HomeMy WebLinkAboutCOST ESTIMATES - 20-00241 - 821 Griffin St - Basement FinishAdamson – 821 Griffin Street Basement Finish Budget/Costs WALLS Sheetrock – 70 sheets 658.70 Greenboard (Bathroom) – 4 sheets 45.88 Joint Compound – 12 5-gal containers 150.00* Joint Tape – 10 rolls (250 ft p/roll) 25.00* Corner Joint Tape – 3 rolls 25.00* Sheetrock screws – Previously owned 0.00 Interior Doors 252.00 Paint 200.00* Walls Sub-Total: 1,356.58 BATHROOM Tub 245.00 Toilet 89.00 Vanity 249.00 Fan 35.00 Valve & fixtures (Shower & Sink) 269.00 Plumbing contracting (set tub, hookup to rough-in) 1200.00* Tile 500.00* Bathroom Sub-Total: 2587.00 ELECTRICAL Cans 74.50 Wire and Boxes 375.00 CAT5 cable for Ethernet runs 59.00 Outlets & Smoke detectors 115.00 Electrical Sub-Total: 623.50 15% Overage/Misc. Estimate 685.00 Estimated Total: $5252.08 * Estimates for items not on hand/bid out yet