Permit Status of (Open) as of Report Date: 06/23/2020 1:16 pm
Permit Details Permit Number: 10-00152
Nauvoo House II Bldg #6
175 W 5th S
New Multi-Family Residence
Permit Issued Date: 05/06/2010
Permit Inspection Statistics
14Total Inspections Completed:
12Total Inspections Passed:
Inspection Pass Rate: 85.71%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building
06/02/2010PassJohn BerryCommercial Footing Inspection
Footing & Rebar look goodInspector Comments:
06/03/2010PassJohn BerryCommercial Footing Inspection
Footing & Rebar look goodInspector Comments:
06/09/2010PassQuinton OwensFoundation Inspection
Foundation Rebar okInspector Comments:
09/14/2010PassJohn BerryCommercial Framing/Structure Inspection
Framing inspection Looks good Note: Bath exhaust fans need fire caulking around
plastic back draft damper 1st and 2nd floors only
Inspector Comments:
09/17/2010PassJohn BerryCommercial Insulation Inspection
Insulation OKInspector Comments:
09/20/2010PassJohn BerryResidential Sheetrock/Drywall Inspection
1st Layer Looks Good OK to cover Add Blocking at dropped ceilingInspector Comments:
01/26/2011FailJohn BerryCommercial Building Final
Install ZAIDBC Min Fire Ext in Each unitInspector Comments:
Electrical
10/18/2010PassBret StoddardCOM & MFR Electrical Service Inspection
Approved to be energized for permanent powerInspector Comments:
01/20/2011PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final & CO #6Inspector Comments:
Page 1 of 2
(Continued)
Permit Details Permit Number: 10-00152
Nauvoo House II Bldg #6
175 W 5th S
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 06/23/2020 1:16 pm
Permit
Inspection
Summary
Fire
09/15/2010PassJohn BerryFire Sprinkler Hydro
226#@2pm 226 4:40 OK GoodInspector Comments:
01/28/2011N/APLL ADMINFire Alarm Final Inspection
NOT SIGNED
Notes - Flow Switches working (2). Tower Switches working(4) - Heads need to
be cleaned throughout - Pressure test completed by Brad previously(200psi/2hr) -
Need 16' Head coverage literature. (ok)
- Extra Heads on site *Clearance around riser 2' *ok per Brad. *Static 50 psi
both. Residual 45psi
Inspector Comments:
Mechanical
09/10/2010PassQuinton OwensHVAC Rough-in
Mech Rough in OK *Hydronic heating lines test inspected by BradInspector Comments:
12/16/2010PassQuinton OwensHVAC Final Inspection
42 psi @ 5:05, 42 psi @ 5:30Inspector Comments:
01/19/2011PassJohn BerryHVAC Final Inspection
HVAC Final Apts Completed Except BoilerInspector Comments:
Page 2 of 2