Permit Status of (Open) as of Report Date: 06/29/2020 9:29 am
Permit Details Permit Number: 10-00068
South Gate Apts - Bldg #4 - 401-412
370 W 7th S
New Multi-Family Residence
Permit Issued Date: 12/15/2014
Permit Inspection Statistics
20Total Inspections Completed:
18Total Inspections Passed:
Inspection Pass Rate: 90.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building
04/19/2010PassBret StoddardResidential Footing Inspection
Approved to place concrete for the footings-entire building. 4/30 int footings okInspector Comments:
04/20/2010PassPLL ADMINFoundation Inspection
As per Jon Berry.
Southeast and west walls and rebar look good.
Inspector Comments:
06/16/2010PassPLL ADMINResidential Sheetrock/Drywall Inspection
As per Jon Berry.
Drywall screw inspection south side building 4 looks good.
Inspector Comments:
06/17/2010PassPLL ADMINResidential Insulation Inspection
As per Jon Berry
6/11/10 - Wall insulation looks good in south units. OK to cover.
6/17/10 - Units 407,409 and 411 insulation OK to cover. Building 4 insulation
completed ext. walls and int. firewalls all units.
Inspector Comments:
06/21/2010FailPLL ADMINResidential Framing/Structure Inspection
As per Jon Berry.
5/27/10 - MEP not completed.
Inspector Comments:
06/21/2010PassPLL ADMINResidential Framing/Structure Inspection
As per Jon BerryInspector Comments:
09/17/2010PassPLL ADMINSidewalk Inspection
As per Jon BerryInspector Comments:
09/20/2010PassPLL ADMINResidential Building Final
As per Jon Berry.Inspector Comments:
Page 1 of 3
(Continued)
Permit Details Permit Number: 10-00068
South Gate Apts - Bldg #4 - 401-412
370 W 7th S
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 06/29/2020 9:29 am
Permit
Inspection
Summary
Electrical
06/16/2010PassBret StoddardResidential Electrical Service Inspection
Approved to be energized for permanent power-no separate ticket was written
for this service inspection-inspected this service on the rough-in of the north side.
Inspector Comments:
07/02/2010PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
6/10/10 - Approved for cover in the south side only-(2,4,6,8,10,12).
6/16/10 - Approved for cover in all the north units except the last two on the east
side(1,3,5,7). Approved for cover in the last two units on the north side-inspected
the service on this inspection also.
7/2/10 - Approved for cover in the doghouse on this building-no ticket
written-inspected this on the final of the first building.
Inspector Comments:
08/18/2010FailBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Need to install wet location wire in the raceways for the A/C units, call for a
re-inspect when ready.
Inspector Comments:
08/25/2010PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Approved for a final and a C.O.Inspector Comments:
Fire
09/20/2010PassPLL ADMINFire Department Final Inspection
As per Jon Berry.
Hydro and visual OK 200# 4 hrs open units looked good units 406-412 were
drywalled and couldn't inspect.
Inspector Comments:
Mechanical
06/11/2010PassPLL ADMINHVAC Rough-in
As per Jon Berry.
6/10/10 - HVAC rough in south side units looked good.
6/11/10 - HVAC rough completed on building 4. Note: fire dampers not installed.
Inspector Comments:
07/16/2010PassPLL ADMINHVAC Final Inspection
As per Jon Berry
HVAC final completed.
Inspector Comments:
Page 2 of 3
(Continued)
Permit Details Permit Number: 10-00068
South Gate Apts - Bldg #4 - 401-412
370 W 7th S
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 06/29/2020 9:29 am
Permit
Inspection
Summary
Plumbing
04/19/2010PassPLL ADMINPlumbing Water
As per Brad Johnson.Inspector Comments:
04/28/2010PassPLL ADMINPlumbing Underground Inspection
As per Brad Johnson.Inspector Comments:
06/04/2010PassPLL ADMINPlumbing Sewer
As per Brad Johnson.Inspector Comments:
06/04/2010PassSAUREY AMANDAPlumbing Rough-in
Rough plumbing inspection looks good, test held, nailplates needed to be added
on some locations and some strapping.
Inspector Comments:
09/20/2010PassPLL ADMINPlumbing Final Inspection
As per Brad Johnson.Inspector Comments:
Page 3 of 3