Loading...
HomeMy WebLinkAboutCOMCHECK - 08-00153 - 236 Jill - New SFRREScheck Software Ver , -0800153 Com lian ? Name - Title Signature Date Project Notes: Henderson Subd Block 7, Lot 2 Project Title: HE2137 'Davenport C" Data filename: C:1Documents and Settings\John\Desktop\Kartchner Homes\ResCheck Jobs\Idaho\HE2b7 Page 2 of 4 Davenport.rck Report date: 03/24/08 lio Date: 03/24/08 Ceilings: ❑ Ceiling 1: Flat Ceiling or Scissor Truss, R-48.0 cavity insulation Comments: Above -Grade Walls: ❑ Wall 1: Wood Frame, 16" o.c., R-19.0 cavity insulation Comments: ❑ Wall 2 Basment: Wood Frame, 16" o.c., R-19.0 cavity insulation Comments: —_ Basement Walls: ❑ Basement Wall 1: Solid Concrete or Masonry, 4.0' ht / 3.0' bg / 4.0' insul, R-13.0 continuous insulation Comments: — Windows: ❑ Window 1: Vinyl Frame:Double Pane, U -factor: 0.350 For windows without labeled U -factors, describe features: #Panes Frame Type Thermal Break? Yes No Comments: ❑ Window 2: Wood Frame:Double Pane, U -factor: 0.350 For windows without labeled U -factors, describe features: #Panes Frame Type Thermal Break? Yes No Comments: Note: Up to 15 sq.ft. of glazed fenestration per dwelling is exempt from U -factor and SHGC requirements. Doors: ❑ Door 1: Solid, U -factor: 0.200 Comments: ❑ Door 2: Glass, U -factor: 0.350 Comments: Crawl Space Walls: ❑ Crawl 1: Solid Concrete or Masonry, 4.0' ht / 3.0' bg / 4.0' ext. insul / 0.0' inside bg depth, R-13.0 continuous insulation Comments: Exposed earth in unwanted crawl space foundations is covered with a continuous vapor retarder. All joints of the vapor retarder are overlapped by 6 inches and are sealed or taped with edges extending at least 6 inches up the stem wall and securely attached. Heating and Cooling Equipment: ❑ Furnace 1: Forced Hot Air: 90 AFUE or higher Make and Model Number: Air Leakage: ❑ Joints, penetrations, and all other such openings in the building envelope that are sources of air leakage are sealed. ❑ Recessed lights are either 1) Type IC rated with enclosures sealed/gasketed against leaks to the ceiling, or 2) Type IC rated and ASTM E283 labeled, or 3) installed inside an air -tight assembly with a 0.5" clearance from combustible materials and a 3" clearance from insulation. ........... Project Title: HE2B7 "Davenport C" Data filename: C:\Documents and Settings\John\Desktop\Kartchner Homes\ResCheck Jobs\Idaho\HE2b7 Page 3 of 4 Davenport.rck Report date: 03/24/08 Vapor Retarder: Vapor retarder is installed on the warm -in -winter side of all non -vented framed ceilings, walls, and floors; or it has been determined that moisture or its freezing will not damage the materials; or other approved means to avoid condensation are provided. Comments: Materials Identification: ® Materials and equipment are identified so that compliance can be determined. Manufacturer manuals for all installed heating and cooling equipment and service water heating equipment have been provided. [] Insulation R -values, glazing U -factors, and heating equipment efficiency are clearly marked on the building plans or specifications. Insulation is installed according to manufacturer's instructions, in substantial contact with the surface being insulated, and in a manner that achieves the rated R -value without compressing the insulation. Duct Insulation: Ducts in unconditioned spaces are insulated to R-8. ❑ Ducts in floor trusses are insulated to R-6. Duct Construction: L] Air handlers, filter boxes, and duct connections to flanges of air distribution system equipment or sheet metal fittings are sealed and mechanically fastened. [] All joints, seams, and connections are made substantially airtight with tapes, gasketing, mastics (adhesives) or other approved closure systems. Tapes and mastics are rated UL 181A or UL 181 B. Building framing cavities are not used as supply ducts. [] Automatic or gravity dampers are installed on all outdoor air intakes and exhausts. p Additional requirements for tape sealing and metal duct crimping are included by an inspection for compliance with the International Mechanical Code. Temperature Controls: Thermostats exist for each separate HVAC system. A manual or automatic means to partially restrict or shut off the heating and/or cooling input to each zone or floor is provided. Heating and Cooling Equipment Sizing: [] Additional requirements for equipment sizing are included by an inspection for compliance with the International Mechanical Code. Circulating Hot Water Systems: LI Circulating hot water pipes are insulated to R-2. [] Circulating hot water systems include an automatic or accessible manual switch to turn off the circulating pump when the system is not in use. Heating and Cooling Piping Insulation: L] HVAC piping conveying fluids above 105 degrees F or chilled fluids below 55 degrees F are insulated to R-2. Certificate: L] A permanent certificate is provided on or in the electrical distribution panel listing the predominant insulation R -values; window U -factors; type and efficiency of space -conditioning and water heating equipment. NOTES TO FIELD: (Building Department Use Only) Project Title: HE2B7 "Davenport C., Data filename: C:1Documents and Settings\JohnlDesktop\Kartchner Homes\ResCheck JObslldaho\HE2b Davenport.rck Page 4 of 4 Report date: 03/24/08