Permit Status of (Open) as of Report Date: 06/23/2020 1:15 pm
Permit Details Permit Number: 10-00153
Nauvoo House II Bldg #7
175 W 5th S
New Multi-Family Residence
Permit Issued Date: 05/06/2010
Permit Inspection Statistics
10Total Inspections Completed:
8Total Inspections Passed:
Inspection Pass Rate: 80.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building
06/18/2010PassJohn BerryCommercial Footing Inspection
Footing & Rebar for bldg 7 & Floor Rebar for Bldg 6 look goodInspector Comments:
06/24/2010PassJohn BerryFoundation Inspection
Foundation Bldg 7 ok to pourInspector Comments:
01/27/2011FailJohn BerryCommercial Building Final
Install ZAIDBC Fire Ext in each unitInspector Comments:
Electrical
09/24/2010PassBret StoddardCommercial Electrical Rough-in
Approved for cover in #7 except service walls. *Approved for cover in #6 As per
prior inspection(Jack)
Inspector Comments:
10/18/2010PassBret StoddardCOM & MFR Electrical Service Inspection
Approved to be energized for perm powerInspector Comments:
01/20/2011PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final & C.O. #7Inspector Comments:
Fire
10/21/2010PassBrad JohnsonFire Sprinkler Hydro
Fire riser 200 psi test complete: Required flush by Jon BerryInspector Comments:
02/02/2011PassJohn BerryFire Sprinkler Final Inspection
205# @ 1:30 for both 7&8 pressure ok good at 3:30 ADA Unit Horn Strobes OK'd
good & Alarm Bell
Inspector Comments:
Mechanical
09/16/2010FailJohn BerryHVAC Rough-in
Several units - bath exh fans req fire caulck 1/4" at box-pipe connectionInspector Comments:
01/19/2011PassJohn BerryHVAC Final Inspection
HVAC Final Apts Completed Except BoilerInspector Comments: