HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 3 - The Grove at Thomson FarmsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Thompson Farms
20001
Stillwater Equity Partners
Kevin Virgin Construction 11-02-2020
Cold
6:30 AM
26
8:30 AM
I arrived on site at approximately 6:45 AM. I observed that the contractor had placed a blue moisture
barrier as well as rebar in the footing areas. I tested the first truck and sixth trucks and found them to be
within project specifications.
Digitally signed by Jacob P Christensen
Date: 2020.11.05 08:15:07 -07'00'
D. Aust
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: