Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:By:
Neil Stoddard
20060
Jacobson Concrete 09/15/2020
Sunny
12:30 PM
85
2:15 PM
I arrived at the site and began my inspections. I checked the re-bar and confirmed that everything looked
correct according to spec, and then waited for the truck to arrive. the first truck showed up at about 1:40
PM and then I began my testing. The truck passed easily with no problem, and then I observed that
throughout the duration of the pour, the contractor stayed withing general conformance to the project
documents.
Digitally signed by Jacob Christensen
Date: 2020.09.21 10:22:40 -06'00'
Concrete Placement Concrete Reinforcement Concrete Reinforcement
L. Steiner
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: