HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 6 - The Grove at Thomson FarmsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Thompson Farms
20001
Stillwater Equity Partners
Kevin Virgin Construction 07/02/2020
cloudy
6:30 am
48
9:00 am
I arrived on site and began my observation of the concrete reinforcement and concrete placement of the
slab between grid points A-B. I observed the concrete reinforcement was in general conformance to project
documents. I observed the concrete placement was in general conformance to the project documents. I
observed the duration of the pour.
Eli Jenkins Digitally signed by Eli Jenkins
Date: 2020.07.06 08:05:07
-06'00'8129697
concrete reinforcement vibrating concrete
F. Pelton
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: