HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 24 - 19-00727 - Spori Annex - Ceramic & Sculpture LabsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Spori Annex and Parking Lot
20014A
BYU - Idaho
Thompson Excavation 06/23/2020
Sunny
7:30 AM
85
6:00 PM
I arrived on site at approximately 8:00 AM. I observed the contractor backfilling and compacting the storm
drain trench on 2nd South. The means and methods of compaction were a double drum smooth roller, and
a jumping jack for small areas and around the pipe. I observed the contractor make 4-6 vibrating passes. I
also observed that a fire hose was used to add moisture. At approximately 1:00 PM I observed the
contractor begin grading and compacting the pad inside of the building in preparation for concrete. I
observed the same means and methods in the building that I observed in the storm drain trench. I
observed that work done was in general conformance with project documents.
Eli Jenkins Digitally signed by Eli Jenkins
Date: 2020.06.24 08:46:51
-06'00'8129697
D. Aust
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: