTRIC CHARGING
STATION)
SS
9' - 0"
37
'
-
0
"
57
'
-
0
"
9'
-
0
"
20' - 0"
AUTOMOTIVE SHOP PARKING
32.01
ADA VAN
STALL
VEHICLE EXIT
VEHICLE EXIT
32.12
32.12
GRADING TO BE
REVISED PER FUTURE
SURVEY. TBD
GRADING TO BE
REVISED PER FUTURE
SURVEY. TBD
05.05
11.01
11.05
05.0105.01
32.02
32.02
03.01
32.03
POSSIBLE STORM
DRAIN. TBD
26' - 8"
32.04
32.04
E E
E
SD
SD
8'
-
6
"
17' - 0"
6"
2'
-
0
"
28
'
-
0
"
03.05
EXISTING SHED
EXISTING
SHED
26.02
26
'
-
8
"
24' - 0"
26.02
26.02
26.02
26.02
26.02
26.02
26.0226.02
26.02
26.02
26.02
03.03
05.11
EQ
EQ
1'
-
9
"
02.46
05.12
05.0505.05
194' - 11"
9' - 0"
AS101
A3
32.05
32.05
29' - 4"
GRADING TO BE
REVISED PER FUTURE
SURVEY. TBD
32.07
32.07
32.08
32.09
32.10
32.10
32.1132.11
TYP.
32.11
32.11
TYP.
32.11 TYP.TYP.
5' - 2 3/8" F.V.
4'
-
4
"
F
.
V
.
8' - 2" F.V.
15' - 4" F.V.
24
'
-
0
"
C L E A R
8'
-
0
"
2
2
SITE LEGEND
ADA ACCESSIBLE ROUTE
ADA ACCESSIBLE EXIT
SD
SS
E
SD
SS
E
STORM DRAIN
SANITARY SEWER
ELECTRICAL
EXISTING STORM DRAIN
EXISTING SANITARY SEWER
EXISTING ELECTRICAL
FIELD VERIFY
150' - 11"10' - 0"
3'
-
6
"
03.0305.1226.02 02.4702.47AE521
B4
3 6 0 w e s t a s p e n a v e n u e
s a l t l a k e c i t y , u t a h 8 4 1 0 1
8 0 1 5 3 2 4 4 2 2
sheet:
title:
revisions :
p r o j e c t # :
d a t e :
UNLESS A PROFESSIONAL SEAL WITH SIGNATURE AND
DATE IS AFFIXED, THIS DOCUMENT IS PRELIMINARY AND IS
NOT INTENDED FOR CONSTRUCTION, RECORDING
PURPOSES, OR IMPLEMENTATION
THE DESIGNS SHOWN AND DESCRIBED HEREIN INCLUDING
ALL TECHNICAL DRAWINGS, GRAPHIC REPRESENTATIONS &
MODELS THEREOF, ARE PROPRIETARY & CAN NOT BE
COPIED, DUPLICATED, OR COMMERCIALLY EXPLOITED IN
WHOLE OR IN PART WITHOUT THE SOLE AND EXPRESS
WRITTEN PERMISSION FROM METHOD STUDIO INC.
project:
E
D
C
B
A
E
D
C
B
A
1 2 3 4 5 6
1 2 3 4 5 6
b y u i d a h o p r o j e c t # : 12005
AS101
Architectural
Site Plan
20.0220
october 27, 2020
525 South Center Street
Rexburg, ID 83440
BYUI
Engineering
Technology
Center (ETC)
100% construction
documents
1/16" = 1'-0"A2 Site Plan
KEYED NOTES
02.12 REMOVE LANDSCAPING, FILL WITH CONCRETE AND PROVIDE CURB CUT FOR ADA ACCESSIBILITY, RE:
SITE PLAN / CIVIL DRAWINGS
02.46 PROTECT EXISTING BOLLARD TO REMAIN. IF BOLLARD NEED TO BE REMOVED TO PLACE NEW FOOTING
AND FOUNDATION, SALVAGE BOLLARD AND RE-INSTALL IN SAME LOCATION.
02.47 EXISTING RETAINING WALL AND STRUCTURE TO BE PROTECTED DURING CONSTRUCTION.
03.01 BACKFILL EXISTING LOADING BAY RECESSES AND TOP WITH CONCRETE
03.03 NEW SIDEWALK, RE: CIVIL
03.04 NEW HEATED SIDEWALK AND STAIRS. THIS STAIR IS OVER AN EXISTING STEAM TUNNEL AND WILL NEED
FURTHER INVESTIGATION AND COORDINATION DURING DEMOLITION AND CONSTRUCTION, RE:
MECHANICAL, PLUMBING, CIVIL AND ELECTRICAL.
03.05 NEW SAND AND GREASE SEPARATORS
05.01 NEW LANDING, STAIRS AND GUARDRAIL AND RAILING (POWDER COATED - COLOR TO BE SELECTED BY
OWNER AND ARCHITECT.)
05.05 NEW CHAIN LINK FENCE GATE WITH PRIVACEY SLATS
05.11 NEW 6" STEEL BOLLARD, RE: CIVIL
05.12 NEW POWDER COATED GUARDRAIL, COLOR TO BE SELECTED BY OWNER AND ARCHITECT. RE;
ELEVATIONS, DETAILS AND STRUCTURAL.
11.01 DUMPSTER LOCATION
11.05 CONCRETE WASH OUT. RE: INTERIOR FURNISHINGS AND EQUIPMENT PLANS AND SCHEDULES
26.02 LIGHT FIXTURE, RE: ELECTRICAL
32.01 ACCESSIBLE CURB CUT WITH TRUNCATED DOME
32.02 PATCH PAVEMENT, RE: CIVIL
32.03 NEW 6" CURB. PAINT RADIUS OF NEW CONCRETE CURB.
32.04 EXISTING TREE TO BE PROTECTED DURING CONSTRUCTION. TRIMMING MAY BE REQUIRED FOR NEW
CANOPY. OWNER WILL PROVIDE TRIMMING.
32.05 NEW PAINTED STRIPING FOR WALKWAY AND/OR ADA PARKING STALL ACCESS.
32.07 NEW 4" SANITARY SEWER SERVICE TO CONNECT TO EXISTING 8" SEWER, RE: CIVIL
32.08 CONVERT EXISTING CATCH BASIN INTO A MANHOLE, RE: CIVIL
32.09 NEW CATCH BASIN, RE: CIVIL
32.10 NEW CURB AND GUTTER, RE: CIVIL
32.11 NEW PAINTED STRIPING
32.12 NEW 6'-0" POWDER COATED POSTS WITH GALVANIZED CHAIN LINK FENCE AND VINYL PRIVACY SLATS.
COLOR TO BE BLACK OR TAN. CONFIRM COLOR WITH OWNER AND ARCHITECT DURING SUBMITTAL
PROCESS (PRIOR TO PURCHASE OR INSTALLATION).
GENERAL NOTES - SITE PLAN
1 REFER TO CIVIL AND STRUCTURAL PLANS FOR CONTROLLING ELEVATIONS OF SITE
ELEMENTS TO INCLUDE BUT NOT LIMITED TO HARDSCAPE, STAIRS, RAMPS AND
PLANTER WALLS
2 CONTRACTOR TO PROVIDE NECESSARY SIGNAGE FOR PEDESTRIAN ACCESS AND
ROUTE AROUND CONSTRUCTION SITE AND CONSTRUCTION FENCE A MINIMUM OF
6'-0" IN HEIGHT
1/16" = 1'-0"A3 Guardrail On Existing Retaining Wall
2 Addendum #2 11/9/2020
2
2
2
3
3
4
4
5
5
6
6
7
7
BB
CC
1
1
8
8
AA
DD
EE
F1
F1
03.01
F2
F2
F2
120' - 4 1/8"
20
'
-
8
"
4' - 7 5/8"18' - 8 3/8"4' - 8"
11
'
-
5
3
/
4
"
26
'
-
8
"
38
'
-
1
3
/
4
"
7'
-
4
"
2'
-
4
"
6'
-
4
"
7'
-
4
"
8'
-
8
"
7'
-
4
"
11' - 0"
03.01
03.01
17
'
-
0
"
1'
-
4
"
AL
I
G
N
100' - 0"
100' - 0"
100' - 0"
100' - 0"
100' - 0"
6 1/8"
4'
-
9
"
1'
-
2
"
D6
AE521
D6
AE521
99' - 10"
15' - 0" 12' - 6"2' - 10"
25
'
-
7
1
/
2
"
F1
D5
AE521
99' - 10"
F1
6" 6' - 3"
4'
-
2
"
3'
-
5
"
3'
-
8
"
2'
-
9
"
3'
-
8
"
3'
-
5
"
4'
-
2
"
03.09
03.10
03.10
03.12 03.12 03.12
NEW CONCRETE IN THIS AREA. SEE DEMOLITION
PLANS, STRUCTURAL, MECHANICAL AND
PLUMBING.
NOTE THAT SOME OF THE NEW CONCRETE
IS OVER AN EXISTING TUNNEL. SEE
SHEET AE100 AND STRUCTURAL
NEW HATCH LOCATION SEE
FLOOR PLANS AND DETAILS
F1
6' - 6 7/8"8' - 6 1/2"
100' - 7"
100' - 0"
100' - 0"
2
NEW FLOOR, SEE FLOOR TAG FOR TYPE
SEE SHEET FOR FLOOR ASSEMBLIES
FLOOR LEGEND
AE501
NEW FLOOR, RECESS 2" FOR TILE TO SLOPE TO DRAINS
SEE STRUCTURAL FOR CLARIFICATION
3 6 0 w e s t a s p e n a v e n u e
s a l t l a k e c i t y , u t a h 8 4 1 0 1
8 0 1 5 3 2 4 4 2 2
sheet:
title:
revisions :
p r o j e c t # :
d a t e :
UNLESS A PROFESSIONAL SEAL WITH SIGNATURE AND
DATE IS AFFIXED, THIS DOCUMENT IS PRELIMINARY AND IS
NOT INTENDED FOR CONSTRUCTION, RECORDING
PURPOSES, OR IMPLEMENTATION
THE DESIGNS SHOWN AND DESCRIBED HEREIN INCLUDING
ALL TECHNICAL DRAWINGS, GRAPHIC REPRESENTATIONS &
MODELS THEREOF, ARE PROPRIETARY & CAN NOT BE
COPIED, DUPLICATED, OR COMMERCIALLY EXPLOITED IN
WHOLE OR IN PART WITHOUT THE SOLE AND EXPRESS
WRITTEN PERMISSION FROM METHOD STUDIO INC.
project:
E
D
C
B
A
E
D
C
B
A
1 2 3 4 5 6
1 2 3 4 5 6
b y u i d a h o p r o j e c t # : 12005
AE111
Slab Edge
Plan
20.0220
october 27, 2020
525 South Center Street
Rexburg, ID 83440
BYUI
Engineering
Technology
Center (ETC)
100% construction
documents
GENERAL NOTES - SLAB EDGE
1 COORDINATE SLAB EDGE PLANS WITH STRUCTURAL DRAWINGS
2 COORDINATE SLAB EDGE PLANS WITH MECHANICAL DRAWINGS FOR
HOUSEKEEPING PADS, SIZE, AND EXACT LOCATION
3 COORDINATE SLAB EDGE PLANS WITH WALL TYPES FOR ACOUSTIC ISOLATION
TREATMENTS
4 SLAB EDGE SHOWS MAIN AREAS OF CONCRETE SLAB ON GRADE, IT DOES NOT
SHOW ALL LOCATIONS FOR PATCH AND REPAIR - COORDINATE THESE WITH
MECHAINCAL, ELECTRICAL, PLUMBING AND STRUCTURAL DRAWINGS
KEYED NOTES
03.01 BACKFILL EXISTING LOADING BAY RECESSES AND TOP WITH CONCRETE
03.09 CONCRETE STEP. VERIFY HEIGHT WITH FUTURE SURVEY AND CIVIL DRAWINGS. RE: STRUCTURAL
03.10 RECESSED SLAB AREA, RE: STRUCTURAL
03.12 SLAB TO ROLL OVER CONCRETE AT DOORS.
1/8" = 1'-0"A1 Slab Edge Plan - Level 1
1 Addendum #1 11/5/20
2 Addendum #2 11/9/2020
2x NAILER
SKYLIGHT, INSTALL PER MANUF. USE VELUX
DYNAMIC DOME AS BASIS OF DESIGN
RIGID INSULATION
PREFAB ALUMINUM CURB, INSTALL PER MANUF
2X4 AT SKYLIGHT OPENING, RE: STRUCTURAL
R1 8"
COUNTER FLASHING
RETURN ROOFING
MEMBRANE UP WALL
TERMINATION BAR
6"
3'
-
6
"
3"
2" SQUARE STEEL PIPE SLEEVE
W/ BOTTOM; PAINT
STEEL BEAM,
RE: STRUCTURAL
STEEL ANGLE, RE:
STRUCTURAL
1/4" CONT. WELD AROUND
PIPE SLEEVE TO STEEL ANGLE
1/4" CONT. WELD VERTICAL RAIL TO PIPE
SLEEVE
1/2" SQUARE STEEL PIPE,
VERTICALS @ 4'-0" O.C.
MAX SPACING; PAINT
1 1/2" DIA. STEEL PIPE; PAINT
Top of Lower Wall
114' -0"
R1
ES6a
STEEL ROOF JOIST,
RE: STRUCTURAL
FLUID APPLIED AIR
AND WATER
RESISTIVE BARRIER,
VAPOR PERMEABLE
BARRIER
RUN ROOF
MEMBRANE UP
UNDER PARAPET CAP
8
A
ES6a
FLUID APPLIED AIR AND WATER
RESISTIVE BARRIER, VAPOR
PERMEABLE BARRIER
ES6a
PM8
FLUID APPLIED AIR AND WATER RESISTIVE
BARRIER, VAPOR PERMEABLE BARRIER
RETURN BRICK
BACK TO CMU WALL
1" TYP.
11" MIN.
7"
M
A
X
CONCRETE FILLED STAIR PANS, TYP
SUPPORT ANGLE WELDED
TO STRINGER AND TREAD
STRINGER, RE: STRUCTURAL
CONCRETE ON METAL DECK -
RE: STRUCT
STEEL ANGLE -RE: STRUCT
STEEL BEAM -RE: STRUCT
STRINGER
NOTCH STRINGER AROUND
FLOOR PLATE
WELD STRINGER TO FACE OF
EDGE ANGLE, TYP
CONT. WELDED RISER AND
STAIR NOSING TO TOP OF EDGE
ANGLE: GRIND SMOOTH, TYP
THICKENED SLAB,
RE; STRUCTURAL
EMBEDED PLATE,
RE: STRUCTURAL
SUPPORT ANGLE WELDED
TO STRINGER AND BOLTED
TO FLOOR
3'
-
6
"
3"
6"
A5
AE521
5' - 0"
TYPICAL; GRIND ALL WELDS
SMOOTH, PRIME AND PAINT ALL
RAIL SYSTEMS (PNT-04)
1 1/2" SQUARE STEEL PIPE HANDRAIL,
GRIND ALL WELDS SMOOTH. PRIME
AND PAINT (PNT-04)
1/2" SQUARE STEEL PIPE
HANDRAIL, GRIND ALL WELDS
SMOOTH. PRIME AND PAINT
(PNT-04)
2" SQUARE STEEL PIPE SLEEVE
W/ BOTTOM; PRIME AND PAINT
(PNT-04)
TYP.
4" MAX
3'
-
6
"
3"
5' - 0" MAX
TYP.
4" MAX TYPICAL; GRIND ALL WELDS
SMOOTH, PRIME AND PAINT ALL
RAIL SYSTEMS (PNT-04)
1 1/2" SQUARE STEEL PIPE
HANDRAIL, GRIND ALL WELDS
SMOOTH. PRIME AND PAINT
INTERIOR RAILINGS (PNT-04)
1/2" SQUARE STEEL PIPE
HANDRAIL, GRIND ALL WELDS
SMOOTH. PRIME AND PAINT
INTERIOR RAILINGS (PNT-04)
SEE STRUCTURAL DETAIL C2/SE-521
FOR POST CONNECTION AT EXTERIOR
APPLICATIONS
FOR EXTERIOR APPLICATIONS,
POWDER COAT -COLOR TO BE
SELECTED BY ARCHITECT AND OWNER
STEEL STRINGER,
RE: STRUCTURAL
METAL PAN CONCRETE
STAIR TREAD
1/4" CONT. WELD TO STAIR
STRINGER
1 1/2" DIA. STEEL PIPE; PAINT
3"
3/4" x 1/2" STEEL BAR
BALUSTER @ 4" MAX. O.C.
WELD TOP AND BOTTOM TO
STEEL PIPES GRIND ALL
WELDS SMOOTH. PRIME AND
PAINT AS SPECIFIED
1 1/4" SQUARE GALVANIZED
STEEL PIPE, TOP AND BOTTOM
RAIL GRIND ALL WELDS
SMOOTH.
1 1/2" SQUARE STEEL PIPE; PAINT
3'
-
6
"
3" x 2" x 1/4" STEEL BASE, SECURE W/
(4) 3-3/4" x 1/2" DIA. DOUBLE WEDGE
ANCHORS. PRIME AND PAINT AS
SPECIFIED.
3/4" x 1/2" STEEL BAR BALUSTER @ 4"
MAX. O.C. WELD TOP AND BOTTOM TO
STEEL PIPES GRIND ALL WELDS SMOOTH.
PRIME AND PAINT AS SPECIFIED
1 1/4" SQUARE SCHEDULE 40 STEEL
PIPE HANDRAIL. PLUG ENDS AND
RETURN TO WALL, LEAVING 1/4" GAP
BETWEEN WALL AND FINISH END OF
RAIL. GRIND WELDS SMOOTH,
PRIME AND PAINT PNT-5 AS
SPECIFIED IN FINISH SCHEDULE.
3
"
3"
1
/
2
"
1
/
2
"
1/2" 1/2"
EQ
EQ
EQ EQ
2x NAILER
SKYLIGHT, INSTALL PER MANUF. USE
VELUX DYNAMIC DOME AS BASIS OF
DESIGN
1"
6"
RIGID INSULATION
FINISH INTERIOR FACE W/ 5/8" GYP BD,
RE: FINISH SCHEDULE / RCP
RE: RCP FOR CEILING FINISH
3 5/8" METAL STUD WALL FRAMING
5/8" GYP BD, RE: FINISH SCHEDULE / RCP
PREFAB ALUMINUM CURB, INSTALL PER MANUF
2X4 AT SKYLIGHT OPENING, RE:
STRUCTURAL
3'
-
6
"
3"
6"
A5
AE521
6' - 0"
INDUSTRIAL HINGE, TYP.
GRIND ALL WELDS SMOOTH
TYPICAL; GRIND ALL WELDS
SMOOTH, PRIME AND PAINT ALL
RAIL SYSTEMS (PNT-04)
1 1/2" SQUARE STEEL PIPE
HANDRAIL, GRIND ALL WELDS
SMOOTH. PRIME AND PAINT (PNT-04)
1/2" SQUARE STEEL PIPE HANDRAIL,
GRIND ALL WELDS SMOOTH. PRIME
AND PAINT (PNT-04)
2" SQUARE STEEL PIPE SLEEVE
W/ BOTTOM; PRIME AND PAINT
(PNT-04)
LATCH ON MEZZANINE
SIDE OF GATE
TYP.
4" MAX
EQ EQ
SEPARATE POST FOR GATE
SUPPORT ON EACH SIDE, RE:
STRUCTURAL
Level 1
100' -0"
2'
-
0
"
TWO FEET OF R-7.5 MINIMUM
CONTINUOUS RIGID
INSULATION AT FOUNDATION
PERIMETER
CONC SLAB ON GRADE, RE: STRUCT
NEW FOUNDATION, RE: STRUCT
1/2" FIBRE EXPANSION JOINT FILLER
SCHEDULED WALL, RE: PLANS
SCHEDULED WALL, RE: PLANS
CHAMFERED SILL EDGE/REVEAL, TYP
3/
4
"
3/
4
"
3/4"
8"6"
DAMP PROOFING
SITE ASPHALT, RE: CIVIL
FOUNDATION WALL,
RE: STRUCTURAL
FLASHING SET IN CONTINUOUS SEALANT
MORTAR DEFLECTION SYSTEM
SELF-ADHERED MEMBRANE FLASHING
2
CONCRETE COLUMN
5/8" PAINT-GRADE
PLYWOOD SHEATHING,
RE: FINISH SCHEDULE
3 5/8" METAL
STUD FRAMING
EQ
EQ
EQ EQ
1'
-
1
0
"
1' - 10"
ALUMINUM FRAME
W/ ANCHOR FLANGE
LOCK STRIKE
DETENTION SECURITY LOCK
DIAMOND STEEL
PLATE COVER
CONC FLOOR
SUPPORT PLATE
WELDED TO FRAME
FLOOR HATCH,
INSTALL PER MANUF
CONT NEOPRENE
BUMPER AT PERIMETER Level 1
100' -0"
2'
-
0
"
3" RIGID INSULATION AT
FOUNDATION PERIMETER
CONC SLAB ON GRADE, RE: STRUCT
1/2" FIBRE EXPANSION JOINT FILLER
SCHEDULED WALL, RE: PLANS
CHAMFERED SILL
EDGE/REVEAL, TYP
3/4"
8"
DIMPLED DRAINAGE BOARD
FLUID APPLIED WATERPROOFING
CONTINUOUS OVER FULL HEIGHT
OF WALL
FOUNDATION WALL,
RE: STRUCTURAL
2"X2"X1/4" ANG.
CONTINUOUS WELD
TO TS POST
2"x2"x1/4" TS WELDED TO
2"x8"x1/4" PLATE EPOXY /
BOLTED TO SLAB W/ 1/2"
DIA. ANCHORS, TYP.
2"X2"X1/4" ANG.
BOLTED TO STUD
2x FRAMING
T.S. POST CONDITION STUD SIDE-MOUNT CONDITION
1
"
NOTCH END OF ANGLE
2' - 0"
1'
-
0
"
3"
1/4" STEEL PLATE (MIN) -42" HIGH
3 6 0 w e s t a s p e n a v e n u e
s a l t l a k e c i t y , u t a h 8 4 1 0 1
8 0 1 5 3 2 4 4 2 2
sheet:
title:
revisions :
p r o j e c t # :
d a t e :
UNLESS A PROFESSIONAL SEAL WITH SIGNATURE AND
DATE IS AFFIXED, THIS DOCUMENT IS PRELIMINARY AND IS
NOT INTENDED FOR CONSTRUCTION, RECORDING
PURPOSES, OR IMPLEMENTATION
THE DESIGNS SHOWN AND DESCRIBED HEREIN INCLUDING
ALL TECHNICAL DRAWINGS, GRAPHIC REPRESENTATIONS &
MODELS THEREOF, ARE PROPRIETARY & CAN NOT BE
COPIED, DUPLICATED, OR COMMERCIALLY EXPLOITED IN
WHOLE OR IN PART WITHOUT THE SOLE AND EXPRESS
WRITTEN PERMISSION FROM METHOD STUDIO INC.
project:
E
D
C
B
A
E
D
C
B
A
1 2 3 4 5 6
1 2 3 4 5 6
b y u i d a h o p r o j e c t # : 12005
AE521
General
Construction
Details
20.0220
october 27, 2020
525 South Center Street
Rexburg, ID 83440
BYUI
Engineering
Technology
Center (ETC)
100% construction
documents
3" = 1'-0"B6 Skylight Detail - Shop
1 1/2" = 1'-0"A4 Roof Connection - Upper
1 1/2" = 1'-0"A5 Removeable Guard Rail @ Mezzanine
1 1/2" = 1'-0"A3 Roof Connection - Lower
1 1/2" = 1'-0"A1 Plan Detail
1 1/2" = 1'-0"A2 Plan Detail
1 1/2" = 1'-0"C1 Stair Tread Detail
1 1/2" = 1'-0"C2 Top of Stair Detail
1 1/2" = 1'-0"C3 Bottom of Stair Detail
1" = 1'-0"B2 Mezzanine Guardrail
1" = 1'-0"B4 Guardrail
1 1/2" = 1'-0"A6 Stair Handrail Section
3" = 1'-0"C4 Handrail to Wall Detail
3" = 1'-0"B5 Skylight Detail - Seating Area
1" = 1'-0"B1 Mezzanine Guardrail Gate
1 1/2" = 1'-0"D6 Slab Edge at Engines Lab
1 1/2" = 1'-0"D3 Typical Column Wrap / Framing
1 1/2" = 1'-0"D4 Floor Access Hatch
1 1/2" = 1'-0"D5 Slab Edge at Exterior Storage
1" = 1'-0"D1 Hidden Support Bracket
1 1/2" = 1'-0"E1 Steel Downspout Protector
1 Addendum #1 11/5/20
2 Addendum #2 11/9/2020
November 10, 2020
BYUI Engineering Technology Center (ETC) Addendum #2
SE-101
1. Four-inch step in the slab was modified to be 7” in height. Step occurs between grids 5 and 6 at
east side of building.
Thanks,
Donald Lee Barfuss
INDICATES NOTES ARE KEYED ON PLAN.1.SEE ARCHITECTURAL DRAWINGS FOR SLOPES AND RECESSES IN FLOOR SLABS 2.FOR CONCRETE WALL REINFORCING, SEE CONCRETE WALL SCHEDULE ON SHEET SE -002.3.FOR CONCRETE PIER/COLUMN REINFORCING, SEE CONCRETE PIER SCHEDULE ON SHEET SE -002.4.FOR CORNER, INTERSECTION, AND END BARS IN CONCRETE WALLS SEE DETAILS A1 AND A2/SE -501.5.FOR CONTROL JOINTS IN SLABS ON GRADE SEE DETAIL B4/SE -501.GENERAL SHEET NOTES INDICATES NOTES ARE KEYED ON PLAN.1 DRILL AND EPOXY TO EXISTING. 5" MINIMUM EMBEDMENT.2 DEMOLISH SLAB TO INSTALL NEW FRENCH DRAIN, SEE SHEE T M301 FOR PIPE RUNNING PARALLEL TO FRENCH DRAIN. REPAIR AS REQ'D. 3 INFILL MASONRY WALL, SEE DETAIL A1/SE -511 4 INFILL DOCK LEVELER WITH 6" REINFORCED CONCRETE WALLS AND SLAB WITH #4 AT 18"O.C. EACH WAY. FILL WITH GRAVEL.5 DEMOLISH SLAB TO INSTALL NEW FOUNDATION FOR MEZANINE. REPLACE AS REQ'D.6 NOT USED.7 MODIFY FLOOR VENTS, COORDINATE WITH MECHANICAL FILL EXISTNIG VENT OPENINGS WITH 1/4" PLATE THAT EXTENDS 3" PAST OPENING AND SCREW INTO CONCRETE WITH 1/4"Ø SIMPSON CONCRETE SCREWS AT 4" O.C.CUT NEW OPENINGS WITH DRILLED HOLES AT CORNERS AND CUTTING BETWEEN HOLES. DO NOT OVERCUT CORNERS.8 PROVIDE NEW 6" CONCRETE SLAB ON 4" FREE DRAINING GRAVEL. REINFORCE WITH #4 AT 18"O.C. EACH WAY,CENTER OF SLAB 10 NEW MW -8A REINFORCED MASONRY WALL ON 12"X2' FOOTING.11 LOWER SLAB TO BE SAME ELEVATION AS MAIN BUILDING.NEW 6" SLAB ON GRADE.12. FREEZER SLAB: REMOVE EXISTING TOP SLAB AND FOAM. FILL WITH GRAVEL AS REQUIRED. PROVIDE 5" SLAB ON GRADE REINFORCED WITH #4 AT 24"O.C. EACH WAY IN CENTER OF SLAB.13.FOR NEW GUARDRAIL AT RETAINING WALL, SEE DETAIL D4/SE -521.14.ALL STEEL ANGLES AND PLATES ETC. IN THE TUNNEL AREA SHALL BE GALV. AFTER FABRICATION.15.TOP OF FOUNDATION CALLOUTS ARE APPROX. MATCH EXISTING FOUNDATION TO AVOID ROCK BLASTING.KEYED SHEET NOTES LEGEND INDICATES CONCRETE FILLED STEEL COLUMN, FILL WITH 4000psi SELF CONSOLIDATING CONCRETE.H SS ?? CF INDICATES CONCRETE SLAB ON GRADE, SEE PLAN NOTES.INDICATES CHANGE IN SLAB ELEVATION AND DEPTH FROM F.S.E.INDICATES CONCRETE WALL, SEE SCHEDULE.INDICATES RECESSED SLAB, SEE ARCH.CW -??INDICATES MASONRY WALL, SEE SCHEDULE.MW -??INDICATES MASONRY BEAM, SEE SCHEDULE.MB -??INDICATES CONCRETE PIER (CP), SEE SCHEDULESCP-?INDICATES STEEL HSS (HSS) OR STEEL WIDE FLANGE (W). COLUMN AND BASE PLATE, SEE SCHEDULESBP-?BP -?H SS??W ?X??INDICATES DIFFERENT SLAB THICKNESSINDICATES RECESS IN CONCRETE FOUNDATION WALLCW-??INDICATES NON -BEARING MASONRY WALL.MW -??S S INDICATES STEP IN WALLF-????'-??"INDICATES CONCRETE FOOTING TYPE AND TOP OF FOOTING ELEVATION.INDICATES CONCRETE FOOTING & FOUNDATION WALL, SEE SCHEDULES FOR SIZE AND REINFORCING.INDICATES ISOLATION JOINT IN SLAB ON GRADE. SEE DETAIL ?"INDICATESMASONRY PIER (MP) OR COLUMN (MC), SEE SCHEDULESM?-?INDICATES CONCRETE ON METAL DECK
1
2
3
4
5
6
7
8
A B C D E
C
W
-
8
A
9
6
'
-
0
"
F
-
3
C
3
3
3
3
3
3
3
3
2
4
7
5
3
3
3
3
8
10
11
11
7
12
10
0
'
-
0"
F -2C
D6
SE
-
5
1
1
C
W
-
1
4
A
96' -0"F-3C
CW
-
1
4
A
96
'
-
0"
F -3C
C
W
-
8
A
9
6
'
-
0
"
F
-
3
C
11
8
1
0
0
'
-
0
"
F
-
2
C
1
0
0
'
-
0
"
F
-
2
C
10
0
'
-
0"
F -2C
1
0
0
'
-
0
"
F
-
2
C
10
0
'
-
0"
F -2C
10
0
'
-
0"
F -2C
OP
E
N
AD
D
(
4
)
#
6
B
O
T
T
O
M
IN
2
4
"
W
I
D
E
S
T
R
I
P
H SS 8 X4X1/4 BP -1 H SS 8 X4X1/4 B P -1 C P -2 C P -2
F-
3
C P -2 F-
3
10
0
'
-
0"
F -2C
C3
SE
-
5
0
1
C3
SE
-
5
0
1
13
C2
SE
-
5
0
1
10
0
'
-
0"
F -2C
1
0
0
'
-
0
"
F
-
2
C
CW
-
8
A
C
W
-
8
A
T.
W
=
1
0
2
'
-0"
T.
W
=
1
0
0
'
-0"
T.
W
=
1
0
2
'
-0"
T.
W
=
1
0
0
'
-0"
T.
P
.
=
10
0
'
-
0
"
T.
P
.
=
10
0
'
-
0
"
1
C
W
-
8
A
9
3
'
-
6
"
F
-
3
C
MA
T
C
H
E
X
I
S
T
I
N
G
EL
E
V
A
T
I
O
N
C1
SE
-
5
0
1
C1
SE
-
5
0
1
OP
P
.
MA
T
C
H
E
X
I
S
T
I
N
G
EL
E
V
A
T
I
O
N
L
6
X
4
X
1
/
2
(2
)
5
X
3
½
X
3
/
8
A
N
G
L
E
S
LL
B
A
C
K
T
O
B
A
C
K
D5
SE
-
5
0
1
C4
SE
-
5
0
1
C5
SE
-
5
0
1
D2
SE
-
5
0
1
D1
SE
-
5
0
1
D2
SE
-
5
0
1
D3
SE
-
5
0
1
RE
M
O
V
E
T
H
I
S
A
R
E
A
OF
S
L
A
B
O
N
G
R
A
D
E
RE
M
O
V
E
T
H
I
S
A
R
E
A
O
F
T
U
N
N
E
L
S
L
A
B
(
6
"
S
L
A
B
,
TY
P
.
)
R
E
P
L
A
C
E
W
I
T
H
6
"
T
O
T
A
L
T
H
I
C
K
N
E
S
S
CO
N
C
R
E
T
E
S
L
A
B
R
E
I
N
F
O
R
C
E
D
W
I
T
H
#
4
A
T
1
8
"
O.
C
.
B
O
T
H
W
A
Y
S
,
S
E
E
S
C
H
E
D
U
L
E
.
L
6
X
4
X
5
/
1
6
D4
SE
-
5
0
1
C5
SE
-
5
0
1
SI
M
.
D1
SE
-
5
0
1
SI
M
.
L6
X
4
X
5
/
1
6
14
E1
SE
-
5
0
1
TY
P
.
E1
SE
-
5
0
1
TY
P
.
2"
6 -W2
-18
RE
M
O
V
E
T
H
I
S
A
R
E
A
O
F
T
U
N
N
E
L
S
L
A
B
(
6
"
S
L
A
B
,
TY
P
.
)
R
E
P
L
A
C
E
W
I
T
H
8
"
T
O
T
A
L
T
H
I
C
K
N
E
S
S
CO
N
C
R
E
T
E
S
L
A
B
R
E
I
N
F
O
R
C
E
D
W
I
T
H
#
4
A
T
1
8
"
O.
C
.
B
O
T
H
W
A
Y
S
,
S
E
E
S
C
H
E
D
U
L
E
.
8 -W2
-18
6 -W2
-20
A3
SE
-
5
0
1
E2
SE
-
5
0
1
E2
SE
-
5
0
1
E2
SE
-
5
0
1
F.
S
.
E
=
1
0
0
'
-0"
F.
S
.
E
=
1
0
0
'
-7"
15
15
15
15
2
3 6 0 w e s t a s p e n a v e n u e s a l t l a k e c i t y , u t a h 8 4 1 0 1 8 0 1 5 3 2 4 4 2 2 sheet:title:revisions :p r o j e c t # :d a t e :UNLESS A PROFESSIONAL SEAL WITH SIGNATURE AND DATE IS AFFIXED, THIS DOCUMENT IS PRELIMINARY AND I S NOT INTENDED FOR CONSTRUCTION, RECORDING PURPOSES, OR IMPLEMENTATION THE DESIGNS SHOWN AND DESCRIBED HEREIN INCLUDING ALL TECHNICAL DRAWINGS, GRAPHIC REPRESENTATIONS & MODELS THEREOF, ARE PROPRIETARY & CAN NOT BE COPIED, DUPLICATED, OR COMMERCIALLY EXPLOITED IN WHOLE OR IN PART WITHOUT THE SOLE AND EXPRESS WRITTEN PERMISSION FROM METHOD STUDIO INC.project:
E D C B A
E D C B A
1
2
3
4
5
6
1
2
3
4
5
6 byu idaho project # : 12006 SE -101FOUNDATIONPLANOct. 27, 2020525 South Center Street Rexburg, ID 83440BYUIEngineeringTechnologyCenter (ETC)100% Construction Documents
1/
8
"
=
1
'
-
0
"
SE
-
1
0
1
A1
FO
O
T
I
N
G
A
N
D
F
O
U
N
D
A
T
I
O
N
P
L
A
N
1
A
d
d
e
n
d
u
m
1
1
1
/
5
/
2
0
2
0
2
A
d
d
e
n
d
u
m
2
1
1
/
1
0
/
2
0
2
0
11/10/2020