HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 4 - 19-00727 - Spori Annex - Ceramic & Sculpture LabsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Spori Annex and Parking Lot
20014A
BYU - Idaho
Bingham Mechanical 09/17/2020
Clear
9:00 AM
54
12:00 PM
I arrived on site and began my observations of the condensate line going into the building. I observed the
contractor place the gilsulate and consolidate it in place with a mechanical vibrator until firm under foot. I
observed the contractor level off the gilsulate and place a piece of blue board on top then cover it with
plastic. I notified the contractor of my observations prior to leaving.
Digitally signed by Jacob P Christensen
Date: 2020.09.20 14:42:42 -06'00'8129697
J. Christensen
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: