BUILDING INSPECTION SEQUENCE
Type of Inspections: For on-site construction, from time to time the building official, upon
notification from the permit holder or his agent, shall make or cause to be made any necessary
inspections and shall either approve that portion of the construction as completed or shall notify
the permit holder or his agent wherein the same fails to comply with this code.
1. LAYOUT: Lot corners staked, staking in glace for building, prior to excavation:
2. FOOTING: Commonly made after poles or piers are set or trenches or basement
areas are excavated. Forms and horizontal reinforcing tied in place,
vertical reinforcing cut and on job site or tied in place.
3. FOUNDATION INSPECTION:
The foundation inspection shall islciā¬.rded exca,'°ations for thickened slabs
intended for the support of bearing walls, partitions, structural supports, or
equipment and special requirements for wood foundations. All forms and
reinforcing steel, etc., shall be in place.
4. PLUMBING, MECHANICAL AND ELECTRICAL:
Rough inspection: Commonly made prior to covering or concealment,
before fixtures are set, and prior to framing inspection.
5. TRUSS INSPECTION:
Inspections of trusses.
6. FRAME INSPECTION:
Commonly made after the roof, all framing, firestopping, draftstopping and
bracing are in place and after the plumbing, mechanical and electrical
rough inspections are approved. !Electrical inspection performed through
State of Idaho Electrical Bureau)
7. LATH AND/OR WALLBOARD INSPECTION:
Commonly made after all lathing and/or wallboard interior is in place, but
before any plaster is applied, or before wallboard joints and fasteners are
taped and finished.
8. FINAL PLUMBING AND HEATING INSPECTION:
All systems in place, fixtures set, ready for occupancy
9. SIDEWALK INSPECTIONS:
After forms are set, prior to placing concrete.
10. FINAL INSPECTION:
Commonly made after the building is completed and ready for occupancy .
11. OCCUPANCY PERMIT:
Issued when, on final inspection, building is ready to occupy.
12. OTHER INSPECTIONS:
In addition to the called inspections above, the building department may
make or require any other inspections to ascertain compliance with this
code and other laws enforced by the building department.
INSPECTION CARD
The permit holder or his agent shall post the inspection record on the job site in an accessible
and conspicuous place to allow the building official to make the required entries. The record
shall be maintained by the permit holder until the final inspection has been made and approved.
I have read the above and will comply in my requests for inspections by giving 24 HOUR
NOTICE prior for inspections to be made.