HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 11 - 19-00727 - Spori Annex - Ceramic & Sculpture LabsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Spori Annex and Parking Lot
20014A
BYU - Idaho
Elite Steel 07/09/2020
Clear
1:00 PM
75
5:00 PM
I arrived on site and began my observations of the steel structure. I observed that the contractor had
completed the majority of the erection and welding work. I observed that the full penetration welds had
been completed and were in tolerance of the project documents. I observed that the joists were in place
and welded to the beams with fillet welds on each side. The contractor had also placed the majority of the
bridging. I observed that the contractor had drilled holes for one of the base plates at grid line F:4. I notified
the contractor to let us know when they would be epoxying these in place so we could observe this
process. No deficiencies were noted.
Digitally signed by Jacob P Christensen
Date: 2020.07.31 15:00:09 -06'00'8129697
J. Christensen
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: