HomeMy WebLinkAboutSPECIAL CONCRETE INSPECTION 7 - The Grove at Thomson FarmsProject Name:
Project Number:
Client:
Contractor:Date:
Weather:
Time start:
Temperature:
Time End:
Concrete Reinforcement
Concrete Placment
Epoxy Bolt/ Anchors
Post Tensioned Concrete
Masonry Reinforcement Structural Steel Spray-Applied Fireproofing
Masonry Grout Placement
High Strength Grout
Earthwork Inspection
Welding
High Strength Bolting
Cold Weather Concrete
Roads/ Utilities
Other
Daily Field Diary
Observations, Items, and Locations
Deficiencies:
Reviewed By:Certification #:
Page 1 of 2
NoYes
°F
Description: Description: Description:
4103 E 605 N Suite 1 Rigby, ID 83442 208.970.6237 www.connectengr.com
Inspected By:
Thompson Farms
20001
Stillwater Equity Partners
Kevin Virgin Construction 06/10/2020
Sunny
7:00 AM
80
4:30 PM
I arrived on site at approximately 7:30 AM. I observed that the contractor had prepared the breezeways for
concrete. I observed that the preparations were in general conformance with project documents. I returned
at approximately 2:00 PM and observed that the contractor had prepared the footings and footing walls in
another building. I observed that they were in general conformance with project documents as well.
Eli Jenkins Digitally signed by Eli Jenkins
Date: 2020.06.11 07:20:52
-06'00'8129697
Footing Walls Footings
D. Aust
Page 2 of 2
Description: Description:
Description: Description:
Additional Comments: